Change of Use Permit (Change in Use/Occupancy Inspection) in Pueblo, Colorado

The City of Pueblo's change-of-use process is administered by the Southern Colorado Building Department (SoCoBD) as a Change in Use/Occupancy Inspection — a cursory code-compliance inspection triggered when a new business or tenant occupies an existing commercial space, whether or not construction is involved. The inspection's findings can independently trigger a requirement for full Commercial Plan Review (this file's tenant-improvement-permit entry) at additional cost.

Verified 2026-08-14 · Source

When you need this permit

  • Change in Use/Occupancy Inspection Application Form must be fully completed: address of inspection, name of new business, site contact name/phone/email, name and description of the previous business, and building owner name/phone/email/mailing address
  • If the applicant is not the building owner, a copy of the lease agreement, signed by both parties and showing the property address, is required to process the application
  • The owner or owner's agent must sign to authorize SoCoBD to inspect the property, and acknowledges receipt of the Code Compliance Inspection Disclaimer accompanying the request
  • The inspection is expressly cursory and code-compliance-focused only — SoCoBD's own disclaimer states it cannot discover all violations (much work is concealed in a completed structure) and is not a working-order/systems report; a trade-specific contractor should be hired separately if a working-order report is desired
  • Any life-threatening or serious code violations found must be corrected within a time specified by the inspector; if not corrected in time, utilities may be disconnected to prevent further occupancy of an unsafe structure
  • The completed form is given to the Chief Building Inspector, who schedules the inspection
  • Findings from this inspection may result in a requirement for full Commercial Plan Review at additional cost, separate from this inspection's own fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Change in Use/Occupancy Inspection FeeSoCoBD Change in Use/Occupancy Inspection Application Form (PDF), read directly — flat fee stated on the form itself, paid at the time of application
$110.25

Review timeline

Plan review
Not published — contact the department

How long did your Change of Use Permit (Change in Use/Occupancy Inspection) permit actually take in Pueblo?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Change in Use/Occupancy Inspection

    Cursory code-compliance inspection of the space by SoCoBD; not a structural, working-order, or exhaustive code-violation inspection

See the full Pueblo inspection guide — scheduling & re-inspection fees →

Tips

  • This inspection is deliberately described by SoCoBD as cursory, not exhaustive — it does not guarantee no other code issues exist, and does not evaluate whether building systems are in good working order (hire a trade-specific contractor separately for that).
  • If you are not the building owner (e.g., a new tenant), have your signed lease agreement showing the property address ready before applying.
  • A change of use/occupancy that involves construction, or that the inspection finds requires it, can be routed into full Commercial Plan Review (see this file's tenant-improvement-permit entry) at additional cost beyond this inspection's $110.25 fee.

Frequently asked questions

Pueblo requires a change of use permit (change in use/occupancy inspection) for: Change in Use/Occupancy Inspection Application Form must be fully completed: address of inspection, name of new business, site contact name/phone/email, name and description of the previous business, and building owner name/phone/email/mailing address; If the applicant is not the building owner, a copy of the lease agreement, signed by both parties and showing the property address, is required to process the application; The owner or owner's agent must sign to authorize SoCoBD to inspect the property, and acknowledges receipt of the Code Compliance Inspection Disclaimer accompanying the request; The inspection is expressly cursory and code-compliance-focused only — SoCoBD's own disclaimer states it cannot discover all violations (much work is concealed in a completed structure) and is not a working-order/systems report; a trade-specific contractor should be hired separately if a working-order report is desired; Any life-threatening or serious code violations found must be corrected within a time specified by the inspector; if not corrected in time, utilities may be disconnected to prevent further occupancy of an unsafe structure; The completed form is given to the Chief Building Inspector, who schedules the inspection; Findings from this inspection may result in a requirement for full Commercial Plan Review at additional cost, separate from this inspection's own fee. If your project isn't listed, confirm with Southern Colorado Building Department (SoCoBD) at 719-543-0002 before starting work.

In Pueblo, the published Change in Use/Occupancy Inspection Fee is: $110.25. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Pueblo does not publish a plan-review timeline for this permit. Contact Southern Colorado Building Department (SoCoBD) at 719-543-0002 for current turnaround.

You'll need: Change in Use/Occupancy Inspection Application Form. Depending on your project, Pueblo may also ask for: Signed Lease Agreement. See the required-documents checklist on this page for details on each.

The completed Change in Use/Occupancy Inspection Application Form is given to SoCoBD's Chief Building Inspector, who schedules the inspection. No numeric turnaround time is published.

Apply through Southern Colorado Building Department (SoCoBD) at 830 N Main St, Pueblo, CO 81003. Phone: 719-543-0002, email: permits@socobd.com. Office hours: Front counter open to the public 7:30 a.m.-4:30 p.m., Monday-Friday; online services available 24/7. Field inspectors are generally reachable in the office between 7:30 and 8:30 a.m. Homeowner/Contractor permit applications may also be emailed to permits@socobd.com or faxed to 719-543-0062.. Official information: https://www.socobd.com/.

Pueblo, Colorado has adopted: Colorado has no statewide mandatory building code for most jurisdictions (home-rule authority); each municipality or building authority adopts and amends its own construction codes. The main statewide floors that DO apply everywhere are energy/electric-vehicle/solar-ready requirements under HB22-1362 (Colorado's building energy codes law) and, for accessory dwelling units, HB24-1152 (which addresses local ADU regulation but does not itself set a building code). Applicants should always confirm the specific adopted edition and local amendments with the issuing building department. Source: Colorado Energy Office, Building Energy Codes Toolkit, https://energyoffice.colorado.gov/building-energy-codes-toolkit; Verify Pueblo's own adopted code editions and amendments below — the City of Pueblo does not use a separate 'city code' distinct from the joint department's adopted codes; the Southern Colorado Building Department (SoCoBD, formerly Pueblo Regional Building Department/PRBD) is the single building authority for the City of Pueblo and administers one set of adopted codes for its full service area.; The Southern Colorado Building Department (SOCOBD) was created by an intergovernmental agreement between the City of Pueblo and the Town of Boone to serve as a single building-code authority for both. SOCOBD does not have jurisdiction in unincorporated areas of Pueblo County. Source: SoCoBD 'About' page, https://www.socobd.com/ (aboutprbd.php); 2021 International Building Code (IBC), as amended by Pueblo City Code Title IV, Building Regulations, Chapter 2 (Building and Energy Code amendments). Source: SoCoBD Building & Code Information page, https://www.socobd.com/ (handouts-forms.php) and Pueblo Municode, https://library.municode.com/co/pueblo/codes/code_of_ordinances?nodeId=TITIVBURE_CH2INBUCO_S4-2-2AMIBIE; 2021 International Residential Code (IRC), as amended by Pueblo City Code Title IV, Chapter 6 (Residential Code amendments). Source: https://library.municode.com/co/pueblo/codes/code_of_ordinances?nodeId=TITIVBURE_CH6RECO_S4-6-2AM; 2021 International Plumbing Code (IPC) — note this jurisdiction uses the International Plumbing Code, not the Uniform Plumbing Code — as amended by Pueblo City Code Title IV, Chapter 4 (Plumbing Code amendments). Source: https://library.municode.com/co/pueblo/codes/code_of_ordinances?nodeId=TITIVBURE_CH4PL_S4-4-2AMCOPLCOSE1.2E.ADFO; 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2023 National Electrical Code (NEC), as amended by Pueblo City Code Title IV, Chapter 3 (Electrical/NEC amendments). Source: https://library.municode.com/co/pueblo/codes/code_of_ordinances?nodeId=TITIVBURE_CH3EL_S4-3-2N.AM; 2021 International Energy Conservation Code (IECC), adopted WITHOUT modifications, plus the Colorado Model Electric and Solar Ready Code, both effective 6/30/2026 per SoCoBD notice; the department is NOT adopting the Model Low Energy and Carbon Code (MLECC) at this time. A one-month transition period was allowed; plans/permits submitted on or after 8/1/2026 are subject to the new code, while plans/permits already in process remain on the prior code unless they expire. Source: SoCoBD homepage notice, https://www.socobd.com/ ('New Code Adoption 6/30/2026'), and Colorado Energy Office Building Energy Codes Toolkit, https://energyoffice.colorado.gov/building-energy-codes-toolkit (HB22-1362 statewide energy/electric-vehicle/solar-ready floor); Prior to the 2026 IECC/electric-ready adoption, SoCoBD used 2021 IECC prescriptive insulation values (adopted for the SoCoBD code cycle effective June 29, 2023): Climate Zone 5, Fenestration U-factor 0.32, Skylight U-factor 0.55, Ceiling R-49, Wood Frame Wall R-20 or R-13+5ci, Mass Wall R-13/17, Floor R-30, Basement Wall R-15ci or R-19 or R-13&5ci, Slab R-10ci at 2 ft, Crawl Space Wall R-15ci or R-19 or R-13&5ci. REScheck users may use either the 2018 or 2021 version. Source: SoCoBD Prescriptive Insulation Values handout (PDF), https://socobd.com/pubs/prescriptive.pdf. Local amendments apply — see the Pueblo overview page for the full list.

SoCoBD offers a Change in Use/Occupancy Inspection ($110.25) for exactly this scenario — a cursory code-compliance inspection of the space. If the applicant is not the building owner, a signed lease agreement showing the property address is required, and the inspection's findings can still trigger a requirement for full Commercial Plan Review at additional cost.

Sources & verification

Verified against official sources. Last reviewed 2026-08-14.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pueblo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.