EV Charging Station Permit (Electrical Permit) in Pueblo, Colorado
Required for installation of a Level 2 (or higher) electric vehicle charging station/EVSE within the City of Pueblo, permitted the same way as any other electrical work under the 2023 NEC as amended by Pueblo City Code Title IV, Chapter 3, and issued by the Southern Colorado Building Department (SoCoBD). Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act) designates the City of Pueblo a 'covered municipality' (population over 10,000) and Pueblo County a 'covered county' (population over 20,000), requiring both to have adopted, by 12/31/2025, either the Colorado Energy Office's EV Charger Permitting Model Code, an equivalent locally-adopted objective standard, or a resolution affirming continued use of their existing permitting review process — this file could not independently confirm which of the three compliance options SoCoBD/the City selected.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the new/upgraded circuit and EVSE connection, the same as any other electrical work per Pueblo City Code Title IV, Chapter 3 (2023 NEC as amended)
- Installation must comply with NEC Article 625 (Electric Vehicle Power Transfer System); GFCI protection applies per NEC 625 where the EVSE is cord-and-plug connected
- Apply via the SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax, the same intake channels used for the file's general electrical-permit entry
- If the charger install requires a panel/service upgrade, that scope is included in the same electrical permit application
- No dedicated EV/EVSE fee line item exists in SoCoBD's Fee Table Table C (Residential Electrical Only Permits) -- confirmed by reading the full table, which lists exactly three fixed-fee residential electrical categories (Upgrade/Replace Service, Solar PV Systems, A/C Hook Up) and no others; a standalone EV charger circuit addition with no service upgrade does not match any of the three
- Because a plain EV charger circuit addition is not one of Table C's fixed-fee categories, it falls back to SoCoBD's general valuation-based permit fee (Table B), applied to the contractor's declared job value for the electrical work -- the same mechanism Table C's own instructions specify for any permit type not itemized as a fixed fee
- If the installation instead requires a service/panel upgrade to support the charger, it is billed under Table C's fixed 'Upgrade/Replace Service' fee ($55.13) instead of the valuation-based Table B calculation
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In (if applicable)
Wiring, box placement, and service connections before walls are closed
- 2
Final
EVSE breaker sizing, GFCI protection (where applicable), panel labeling, and NEC Article 625 compliance verified
See the full Pueblo inspection guide — scheduling & re-inspection fees →
Tips
- SoCoBD's published Fee Table has no dedicated EV charger/EVSE line item -- confirmed against the full table, which lists only three fixed-fee residential electrical categories (Upgrade/Replace Service, Solar PV Systems, A/C Hook Up). A plain EVSE circuit addition instead falls back to the general valuation-based Table B fee schedule; only an installation that includes a service/panel upgrade would use the fixed $55.13 Upgrade/Replace Service fee.
- Pueblo is a 'covered municipality' and Pueblo County a 'covered county' under Colorado's HB24-1173, which required an EV charger permitting process decision (model code adoption, an equivalent local standard, or continuing the existing process) by 12/31/2025 with a compliance report due to the Colorado Energy Office by 3/1/2026 — confirm with SoCoBD/the City of Pueblo which option was selected if an expedited/administrative review process is expected.
- Electrical inspectors are available by phone (719-543-0002) 7:30-9:00 a.m. Monday-Friday, the same contact used for the file's general electrical-permit entry.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pueblo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Pueblo
EV Charging Station Permit (Electrical Permit) in other cities
Compare ev charging station permit (electrical permit) fees across Colorado →
Look up this fee in a different city →