Julesburg building inspections
Inspection sequence, scheduling, and re-inspection fees for building permits in Julesburg, Colorado.
Reviewed 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 100 West 2nd Street, Julesburg, CO 80737
- Phone
- 970-474-3344
- julesburg@live.com
- Office hours
- No published office hours specific to permitting were found on the Town's website; general Town Hall contact is 970-474-3344 (fax 970-474-3345). Julesburg is a statutory town with no dedicated 'Building Department' webpage — permitting is administered out of Town Hall by the Building Official (per Municipal Code Section 15.04.030, an office whose appointment now functions through the Town Manager or designee, per Ordinance 23-472's 2023 update naming the Town Manager/designee as inspector for the plumbing and electrical trades specifically).
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour, per 36-inch minimum frost depth (locally amended IBC Section 1809.5)
- 2
Framing
Structural framing complete before cover
- 3
Final Inspection
Completed work approved by the Building Official (Municipal Code Section 15.04.050)
Applies to: Electric Vehicle (EV) Charger / EVSE Permit
- 1
Electrical Inspection
Inspection and testing of the EV charger circuit and wiring for code compliance by the Town's Electrical Inspector, per Section 15.12.110
- 2
Certificate of Satisfactory Inspection
Issued upon completion and compliant inspection before current may be energized, per Section 15.12.120
Applies to: Electrical Permit
- 1
Electrical Inspection
Inspection and testing of wiring/apparatus for code compliance by the Town's Electrical Inspector, per Section 15.12.110
- 2
Certificate of Satisfactory Inspection
Issued upon completion and compliant inspection before current may be energized, per Section 15.12.120
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, venting/combustion air verified by the Building Official
Applies to: Plumbing Permit
- 1
Rough-in Inspection
Plumbing rough-in inspected before concealment, per the Section 15.08.100 fee schedule structure
- 2
Final Certificate of Inspection
Final inspection and certificate issued by the Plumbing Inspector
Applies to: Residential Addition / Remodel Permit
- 1
Framing / Rough-in
Framing and any rough trade work inspected before concealment
- 2
Final Inspection
Completed work approved by the Building Official
Applies to: Rooftop Solar Photovoltaic Permit
- 1
Foundation/Footing (ground-mount) or Framing (rooftop racking)
Structural attachment verified before panels are installed
- 2
Electrical Interconnection (Town Electrical Inspector)
Performed by the Town's own local electrical inspector ('city electrician,' Municipal Code Chapter 15.12), not the Colorado State Electrical Board
Final inspection only: Reroof / Residing Permit
Re-inspection fees
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Julesburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Julesburg building permits
Get alerts for Julesburg
We'll email you when Julesburg's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.