Electric Vehicle (EV) Charger / EVSE Permit in Julesburg, Colorado

Julesburg has no dedicated EV charger/EVSE fee line, application, or standard — the Town's Municipal Code Chapter 15.12 (Electrical Code) and Ordinance No. 23-472 publish no EV-specific provisions, and no fee schedule of any kind is published online for any Julesburg permit type (fees are set case-by-case by the Board of Trustees / Town Hall). EV charger circuit installation is treated as ordinary electrical work, requiring the same written permit obtained through the Town's own electrical licensing and inspection program under Chapter 15.12 (Julesburg does not defer to Colorado DORA's State Electrical Board). Julesburg's population (approximately 1,200) is far below the 10,000-resident municipal threshold that triggers Colorado HB24-1173's requirement to adopt a standardized/expedited EV charging system permitting program, so the Town is not required to have adopted a distinct EV permitting track.

Reviewed 2026-07-20 · Source

When you need this permit

  • Written permit required before any EV charger circuit installation, wiring alteration, or load increase, obtained from the Town's license-issuing clerk (Municipal Code Section 15.12.050) — the same permit used for any other electrical work
  • Contractors/firms must hold a Town of Julesburg electrical license (fee set by the Board of Trustees); individual homeowners performing their own work on their own home are exempt from licensing/bonding but still need the permit
  • All electrical construction/materials/apparatus must conform to the National Electrical Code rules in effect when work is performed (Section 15.12.100) — confirm the currently enforced NEC edition and its EV charging (Article 625) provisions directly with Town Hall
  • Upon completion, the Electrical Inspector must inspect and issue a certificate of satisfactory inspection before current may be turned on (Section 15.12.120)
  • Julesburg's population (approximately 1,200) is well below Colorado HB24-1173's 10,000-resident municipal threshold, so no distinct state-mandated EV charging permit standard applies here

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit / Inspection FeeNo dedicated EV charger/EVSE fee line exists, and no dollar-denominated electrical permit fee schedule of any kind is published online for Julesburg — the Board of Trustees sets fees by resolution rather than in the Municipal Code itself. Confirm the current fee directly with Town Hall (970-474-3344) before budgeting.
Not published; determined by Town Hall at time of application

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger / EVSE Permit permit actually take in Julesburg?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection and testing of the EV charger circuit and wiring for code compliance by the Town's Electrical Inspector, per Section 15.12.110

  2. 2

    Certificate of Satisfactory Inspection

    Issued upon completion and compliant inspection before current may be energized, per Section 15.12.120

See the full Julesburg inspection guide — scheduling & re-inspection fees →

Tips

  • Julesburg does not price EV chargers separately from other electrical work, and in fact publishes no dollar-denominated electrical permit fee schedule at all online — call Town Hall (970-474-3344) directly to get a current fee quote before budgeting.
  • Julesburg runs its own local electrical licensing/permitting/inspection program (Municipal Code Chapter 15.12) rather than deferring to Colorado DORA's State Electrical Board — confirm requirements directly with the Town's Electrical Inspector.
  • As one of this dataset's smallest Colorado jurisdictions, Julesburg is well under the population threshold that would legally require it to adopt a distinct, streamlined EV charging permit process under Colorado HB24-1173.
  • Re-chased 2026-07-20: re-fetched the Town's Municipal Code Chapter 15.12 PDF and ran a fresh targeted web search for a Julesburg electrical/building fee resolution -- found only a December 2025 Board of Trustees minutes document addressing an electric utility RATE increase (not a permit fee), confirming no permit fee schedule of any kind is published online. Since Julesburg runs its own local electrical program rather than deferring to Colorado DORA's State Electrical Board (unlike some other small Colorado towns in this dataset), the DORA state fee-schedule fallback does not apply here either. No citable dollar figure exists; genuinely thin documentation, not an oversight.
  • Re-chased 2026-07-23, new avenues (not previously exhausted): downloaded and full-text-searched all 13 Town of Julesburg Board of Trustees meeting minutes for calendar year 2025 and all 5 minutes published so far for 2026 (townofjulesburg.com/documents/board-of-trustees) for any resolution establishing an electrical/EV-charger permit or inspection fee -- none exists; the only 2026 fee resolution passed (Resolution No. 2026-03, adopted at the March 2026 meeting) sets a $250 Use-by-Special-Review land-use application fee, unrelated to electrical/EV work. Also fetched and searched Municipal Code Title 3 (Revenue and Finance) in full -- it governs sales/use tax only, not permit fees. Also re-confirmed via the operative Ordinance No. 23-472 text itself that the Town's only 2023 electrical-fee change was administrative/licensure, with no EV-specific provision. 2024 Board minutes were sought via Wayback Machine (the live site no longer links a 2024 minutes folder) but the underlying per-meeting PDF documents were never independently archived by Wayback (confirmed via a direct CDX API lookup returning zero snapshots for each PDF's asset URL), so that year's minutes remain unrecoverable through this avenue. No governing EV-charger fee figure exists after this exhaustive re-chase; still confirm with Town Hall (970-474-3344).

Frequently asked questions

Julesburg requires an electric vehicle (ev) charger / evse permit for: Written permit required before any EV charger circuit installation, wiring alteration, or load increase, obtained from the Town's license-issuing clerk (Municipal Code Section 15.12.050) — the same permit used for any other electrical work; Contractors/firms must hold a Town of Julesburg electrical license (fee set by the Board of Trustees); individual homeowners performing their own work on their own home are exempt from licensing/bonding but still need the permit; All electrical construction/materials/apparatus must conform to the National Electrical Code rules in effect when work is performed (Section 15.12.100) — confirm the currently enforced NEC edition and its EV charging (Article 625) provisions directly with Town Hall; Upon completion, the Electrical Inspector must inspect and issue a certificate of satisfactory inspection before current may be turned on (Section 15.12.120); Julesburg's population (approximately 1,200) is well below Colorado HB24-1173's 10,000-resident municipal threshold, so no distinct state-mandated EV charging permit standard applies here. If your project isn't listed, confirm with Town of Julesburg — Town Hall / Building Official (Town Manager or designee) at 970-474-3344 before starting work.

No. Julesburg has no dedicated EV charger/EVSE permit category, and in fact publishes no dollar-denominated electrical fee schedule of any kind online. EV charger installation uses the Town's standard electrical permit process under Municipal Code Chapter 15.12, with the fee determined by Town Hall at the time of application.

Julesburg does not publish a plan-review timeline for this permit. Contact Town of Julesburg — Town Hall / Building Official (Town Manager or designee) at 970-474-3344 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Julesburg requires 2 inspection(s) for an electric vehicle (ev) charger / evse permit, in order: Electrical Inspection, Certificate of Satisfactory Inspection. Schedule each through Town of Julesburg — Town Hall / Building Official (Town Manager or designee) (970-474-3344).

Apply through Town of Julesburg — Town Hall / Building Official (Town Manager or designee) at 100 West 2nd Street, Julesburg, CO 80737. Phone: 970-474-3344, email: julesburg@live.com. Office hours: No published office hours specific to permitting were found on the Town's website; general Town Hall contact is 970-474-3344 (fax 970-474-3345). Julesburg is a statutory town with no dedicated 'Building Department' webpage — permitting is administered out of Town Hall by the Building Official (per Municipal Code Section 15.04.030, an office whose appointment now functions through the Town Manager or designee, per Ordinance 23-472's 2023 update naming the Town Manager/designee as inspector for the plumbing and electrical trades specifically).. Official information: https://www.townofjulesburg.com/.

Julesburg, Colorado has adopted: 2018 International Building Code (IBC), as locally amended — Town of Julesburg Municipal Code Chapter 15.04, adopted by Ordinance No. 23-470 (passed June 5, 2023); 2018 International Residential Code (IRC), as locally amended — same Ordinance No. 23-470; 2018 International Mechanical Code (IMC), as locally amended — same Ordinance No. 23-470; 2018 International Fire Code (IFC), as locally amended — same Ordinance No. 23-470; 2018 International Fuel Gas Code (IFGC), as locally amended — same Ordinance No. 23-470; 2018 International Energy Conservation Code (IECC), as locally amended — same Ordinance No. 23-470; Legacy 1965-edition National Electrical Code base text remains codified at Municipal Code Chapter 15.12 (Ord. 268(3), 1967) and has NOT been superseded by a newer NEC edition adoption ordinance found in this corpus's document chase; Ordinance No. 23-472 (2023) updated ONLY the licensure/permitting administrative sections (15.12.070, 15.12.090) for electrical work, not the substantive wiring-code edition. Confirm the currently enforced NEC edition directly with Town Hall (970-474-3344) before relying on a specific cycle for electrical plan review — this is a genuine open question after full document chasing, not an assumption.; Ordinance No. 23-470 explicitly repeals all conflicting/inconsistent prior Town of Julesburg ordinances and supersedes the original 1967 Basic Building Code (BOCA) and 1965 National Electrical Code base adoption at Chapter 15.04, replacing the substantive building/residential/mechanical/fire/fuel-gas/energy code editions with the 2018 ICC family; the base administrative/licensing chapters for Plumbing (15.08) and Electrical (15.12) remain independently codified from 1967 as amended by Ordinance No. 23-472 (2023).; Frost line: 36 inches below finished grade (IBC Section 1809.5 local amendment, Ordinance No. 23-470).; Ground snow load: 20 psf (Table R301.2, as locally amended, per the adopted Climatic and Geographic Design Criteria table in Ordinance No. 23-470) — figure is somewhat garbled in the source PDF's OCR ('2012fil'), read here as 20 psf; confirm directly with the Building Official before relying on this for structural design.; Wind design speed: 112 mph (Table R301.2, as locally amended).; Ice barrier underlayment required per Section R905.1.2 (2018 IRC as amended): required on roofs with a slope equal to or less than 4:12, consisting of not fewer than two layers of cemented underlayment or a self-adhering polymer-modified bitumen sheet, extending from the lowest roof edge to at least 24 inches inside the exterior wall line — this is a slope-triggered requirement, not a 100%-of-all-roofs rule.; Flood hazard areas established by reference to 'The Flood Plain Information Report: South Platte River for the Town of Julesburg and Sedgwick County, Colorado' (dated May 18, 2021) plus the accompanying FEMA Flood Insurance Rate Map (FIRM) and Flood Boundary and Floodway Map (FBFM), per Section 1612.3 local amendment; Chapter 15.32 'Flood Damage Prevention' is a separate standalone chapter of the Municipal Code (not modeled as a permitType, but is a co-applicable regulatory layer for any parcel in a mapped flood hazard area).; Elevation for Manual J design criteria: 3,470 ft; Latitude 40.9883°N; Winter design dry-bulb 0°F (indoor 70°F referenced); Summer design dry-bulb 90°F (outdoor); Indoor summer relative humidity gains blank/not legible in source; per the adopted Climatic and Geographic Design Criteria table, Ordinance No. 23-470.; Unvented gas log heaters and unvented room/decorative heaters are PROHIBITED under locally amended IRC Section R1004.4 and IMC Section 903.3 / IFGC Section G2445.1 (Ordinance No. 23-470) — a materially stricter local amendment than the base ICC text.; Automatic fire sprinkler systems requirement (IRC Section R313) is DELETED IN ITS ENTIRETY by local amendment (Ordinance No. 23-470) — Julesburg does NOT require residential fire sprinklers for one- and two-family dwellings.; IBC Appendix Adoption Table (Ordinance No. 23-470): Adopted — Appendix AG (Flood-Resistant Construction), AH (Signs), AI (Patio Covers), AJ (Grading). Explicitly Not Adopted — Appendix AA (Employee Qualifications), AB (Board of Appeals), AC (Group U Agricultural Buildings), AD (Fire Districts), AE (Supplementary Accessibility Requirements), AF (Rodent-Proofing), AK (Administrative Provisions), AL (Earthquake Recording Instrumentation), AM (Tsunami-Generated Flood Hazards), AN (Replicable Buildings), AO (Performance-Based Application Index), AU (Cob Construction), AV (Board of Appeals, IRC table), AW (3D-Printed Building Construction).; IRC Appendix Adoption Table (Ordinance No. 23-470): Adopted — Appendix AH (Patio Covers), AQ (Tiny Homes). Not Adopted — Appendix RA (Solar-Ready Zone, Residential) among others listed Not Adopted.; HB22-1362 (Colorado 'Building Greenhouse Gas Emissions' Act, 2022) note, checked honestly rather than assumed: the Town's own adopted IRC/IBC Appendix Adoption Tables (Ordinance No. 23-470, June 2023) explicitly list Appendix RA (Solar-Ready Zone — Residential) and Appendix CA (Solar-Ready Zone — Commercial) as 'Not Adopted.' HB22-1362 does not create a flat population-based exemption for any jurisdiction (that premise is associated with a different, never-enacted bill, SB25-141, and was explicitly flagged as wrong going into this research); instead HB22-1362 requires jurisdictions updating to a later-triggering code cycle to adopt either the Model Electric Ready and Solar Ready Code, the Model Low Energy and Carbon Code, or — for rural counties that apply for and are not awarded state grants substantially assisting adoption/enforcement — energy codes achieving equivalent or better performance than the three most recent IECC editions. Julesburg's current adopted energy code is the 2018 IECC (adopted June 2023), and its own appendix table shows solar-ready provisions not adopted as of that ordinance. Whether/when HB22-1362's triggering mechanism reaches a town of Julesburg's size, and whether Sedgwick County or Julesburg has pursued the rural-county grant pathway, was NOT found published anywhere in the Town's ordinances, Sedgwick County's website, or general search after full chasing — flagged as a genuinely open/unresolved compliance question rather than invented.; Electrical and plumbing: Julesburg runs ITS OWN local licensing and inspection program — it does NOT defer to Colorado DORA state trade boards. Municipal Code Chapter 15.12 creates a Town 'electrical inspector' (referred to in the code as the 'city electrician') appointed by the mayor, and Chapter 15.08 creates a Town 'plumbing inspector.' Ordinance No. 23-472 (2023) updated the licensure sections so that the Town Manager or their designee now serves as plumbing inspector, and updated qualification/bonding requirements for both trades. Permits, licensing, bonding/insurance, and inspection-and-certificate sign-off for both trades are handled entirely at the Town level, not referred to DORA's State Electrical Board or State Plumbing Board.; No separately-published, dollar-denominated Building/Plumbing/Mechanical/Electrical permit fee schedule was found on the Town's website, its Documents/Forms & Applications library, or Ordinance No. 23-470/23-472 (both state fees are 'in accordance with a fee schedule adopted from time to time by the Town Board by resolution' — i.e. fees live in a separate resolution, not the ordinance itself, and no such resolution PDF is published online). The generic 'Application for Building Permit' and 'Application for Building Permit — Roofing & Siding' forms both have blank Permit Fee / Use Tax fields for Town Hall staff to fill in at submittal. Confirm current fees directly with Town Hall (970-474-3344) before budgeting — omitted rather than invented, per this corpus's zero-tolerance data policy.. Local amendments apply — see the Julesburg overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Julesburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.