Blue River building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Blue River, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
Town Hall, 0110 Whispering Pines Circle, Blue River, CO 80424 (mailing: P.O. Box 1784, Breckenridge, CO 80424)
Phone
(970) 547-0545 (Town Hall, ext. 1 for building permit questions); Building Official direct: (720) 241-4741
Office hours
Town Hall open Tuesday-Friday, 7:00 a.m.-5:00 p.m. (per the Town's own Contact Us page, verified live 2026-07-06). Building inspections are conducted Tuesdays and Thursdays and must be scheduled by 4:00 p.m. the day before (Monday inspections scheduled by 4:00 p.m. the prior Thursday); requests received Friday are scheduled for the following Tuesday. The Building Official's function is performed by a contracted firm (email domain caa.inc), not a Summit County employee and not a direct Town staff member.

Published scheduling rules

  • Schedule inspections by 4:00 p.m. the day before (Tuesdays/Thursdays only, per the Building Inspections page) or by Thursday 4:00 p.m. for a Monday inspection; requests received Friday roll to the following Tuesday. (Building Permit — New Construction (Type A Permit))

Inspection sequence

Applies to: Building Permit — New Construction (Type A Permit)

  1. 1

    Layout & Footings

    Forms & steel in place; all materials except concrete on site

  2. 2

    Foundation Walls

    Forms & steel in place; Foundation ILC must be received by Building Official prior to this inspection

  3. 3

    Foundation Damp-proofing

  4. 4

    Foundation Insulation

  5. 5

    Foundation Drain

    Properly bedded, prior to cover-up

  6. 6

    Underground Plumbing / Underground Electric / Concrete Slab Prep

    Prior to cover; on test as applicable

  7. 7

    Rough Plumbing / Rough Mechanical / Rough Electric

    Installed and on test prior to cover

  8. 8

    Framing

    After plumbing, mechanical & electric rough inspections are approved; ridgeline ILC required first if applicable

  9. 9

    Insulation

    Insulation certificate must be received by Building Official prior to this inspection

  10. 10

    Roof Underlayment, Fireplace Chase, Gypsum Board Nail/Screw

    Sequenced finish-stage inspections

  11. 11

    Final Plumbing / Final Mechanical / Final Electrical

    All fixtures, equipment, and appliances installed and operable

  12. 12

    Final Building Inspection

    After completion of paint, finish, parking, landscaping, cleanup; requires Summit County Health Department (septic) or Upper Blue Sanitation District (sewer) approval, and HOA approval for certain subdivisions; blower door test/air-sealing sign-off required

Applies to: Addition / Remodel / Deck Permit (Type A or Type B Permit)

  1. 1

    Framing

    After framing complete, before wall cover

  2. 2

    MEP Rough-In

    If mechanical, electrical, or plumbing work is part of the scope

  3. 3

    Final Building Inspection

    All work complete per approved plans

Applies to: Electrical Permit (Type C Permit)

  1. 1

    Underground Electric

    Before cover, if applicable to scope

  2. 2

    Rough Electric

    All wiring pulled & splices made, before wall cover

  3. 3

    Final Electrical

    All equipment and appliances installed and operable

Applies to: Plumbing Permit (Type C Permit)

  1. 1

    Underground Plumbing

    Prior to cover, properly bedded, on test

  2. 2

    Rough Plumbing

    Installed, on test, before wall cover

  3. 3

    Final Plumbing

    All fixtures and appliances installed and operable

Applies to: Mechanical Permit (Type C Permit)

  1. 1

    Rough Mechanical

    Chimneys, vents, piping & ducts installed; gas line & heat pipe on test

  2. 2

    Final Mechanical

    All combustion air, equipment & appliances installed and operable; Flammable Gas Alarm/Shutoff required for propane systems over 60,000 BTU/Hr

Applies to: Roof Permit (Type C Permit)

  1. 1

    Roof Underlayment

    After ice & water shield is in place

  2. 2

    Final Building Inspection

    Roof work confirmed complete as part of overall final sign-off

Re-inspection fees

Electrical Permit (Type C Permit)Reinspection
$65.00

Blue River building permits

Get alerts for Blue River

We'll email you when Blue River's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.