Building department
- Address
- Town Hall, 0110 Whispering Pines Circle, Blue River, CO 80424 (mailing: P.O. Box 1784, Breckenridge, CO 80424)
- Phone
- (970) 547-0545 (Town Hall, ext. 1 for building permit questions); Building Official direct: (720) 241-4741
- Office hours
- Town Hall open Tuesday-Friday, 7:00 a.m.-5:00 p.m. (per the Town's own Contact Us page). Building inspections are conducted Tuesdays and Thursdays and must be scheduled by 4:00 p.m. the day before (Monday inspections scheduled by 4:00 p.m. the prior Thursday); requests received Friday are scheduled for the following Tuesday. The Building Official's function is performed by a contracted firm (email domain caa.inc), not a Summit County employee and not a direct Town staff member.
- Website
- Official site
- Permit portal
- Apply online at Blue River's portal
Inspection guide
See how inspections work in Blue River — sequence, scheduling & re-inspection fees.
Codes adopted
Colorado has no statewide-mandated building code edition. Under the Colorado Constitution's home-rule provisions (art. XX, home rule for municipalities since 1902; home rule for counties since 1970), building codes and zoning are an enumerated home-rule charter power, so cities and counties adopt and amend their own construction codes independently — predominantly the I-Codes, with editions and local amendments varying by jurisdiction. The one statewide floor is for energy: HB22-1362 (2022) created the Energy Code Board (jointly appointed by the Colorado Energy Office and the Department of Local Affairs) and requires that, on or after July 1, 2023 and before July 1, 2026, any municipality or county that adopts or updates a building code must adopt and enforce an energy code achieving performance equivalent to or better than the 2021 IECC together with the board's Model Electric Ready and Solar Ready Code (which includes electric-ready, EV-ready, and solar-ready provisions); from July 1, 2026 onward the floor shifts to the board's Model Low Energy and Carbon Code or an equivalent. Electrical and plumbing permitting defaults to the Colorado State Electrical Board and State Plumbing Board (within DORA's Division of Professions and Occupations) — the state issues permits and inspects statewide except in counties/jurisdictions that operate their own certified Electrical or Plumbing Inspection Program, in which case the local program has authority instead. Always confirm the currently adopted code edition, local amendments, and inspection authority (state board vs. local program) with the specific jurisdiction before submitting plans.
- 2024 International Residential Code (IRC) with Town amendments — the Town of Blue River's Type A Permits page states: 'The Town of Blue River has adopted the following codes with amendments: 2024 International Residential Code, 2024 International Energy Code, 2024 International Electrical Code, 2020 International Fire Code'
- 2024 International Energy Conservation Code (IECC) with Town amendments — per the same live Type A Permits page
- 2024 International Electrical Code (IEC) with Town amendments — per the same live Type A Permits page
- 2020 International Fire Code (IFC) — per the same live Type A Permits page
Blue River's own published sources disagree on the adopted residential code year. Show full textShow less
Blue River's own published sources disagree on the adopted residential code year. The Town's Building FAQ page states that Blue River follows the 2018 International Residential Code, while the Type A Permits page cites the 2024 IRC. The codified ordinance (Chapter 18 of the Town Code) is older than both: it adopts the 2012 IBC, 2017 International Electrical Code, 2012 IECC and 2012 IFC by reference, with extensive local amendments, and has not been re-codified. Treat the Type A Permits page as the operative standard for what a plan submittal must meet today, and confirm the code year with the Building Official before you design or order materials.
- Town of Blue River Municipal Code, Chapter 18 (Building Regulations) — contains extensive local amendments to the (older, codified) I-Code editions, including a locally-amended design snow load, frost line depth, and solid-fuel-burning-device restrictions (see localAmendments)
Ordinance No. 2026-01 (signed, effective 12:00 a.m. March 31, 2026 — townofblueriver.colorado.gov/sites/townofblueriver/files/Ordinance%202026-01%20Chapter%2018%202026%20Code%20Amendments%20Signed.pdf) repealed and… Show full textShow less
Ordinance No. 2026-01 (signed, effective 12:00 a.m. March 31, 2026 — townofblueriver.colorado.gov/sites/townofblueriver/files/Ordinance%202026-01%20Chapter%2018%202026%20Code%20Amendments%20Signed.pdf) repealed and reenacted Article II of Chapter 18 in its entirety, closing the code-edition gap described above. It adopts by reference: International Building Code 2024 (1st printing, Aug. 2023) — the first current-edition IBC codified for Blue River, superseding the 2012 IBC citation above — plus International Residential Code 2024, International Mechanical Code 2024, International Property Maintenance Code 2024, International Existing Building Code 2024, International Energy Conservation Code 2024, International Swimming Pool and Spa Code 2024, International Wildland-Urban Interface Code, the 2023 National Electrical Code (superseding the 2017 IEC citation above), Colorado Fuel Gas Code, Colorado Plumbing Code, Colorado Wildfire Resiliency Code (dated June 1, 2025), and the Colorado Model Electric Ready and Solar Ready Code (June 1, 2023). The Town's live Type A Permits page already cited the 2024 series; the codified ordinance has now caught up to it. Two things the ordinance does not resolve. It does not touch the International Fire Code edition — Ord. 2026-01's title and adopted-codes list include no Fire Code at all, and fire code appears to remain under separate authority, consistent with the Red White & Blue Fire District note. And the Town's own live Building FAQ page (townofblueriver.colorado.gov/building-in-blue-river) still displays stale 'International Residential 2018 Code' text elsewhere on the same page even though the codified ordinance is now 2024, so the page-versus-ordinance discrepancy is real — rely on the codified ordinance. None of this creates a distinct commercial-building-permit or TI-permit track; see the NO COMMERCIAL PERMIT TRACK entry below.
Permit types & fees
Building Permit — New Construction (Type A Permit)
Required for construction of new single-family homes, additions, and garages in Blue River. Classified as a Type A Permit, requiring review and approval by the Blue River Planning & Zoning Commission (meets first Tuesday of the month, 6:00 p.m.) in addition to Building Official plan review, under the Town's own adopted 2024 IRC/IECC/IEC and 2020 IFC with local amendments.
From$50.00Addition / Remodel / Deck Permit (Type A or Type B Permit)
Additions and garages are Type A Permits requiring Planning & Zoning Commission approval; decks are a Type B Permit approvable directly by the Building Official with a site/plat plan (no Commission review); interior remodels are a Type C Permit approvable directly by Town Staff. All three tiers use the same underlying building-permit fee schedule and code requirements (2024 IRC/IECC/IEC, 2020 IFC).
From$50.00valuation-basedElectrical Permit (Type C Permit)
Required for electrical wiring, fixtures, and equipment installation in Blue River. Classified as a Type C Permit, approvable directly by Town Staff without Planning & Zoning Commission review. Issued and inspected by the Town's contracted Building Official under the Town's own adopted 2024 International Electrical Code with amendments.
From$135.00EV Charger / EVSE Installation Permit
Blue River has no separate EV charger/EVSE permit category. A dedicated circuit for a home EV charger is billed under the Town's Electrical Permit (Type C Permit) 'All other electrical work' valuation-based fee table, issued and inspected by the Town's contracted Building Official under the 2024 International Electrical Code with local amendments.
From$135.00Plumbing Permit (Type C Permit)
Required for drain/waste/vent piping, potable water piping, fuel gas piping, and plumbing fixtures in Blue River. Classified as a Type C Permit, approvable directly by Town Staff. Issued and inspected by the Town's contracted Building Official.
From$50.00Mechanical Permit (Type C Permit)
Required for furnaces, ducts, boilers, circulation piping, and exhaust fans in Blue River. Classified as a Type C Permit, approvable directly by Town Staff. Issued and inspected by the Town's contracted Building Official.
From$50.00Roof Permit (Type C Permit)
Required for re-roofing and roofing work in Blue River. Classified as a Type C Permit, approvable directly by Town Staff, distinct from the general building permit. The Town's amended Chapter 18 code specifically addresses wood shakes (must comply with Section 1507.9) and repeals the wood-shakes fire-retardant treatment subsection (1507.9.3) outright.
See fee scheduleSolar Photovoltaic (PV) Permit
Blue River has no separate solar/photovoltaic permit type; rooftop or ground-mounted PV is permitted as a combined Building Permit (structural/racking, valuation-based fee table) and Electrical Permit (square-footage or valuation-based fee table), both under the Town's published Building Permit Fee Schedule. As in every Colorado jurisdiction, the combined total of all governmental fees for the installation is capped by state law at $500 for a residential system and $1,000 for a commercial system (C.R.S. § 24-48.5-113, enacted by HB21-1284).
From$500Sign Permit (Type B Permit)
Required for most permanent signs in Blue River. The Town's Land Use Code (Chapter 16B, Article 8) prohibits ALL permanent signs except Address Signs, Subdivision Entry Signs, Yard Statues, and Exempt Signs — most homeowner scenarios (a compliant address sign, temporary real-estate/yard-sale/political sign, or flag) require NO Town permit at all. The Land Use Code's own Chapter 16C development-application classification table (item 18) designates 'Sign' as a Type B Application, meaning administrative review by Town staff without Planning & Zoning Commission approval — but the Town's live Type B Permits web page (which lists Sheds, Excavation, Landscaping, Berms, Solar, Fences, and Chicken Enclosures) does not itself name 'Sign' as a category, a discrepancy worth confirming directly with the Building Official before applying.
See fee scheduleFire Sprinkler & Fire Alarm System Permit (Red, White & Blue Fire Protection District)
Required for installation, modification, or replacement of an automatic fire-extinguishing (sprinkler) system or a fire alarm/detection system anywhere in Blue River. This permit is issued and inspected by the Red, White & Blue Fire Protection District (RWBFPD) — a separate special fire protection district covering Breckenridge, Blue River, and unincorporated Summit County — NOT the Town of Blue River Building Department. RWBFPD's own live Code Amendments page shows Blue River specifically operates under the District's 2018 International Fire Code adoption (Resolution 2019-06, effective January 1, 2020), distinct from the 2024 IFC amendments RWBFPD applies to Breckenridge and unincorporated Summit County — itself a further wrinkle on top of the already-documented confusion between the Town's own Chapter 18 code (which cites a 2020 IFC edition on its live Type A Permits page) and RWBFPD's separate 2018 IFC district-wide adoption; confirm the governing edition with RWBFPD directly at submittal.
From$300Change of Use Permit
Blue River has no standalone 'change of use permit' distinct from its existing Type A/B/C building-permit and Land-Use-Code development-application framework — an honest gap after a genuine chase, not a coverage oversight. The Land Use Code defines 'change of use' only as one qualifying form of 'Development' generally (Sec. 16-3-20), and it does NOT appear as its own line item in the Land Use Code's Chapter 16C development-application classification table (which names 18+ specific improvement categories — Fence, Gazebo, Hot Tub, Sign, Excavation, etc. — each tagged Type A/B/C). Red White & Blue Fire Protection District's adopted 2018 IFC amendment to Sec. 102.4 instead folds 'changes in use' into standard IBC/IRC-compliant construction-permit review. Given the existing confirmed finding that Blue River has no usable commercial zoning district on any existing in-town parcel, the classic building-code change-of-use scenario (e.g., converting a commercial tenant space between occupancy classifications) has no real-world applicability here; the closest genuine change-of-use action available to a Blue River property owner is Town of Blue River short-term rental (STR) licensing.
See fee schedule
Property Access
Blue River's permit history is searchable by address
4,466 permits on record for Blue River, 2005–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
98% of Blue River's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
New residential construction activity
New privately-owned residential construction onlyHousing units authorized by building permits for new privately-owned residential construction — this is not total permit volume (no commercial permits or remodels).
- Latest month (2026-07)
- No data reported
- Trailing 12 months
- 2units
4 of 12 months reported · #73 in Colorado coverage by units
- Year to date (2026 YTD through 2026-07)
- 3units
3 buildings · $1.4M valuation
3 month(s) reported to Census
- Full year 2025
- 5units
5 buildings · $2.5M valuation
10 of 12 months reported; Census estimates include imputation
Source: U.S. Census Bureau, Building Permits Survey (BPS), 2026-07 vintage. Census survey data — separate from the permit-requirements verification above. All Colorado building activity
Tips & gotchas
- GOTCHA — BLUE RIVER IS GENUINELY INDEPENDENT, NOT A SUMMIT COUNTY PROGRAM: unlike Dillon (fully contracted to Summit County Building Inspection Department) and Silverthorne (split), Blue River runs its own building department end-to-end — its own permit application, its own Building Official (a contracted individual/firm at SPinspections@caa.inc), its own fee schedule, and its own three-tier Type A/B/C permit classification. Summit County's only genuine touchpoint is a Summit County Health Department septic sign-off required at Final Building Inspection — not full plan review/inspection.
- THREE PERMIT TIERS, NOT ONE: Type A (new construction, additions, garages, plat amendments, variances, subdivision) needs Planning & Zoning Commission approval at a MONTHLY meeting (first Tuesday, 6 p.m.), with applications due 3 weeks ahead — plan your timeline around this monthly cadence, not a rolling office turnaround. Type B (sheds, excavation, landscaping features, berms, solar, fences, chicken enclosures, decks) skips the Commission and goes straight to the Building Official with a site/plat plan. Type C (staining/siding, roofs, interior remodel, forest management, hot tubs, windows, plumbing/mechanical/electrical) can be approved directly by Town Staff.
- ALL SUBMITTALS ELECTRONIC — the opposite of Summit County's own in-person-only building department: Blue River's Building Construction Application Packet states in bold 'ALL Submittals Must be Electronic,' emailed to info@townofblueriver.org.
- CODE-EDITION CONFUSION ACROSS THE TOWN'S OWN PAGES: the live Type A Permits page cites 2024 IRC/IECC/IEC + 2020 IFC; the live Building FAQ page says the Town abides by '2018 Code'; the codified Chapter 18 ordinance itself is oldest of all (2012 IBC, 2017 electrical code, 2012 IECC, 2012 IFC). Confirm directly with the Building Official (SPinspections@caa.inc) which edition actually governs your specific submittal.
- Blue River's own fee schedule (revised 2017) is similar to but NOT identical to Summit County's — e.g., Blue River's electrical base fee is $135.00 (vs. Summit County's $146.00) and its mid-tier building-permit marginal rates differ ($15.00/$12.00/$8.00 per $1,000 vs. Summit County's $14.00/$10.10/$7.00) — never assume the two schedules are interchangeable.
- Locally-amended design figures exist and were found (unlike Dillon's documented gap): 100 psf roof snow load / 125 psf deck-and-balcony snow load, 40-inch frost line, and specific solid-fuel-burning-device restrictions, all from Chapter 18's own text.
- Inspections run Tuesday/Thursday only (not the standard weekday schedule) and must be requested by 4:00 p.m. the prior business day; Friday requests roll to the following Tuesday.
- GAP, documented honestly: no distinct Roof Permit fee line was found on the Town's published fee schedule despite Roof being a named Type C permit category — confirm this fee directly with the Building Official rather than assuming it matches the general building-permit valuation table.
- Blue River has no commercial permit track: no commercial building permit, no tenant-improvement permit, and effectively no commercial zoning. The Town's Land Use Code (updated 4-2-2025, Sec. 16A-2-10) establishes exactly seven zone districts — Transitional (TD), Single-Family Residential (R-1), and Planned Residential (PRD) are residential/institutional only (home occupations are the sole permitted business activity); UOP, RF, and PROW are resource-protection/right-of-way districts; and the one Mixed Use District (MUD) allowing limited commercial uses (hotel ≤60,000 sq ft/70 rooms, restaurants ≤3,500 sq ft each, event centers) is restricted by Secs. 16A-7-10/-20 to parcels of 35+ acres annexed into the Town AFTER June 20, 2023, so no existing in-town parcel can hold it. As of Ordinance 2026-01 (eff. 3/31/2026), Chapter 18 adopts a current-edition IBC (2024), not the 2012 edition (see the code-adoption bullet in codesAdopted) — but this is a code-library update, not a zoning or permit-type change, and does not affect this finding. Any hypothetical future commercial construction on a MUD-annexed parcel would still route through the same Type A permit process as residential new construction. Commercial/TI work in this part of Summit County belongs to Breckenridge or unincorporated Summit County, not Blue River.
- The Town has no commercial or tenant-improvement permit track. Neither the Town's Type A Permits page (townofblueriver.colorado.gov/type-a-permits) nor its Business Licenses page (townofblueriver.colorado.gov/business-licenses) contains a single occurrence of the word 'commercial.' The Town's older, pre-2023 zoning regime — codified in the separate 'CHAPTER 16 Zoning' municipal-code PDF (townofblueriver.colorado.gov/sites/townofblueriver/files/CHAPTER%2016%20Zoning.pdf), a distinct document from the current Land Use Code — had only Transition, R-1, PRD, and UOP districts, so no commercial district has existed at any point in this jurisdiction's zoning history, not just under the current Land Use Code. No SAFEbuilt or other regional/contracted commercial-permitting body serves Blue River; the Town's building department is independently run. No existing hotel, restaurant, or retail business has a physical address inside Blue River town limits — the nearest such businesses (e.g., Blue River Bistro) are physically located in Breckenridge, roughly 4 miles away, despite some listings using 'Blue River' loosely as a place-name. Ordinance 2025-02 makes setback/easement measurement amendments only and is unrelated to zoning classification or commercial permitting.
- VALUATION METHOD IS NOT PUBLICLY REACHABLE: the Town fee schedule footnotes its Building table with “see code amendment document for additional fees” and its Mechanical table with “see code amendment document Section A (3) to verify valuation standards” — but both footnotes link to a local drive path (file:///G:/...) that leaked into the published page and cannot be opened by anyone outside Town Hall. The fee figures themselves are printed on the page and are reliable; how the Town determines the valuation those tiers are applied to is not published. Ask the Building Department before relying on a computed total.