This is PermitBase’s published record for Kersey as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Kersey building permits

Kersey, Colorado — as published 2026-07-06.

Reviewed 2026-07-06 · Source

Codes adopted

2024 International Residential Code (IRC) — actively cited as the current adopted code on all nine of the Town's SAFEbuilt-published 'Building Guides for Homeowners' (Additions, Accessory Structures, Re-Roofing, Basement Finish, Decks, Patio Covers/Carports, Window Replacement, Pole Barns, Swimming Pools), each stamped 'Document published by SAFEbuilt, Inc. 1.1.2026' and headed '2024 IRC' — these are the Town's most recently updated, actively maintained permitting documents (site-wide document-center timestamps show a 2026-03-30 publish date).2020 National Electrical Code (NEC) — per the Town's Planning Department 'Current Building Regulations' page, which references a '2020 NEC - Significant Changes Residential Electrical' resource alongside the Municipal Code Chapter 18 structure.Note on code-currency conflict: the Town's Planning Department 'Current Building Regulations' page (a static summary page) states the Town has adopted the '2018 International Building Code (IBC)' and organizes Municipal Code Chapter 18 into Articles I-XI (General Provisions; Building Code; Residential Code; Mechanical Code; Fuel Gas Code; Plumbing Code; Energy Conservation Code; Property Maintenance Code; Existing Building Code; International Fire Code; Swimming Pool and Spa Code) without giving per-article edition years for IMC/IFGC/IPC/IECC/IEBC/IFC. This directly conflicts with the SAFEbuilt-published homeowner guides (dated 1.1.2026, all headed '2024 IRC'), which are the Town's more recently updated and actively distributed permitting documents. Per this corpus's practice of preferring the more current, actively-maintained source (as with Vail's precedent), this file treats 2024 IRC as the governing residential code edition. The Town's own Municipal Code (hosted on Municode, a JavaScript single-page application not text-extractable by automated tools in this session) could not be independently loaded to resolve this conflict for the Building/Mechanical/Fuel Gas/Plumbing/Energy/Existing-Building/Fire articles specifically — confidence for the NON-residential code editions (IBC/IMC/IFGC/IPC/IECC/IEBC/IFC) is therefore marked partial pending direct confirmation of Municipal Code Chapter 18's current article-by-article edition years. Town Hall (970-353-1681 ext. 1) and SAFEbuilt Windsor (970-686-7511) are both listed by the Town itself as the correct contacts for verification of current code requirements.HB22-1362 (Colorado statewide energy code floor, 2021 IECC + electric/solar/EV-ready provisions, effective window July 2023-July 2026): no evidence found that Kersey has adopted a distinct current-cycle IECC edition beyond the ambiguous 'Energy Conservation Code' article referenced on the Current Building Regulations page; the Town's Home Additions guide instructs applicants to submit an 'Energy Code Compliance Report (www.energycodes.gov) or REScheck calculations' without naming a specific IECC year. Not asserting HB22-1362 applicability given the absence of a locally-published edition year for the Energy Conservation Code article — flagged as an open verification item rather than guessed.

Permit types & fees

Residential Building Permit (New Construction / Additions)

Verified

Required for new single-family construction and additions to single-family dwellings in the Town of Kersey. Reviewed under the 2024 IRC per the Town's SAFEbuilt-published Home Additions guide. Building inspection services are contracted to SAFEbuilt Colorado (Windsor Office); permits are issued by the Town after SAFEbuilt plan review.

Verified 2026-07-06 · Source

Requirements

  • Site Plan showing dimensions of the project, setbacks, easements, utilities, other structures, and distance to property lines; structures may not be built over setback lines, easements, or property lines
  • A survey from a registered land surveyor is required if the project is in a protected area; an as-built survey is required if the structure is proposed within 12 inches of a required minimum setback
  • Floor Plan showing existing house dimensions, new room dimensions, new openings, and relocated items; new openings exceeding 6 feet in a bearing wall require detailed specifications; additions cannot enclose bedroom or basement egress windows
  • Construction details: foundation detail, exterior elevations, Energy Code Compliance Report (energycodes.gov) or REScheck calculations, and Manual D & J documentation if new HVAC appliances are installed
  • Approval from the county health department required prior to permit issuance if the property is on a septic tank
  • Owner-builders are the responsible party of record; State law requires 2-year occupancy after owner-performed work
  • Permits valid for work to begin within 6 months of issuance; expire after 180 days of no work performed

Required documents

  • RequiredBuilding Permit ApplicationSubmitted via the Town of Kersey's Community Core online portal (app.communitycore.com) after contractor/applicant registration
  • RequiredSite Plan / SurveyDimensions, setbacks, easements, utility locations; registered land surveyor required in protected areas
  • RequiredFloor PlanExisting and new dimensions, openings, relocated items
  • RequiredEnergy Code Compliance Report or REScheck Calculations

Fee schedule

Fee typeAmountNotes
Building Permit FeeSet by SAFEbuilt per the Uniform Building Code (UBC) valuation-based fee schedule (not a flat Town-published table)Development Fee Schedule PDF worked example: ~$936.35 building fee for a $164,849 UBC-valuation 1,400 sq ft home + 1,400 sq ft unfinished basement + 484 sq ft garage
Plan Review Fee30% of Permit FeeDevelopment Fee Schedule PDF
Town Surcharge20% of the Building Fee
Administrative Fee (New Construction)$250.002026 Fee Schedule; the separate Development Fee Schedule PDF lists this same line item as 'varies' rather than a flat figure — the 2026 Fee Schedule's flat $250 is treated as current
Building Material Use Tax3.0% of 50% of construction material value (effectively ~1.5% of total value)
Water Inspection Fee$40.00
Sewer Inspection Fee$40.00
Construction Meter Fee$57.50Approximate, per Development Fee Schedule worked example
Re-inspection Fee$50.00/hour, 2-hour minimum2026 Fee Schedule
Permit Revision Fee$75.00
Permit Extension Fee$150.00

Residential Addition / Basement Finish Remodel

Covers additions to single-family dwellings and interior basement-finish remodels in Kersey, both reviewed under the 2024 IRC. The Town publishes distinct SAFEbuilt homeowner guides for Home Additions and Basement Finish, reflecting different document scope for exterior-expanding versus interior-only work.

Reviewed 2026-07-06 · Source

Requirements

  • Site Plan required for additions that change the building footprint; not required for a purely interior basement finish that adds no exterior floor area
  • Floor Plan showing new/existing dimensions and any new openings
  • Heat required in all habitable rooms; plans must show how heat is supplied to new/finished space
  • Egress windows may not be enclosed by an addition; basement finishes must meet IRC egress requirements for habitable/sleeping rooms
  • Energy Code Compliance Report or REScheck calculations for additions; combustion equipment must meet the State of Colorado Electric Ready Code where applicable

Required documents

  • RequiredBuilding Permit ApplicationSubmitted via the Town's Community Core online portal
  • RequiredFloor Plan
  • OptionalSite PlanRequired for additions that expand the building footprint; not required for interior-only basement finish

Fee schedule

Fee typeAmountNotes
Building Permit Fee (UBC valuation-based, same schedule as new construction)Set by SAFEbuilt per UBC valuation2026 Fee Schedule / Development Fee Schedule
Plan Review Fee30% of Permit Fee
Town Surcharge20% of Building Fee
Building Material Use Tax3.0% of 50% of construction material value

Electrical Permit

Required for installation, alteration, or repair of electrical systems in Kersey. Governed by the 2020 NEC per the Town's Current Building Regulations page. Kersey defers electrical contractor licensing entirely to the Colorado State Electrical Board (DORA) and performs contemporaneous license verification per its own published guidelines, rather than running a local electrical licensing/registration program.

Reviewed 2026-07-06 · Source

Requirements

  • Electrician's name and Colorado state electrical license number must be listed on any 'electrical only' permit application; applications missing this are rejected
  • The Town verifies the listed electrician's license is active via the Colorado DORA online License Lookup before approving the permit
  • If the electrician changes before final inspection, the applicant must notify the Town, which re-verifies the new electrician's license; work must stop if the new electrician cannot be verified
  • Building inspectors may request to verify the identity of the electrician performing work at any inspection, at their discretion, and may fail an inspection if this cannot be confirmed
  • A permit is required anytime work involves the electrical system, per the Town's general permitting FAQ

Required documents

  • RequiredElectrical Permit ApplicationSubmitted via the Town's Community Core online portal; must list electrician name and Colorado state license number

Fee schedule

Fee typeAmountNotes
Electrical Fee~$51.75 in the Development Fee Schedule's worked example (bundled as a line item within the overall Building Permit Fee for a $164,849-valuation new home)No standalone electrical-only fee table was found; Colorado statute (CRS 12-23-117(3), the state-mandated electrical fee schedule used in peer Colorado jurisdictions such as Vail) may govern the base electrical fee, but Kersey's own published fee documents do not break this out or confirm a local surcharge percentage — marked partial for this reason

Plumbing Permit

Required for installation, alteration, or repair of plumbing systems in Kersey. No local plumbing licensing or registration program is published by the Town; plumbing contractor licensing is assessed as deferring to the Colorado State Plumbing Board (DORA/DPO) by default, consistent with Colorado's framework for small municipalities without their own certified plumbing licensing program.

Reviewed 2026-07-06 · Source

Requirements

  • A permit is required anytime work involves the plumbing system, per the Town's general permitting FAQ
  • Underground plumbing inspection required prior to covering any piping and prior to placing concrete
  • No Kersey-specific local plumbing contractor licensing/registration document was found (unlike the Town's explicit Electrical License Contemporaneous Review Guidelines) — Colorado State Plumbing Board (DORA) licensure is assumed to govern by default

Required documents

  • RequiredPlumbing Permit ApplicationSubmitted via the Town's Community Core online portal, likely combined with the general Building Permit Application for most residential scopes (no standalone plumbing-only application form was found)

Fee schedule

Fee typeAmountNotes
Plumbing Permit FeeNot separately broken out in either published fee documentThe Development Fee Schedule and 2026 Fee Schedule bundle plumbing/water/sewer inspection fees ($40 Water Inspection Fee, $40 Sewer Inspection Fee in the worked example) within the overall Building Permit Fee rather than publishing a standalone plumbing fee schedule

Mechanical / HVAC Permit

Required for heating, cooling, and ventilation equipment installation or replacement in Kersey. Referenced under the Town's Municipal Code Chapter 18, Article IV (Mechanical Code) and Article V (Fuel Gas Code); specific adopted editions for these articles were not independently confirmed in this session beyond the Town's summary page.

Reviewed 2026-07-06 · Source

Requirements

  • Manual D & J documentation required for new HVAC appliance installations, per the Home Additions guide
  • Combustion appliances may be required to comply with the State of Colorado Electric Ready Code; contact the Building Department for applicability
  • Heat required in all habitable rooms for additions/remodels; plans must show how heat is supplied

Required documents

  • RequiredMechanical Permit ApplicationSubmitted via the Town's Community Core online portal, typically bundled with the Building Permit Application for residential scopes
  • RequiredManual D & J DocumentationRequired for new HVAC appliance installations

Fee schedule

Fee typeAmountNotes
Mechanical Permit FeeNot separately broken out; bundled within the overall SAFEbuilt UBC-valuation-based Building Permit FeeNo standalone mechanical fee line item found in either published fee document

Re-Roof Permit

Verified

Required for residential re-roofing work in Kersey. Governed by 2024 IRC Sections R806 (Roof Ventilation) and R908 (Reroofing) per the Town's SAFEbuilt-published Residential Re-Roofing guide. Owners may perform their own re-roof; a Final Roof inspection is mandatory and a mid-roof inspection may be required (though the guide separately states mid-roof inspections are NOT required on residential projects).

Verified 2026-07-06 · Source

Requirements

  • Roof sheathing must provide a rigid surface; warped, cracked, or delaminated boards/sheathing must be repaired or replaced
  • For complete tear-offs: new minimum 15# asphalt-saturated felt underlayment required on a dry deck; roofs 4:12 pitch or greater need one layer of underlayment, roofs between 2:12 and 4:12 need 19-inch laps starting with a 19-inch strip
  • No more than 2 layers of roofing allowed upon completion; roof replacement (tear-off to deck) is required where the existing roof is water-soaked/deteriorated, is wood shake/slate/clay/cement/asbestos-cement tile, or already has 2+ layers
  • Ice and water shield is required on ALL roofs per the guide's Wind/Weather Resistance section
  • Asphalt shingles are not permitted on slopes under 2:12; must be tested to ASTM D7158 for a 115 mph ultimate design wind speed
  • Existing roof jacks and vents must be replaced if in poor condition, badly rusted, or deteriorated
  • A Final Roof inspection is mandatory; the guide's FAQ says a mid-roof inspection 'may be required' but its Additional Information section separately states mid-roof inspections are NOT required on residential projects — this is an internal inconsistency in the Town's own document, noted rather than resolved by assumption

Required documents

  • RequiredRe-Roof Permit ApplicationSubmitted via the Town's Community Core online portal

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based, no separate flat re-roof fee published)Set by SAFEbuilt per UBC valuation of the re-roofing workNo standalone re-roof fee found in either published fee document

Accessory Dwelling Unit (ADU) Permit

Kersey's Planning Department offers a standalone Accessory Dwelling Unit Application as a land-use approval that precedes the SAFEbuilt building-permit process. Full requirements text could not be independently extracted in this session beyond confirming the application's existence and its listing among the Planning Department's land use applications.

Reviewed 2026-07-06 · Source

Requirements

  • A pre-application meeting is required for all Planning Department land use applications, scheduled by calling Town Hall at 970-353-1681
  • Standalone 'Accessory Dwelling Unit Application' form exists and is distinct from the general Land Use Application and Site Plan Review applications
  • Following land-use/ADU approval, a standard SAFEbuilt building permit (new construction or addition-type review) would be required for construction of the unit itself — not independently confirmed as a documented sequential process by the Town in this session, inferred from the general structure of Planning Department land-use review preceding Building Department permitting

Required documents

  • RequiredAccessory Dwelling Unit ApplicationPlanning Department land-use application form; specific submittal checklist not independently retrieved in this session

Fee schedule

Fee typeAmountNotes
ADU Application / Building Permit FeesNot separately publishedNo ADU-specific fee line item found in either fee schedule document; likely follows the general Site Plan Review Fee and/or standard UBC-valuation Building Permit Fee, but this was not independently confirmed

Demolition Permit

No standalone Kersey-specific demolition permit page, guide, or fee line item was found after chasing the Building Inspection Department page, all nine SAFEbuilt homeowner guides, both fee schedule documents, and the Land Use Applications page. This permit type is included in the schema for cross-linking consistency but its Kersey-specific requirements, fees, and process could not be verified.

Reviewed 2026-07-06 · Source

Requirements

  • Not independently documented by the Town in any page or PDF retrieved in this session — general building-permit principles (permit required by Ordinance per Municipal Code, application via Community Core portal, SAFEbuilt plan review) are expected to apply by extension, but no demolition-specific requirement, checklist, or guide was located

Required documents

  • RequiredBuilding/Demolition Permit ApplicationPresumed to route through the same Community Core portal as other building permits; no demolition-specific application form was found

Fee schedule

Fee typeAmountNotes
Demolition Permit FeeNot publishedNo demolition-specific fee line item found in the Development Fee Schedule or 2026 Fee Schedule documents

Deck / Patio Cover / Carport Permit

Covers decks, patio covers, and carports in Kersey, reviewed under the 2024 IRC per the Town's dedicated 'Decks' and 'Patio Covers/Carports' SAFEbuilt homeowner guides. Full text of these two guides was not independently extracted line-by-line in this session beyond confirming their existence, 2024 IRC heading, and 1.1.2026 publish date alongside the other homeowner guides.

Reviewed 2026-07-06 · Source

Requirements

  • Site Plan required showing setbacks, easements, property lines, and distance to other structures, consistent with the pattern used in the Additions and Accessory Structures guides
  • Construction details (footing size, post spacing, joist/beam sizing, guard/handrail requirements per 2024 IRC) expected consistent with the Town's standard construction-detail format used across its other guides — not independently line-item confirmed for this specific guide

Required documents

  • RequiredDeck / Patio Cover / Carport Permit ApplicationSubmitted via the Town's Community Core online portal

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based)Set by SAFEbuilt per UBC valuation of the deck/patio cover/carportNo standalone deck-specific fee line item found in either published fee document

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kersey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Later version (2026-07-07) →View current record →All versions →

Permalink: /colorado/weld-county/kersey/as-of/2026-07-06/

Snapshot date: 2026-07-06