Pierce building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Pierce, Colorado.
Verified 2026-07-23 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 144 Main Street, Pierce, CO 80650 (PO Box 57)
- Phone
- 970-834-2851
- info@piercecolo.gov
- Office hours
- Town Hall main line (970) 834-2851, fax (970) 834-2755, per the Town's Building Permit Application form. The Town's general Contact Us page lists the same address/phone but no posted office hours; the Planning and Zoning department directs all building-permit, addition, new-construction, annexation, and remodel questions to the Town Hall main line. Inspections (not permit intake) are scheduled directly with SAFEbuilt Inc. at 970-674-1036 or 1-866-671-1036, calls before 7:30 a.m. receive same-day inspection, after 7:30 a.m. scheduled for the next working day. Note: the Contact Us page renders the street address as '144 Main Avenue' while the Town Hall page and the Building Permit Application PDF both render it as '144 Main St./144 Main Street' — treated as the same address, minor inconsistency in the Town's own CMS.
- Website
- Official site
Published scheduling rules
- Pierce is a small statutory town in Weld County that contracts plan review and inspections to SAFEbuilt Inc.; permit intake, application questions, and fee payment go through Town Hall (970-834-2851), while inspection SCHEDULING is a separate call to SAFEbuilt directly (970-674-1036 or 1-866-671-1036, before 7:30 a.m. for same-day service). (General)
- Permits become null and void if work is not ready for first inspection within 180 days of issuance, or if more than 180 days elapse between inspections, or if work substantially ceases — track this deadline carefully since Pierce's inspection scheduling runs through a separate contracted provider (SAFEbuilt) rather than Town Hall. (General)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour, per 30-inch minimum frost line; lot corners must be clearly staked for setback inspections
- 2
Framing
Structural framing complete before cover; all concrete reinforcing steel must be in place before inspection
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes; required before Certificate of Occupancy issuance
Applies to: Residential Addition / Remodel Permit
- 1
Rough Frame / Foundation (additions with new footings only)
Before concealment; foundation inspection only if new footings are part of scope
- 2
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment, if applicable to project scope
- 3
Final Inspection
All work complete per approved plans
Applies to: Commercial Tenant Finish / Improvement Permit
- 1
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 2
Final Inspection
All work complete per approved plans and applicable commercial codes
Applies to: Deck / Patio Cover / Carport Permit
- 1
Footing/Foundation (if new footings required)
Before concrete pour, per 30-inch minimum frost line; lot corners must be clearly staked for setback inspections
- 2
Final Inspection
Structure complete, guardrails/stair compliance verified where applicable
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
EVSE circuit wiring and panel/breaker installed before concealment
- 2
Final Inspection
Charger installed, panel labeled, circuit energized and verified
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, gas piping, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Rooftop Solar / Photovoltaic Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final Inspection
Racking, roof penetrations, and electrical connections verified
Final inspection only: Demolition Permit, Re-Roof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pierce building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Pierce building permits
Get alerts for Pierce
We'll email you when Pierce's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.