Chubbuck building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Chubbuck, Idaho.
Verified 2026-07-04 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 290 East Linden Ave, Chubbuck, ID 83202 (mailing: PO Box 5604, Chubbuck, ID 83202)
- Phone
- (208) 417-7176 (Permits/Inspections); main line (208) 237-2430
- Office hours
- Monday-Thursday 7:30am-5:30pm; Friday 7:30am-11:30am. Certified Building Official: Ron Osborn (rosborn@cityofchubbuck.us, (208) 317-7161) — commercial plan reviews/inspections and department oversight. Building Inspector: Becka Sidell (bsidell@cityofchubbuck.us, (208) 417-7176) — residential plan reviews and building/infrastructure inspections. Permit Technician: Katie Lish (permits@cityofchubbuck.us, (208) 417-7176) — permit/application intake and general inquiries.
- Website
- Official site
Published scheduling rules
- Initial ESC inspection must be requested prior to grading/excavation; final ESC inspection required prior to Certificate of Occupancy — call (208) 234-6275 (Erosion and Sediment Control (ESC) Permit)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Footing/Foundation
Prior to concrete pour; verify footing dimensions per the City's frost line (36 inches) and seismic zone C design criteria
- 2
Framing
Structural framing per approved plans
- 3
Erosion and Sediment Control (ESC) — Initial
Requested prior to beginning grading or excavation; call (208) 234-6275
- 4
Final / Certificate of Occupancy
Final building, electrical, plumbing, and mechanical verification; final ESC inspection also required (call 208-234-6275)
Applies to: Solar Photovoltaic (PV) Permit
- 1
Footing/Framing (Building, if ground-mount or structural reinforcement required)
Structural mounting verified per approved plans
- 2
Electrical Rough-In
Wiring and conduit installed prior to cover
- 3
Final Electrical
Interconnection, grounding, and disconnects verified prior to energization
Applies to: Electric Vehicle (EV) Charger / EVSE Permit
- 1
Rough-In
Prior to covering wiring
- 2
Final
Final electrical inspection prior to energization
Applies to: Electrical Permit
- 1
Rough-In
Prior to covering wiring
- 2
Final
Final electrical inspection prior to certificate of occupancy or service energization
Applies to: Erosion and Sediment Control (ESC) Permit
- 1
ESC — Initial
Requested prior to beginning grading or excavation; call (208) 234-6275
- 2
ESC — Final
Requested prior to Certificate of Occupancy; call (208) 234-6275
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork, gas piping, and equipment rough-in prior to cover
- 2
Final
Final mechanical inspection including appliance connections and combustion-air/venting verification
Applies to: Plumbing Permit
- 1
Rough-In
Prior to covering plumbing lines
- 2
Final
Final plumbing inspection including fixture connections and water heater installation
Final inspection only: Sign Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chubbuck building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Chubbuck building permits
Get alerts for Chubbuck
We'll email you when Chubbuck's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.