Residential Building Permit (New Construction) in Chubbuck, Idaho
Required for new single-family residential construction in Chubbuck, administered by the City's Building Division against the 2018 IRC and 2018 IBC, plus city-specific design criteria (seismic zone C, 36-inch frost line, snow/wind loads) and the 2018 IECC energy code. Applications are submitted through the SmartGov portal or via the paper Building Permit Application.
Verified 2026-07-04 · Source
When you need this permit
- Building permit required for new single-family residential construction
- Plans reviewed against the 2018 IRC and 2018 IBC as confirmed on the City's own Building Permit Application, plus Municipal Code 15.04.010 code adoptions
- Two complete sets of plans and a complete site plan required (three sets for commercial)
- Site plan must be drawn to scale (hand-drawn on grid paper or digital) showing lot dimensions, setbacks, rights-of-way, all utilities (water/sewer/irrigation stubs, fire hydrants, power/gas/fiber/telephone), other physical features, existing/proposed outbuildings, driveway, easements, required stormwater swales, sidewalk locations, floodplains if any, north arrow, and scale
- Energy Code Compliance form required for review: either RESCheck (energycodes.gov) or the City's own Prescriptive Specification Worksheet (2018 IECC, Climate Zone 5)
- City Infrastructure Protection acknowledgment form must be signed by the permit holder
- Building Permit Application must include state contractor license number, project valuation ('agents estimated costs of construction'), zoning district, setbacks, and building information (occupancy group, construction type, number of stories, square footage by area) Contractor
- Apply via the SmartGov portal (ci-chubbuck-id.smartgovcommunity.com) or submit the paper Residential Building Permit Packet
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Prior to concrete pour; verify footing dimensions per the City's frost line (36 inches) and seismic zone C design criteria
- 2
Framing
Structural framing per approved plans
- 3
Erosion and Sediment Control (ESC) — Initial
Requested prior to beginning grading or excavation; call (208) 234-6275
- 4
Final / Certificate of Occupancy
Final building, electrical, plumbing, and mechanical verification; final ESC inspection also required (call 208-234-6275)
See the full Chubbuck inspection guide — scheduling & re-inspection fees →
Tips
- The City's Building Permit Application itself states the local design criteria directly on the form: Seismic Zone C, Frost Line 36 inches, Ground Snow Load 45, Roof Snow Load 36, Wind Load 90 MPH 3-second gust — distinct figures from neighboring Pocatello (115 MPH wind, 3-foot frost depth, 45 psf ground/35 psf roof snow load).
- Two sets of plans are required for residential (three for commercial), plus a complete site plan — noted in bold on the Building Permit Application form.
- No published business/working-day SLA for plan review was found specific to Chubbuck; the statutory Idaho Code § 39-4117 completeness-review window (10 business days residential / 20 business days commercial) is the only governing published figure.
- An Erosion and Sediment Control (ESC) permit is a separate, additional permit from the building permit for any site work involving grading — fee is waived only when submitted alongside an approved building permit for a single-family residence.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chubbuck building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Chubbuck
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Idaho →
Look up this fee in a different city →
Now live
Build your Chubbuck project checklist
Describe your project once and get every permit, document, and fee it triggers in Chubbuck — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →