Residential Building Permit (New Construction) in Caldwell, Idaho

Required for all new one- and two-family dwellings, duplexes, and townhouses in Caldwell. Apply through the Citizenserve online portal at citizenserve.com (installation ID 263). Separate trade permits required for electrical, plumbing, and mechanical work.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $0–$499$34.00 flatCaldwell Building Safety Fees Resolution No. 300-25, Table 1
Building Permit — valuation $500–$1,999$34.00 base + $0.02624 per dollar above $500Resolution No. 300-25, Table 1
Building Permit — valuation $2,000–$24,999$64.37 base + $0.01135 per dollar above $2,000Resolution No. 300-25, Table 1
Building Permit — valuation $25,000–$49,999$326.54 base + $0.0085 per dollar above $25,000Resolution No. 300-25, Table 1
Building Permit — valuation $50,000–$99,999$549.65 base + $0.00565 per dollar above $50,000Resolution No. 300-25, Table 1
Building Permit — valuation $100,000–$499,999$846.27 base + $0.004546 per dollar above $100,000Resolution No. 300-25, Table 1
Building Permit — valuation $500,000–$999,999$2,755.45 base + $0.004336 per dollar above $500,000Resolution No. 300-25, Table 1
Building Permit — valuation $1,000,000+$5,031.78 base + $0.003650 per dollar above $1,000,000Resolution No. 300-25, Table 1
Residential Building Plan Review Fee40% of building permit feeResolution No. 300-25, Section I-D-2a; covers initial review through 3rd review
Planning & Zoning Plan Review Fee (residential)35% of building permit fee (minimum $55.00)Resolution No. 300-25, Section I-D-2b
Engineering Plan Review Fee (residential)20% of building permit feeResolution No. 300-25, Section I-D-2c
Reinspection (3rd inspection / 2nd reinspection for same work segment)$60.00Resolution No. 300-25, Section V-C; first reinspection is no charge; reinspection fee levy is at building official's discretion

Review timeline

710 business days

Caldwell’s published plan-review target

Inspection process

  1. 1

    Footing / Foundation

    Before concrete pour — verify depth (24-inch frost line), forms, reinforcement

  2. 2

    Framing

    After structural framing, sheathing, and rough-in trades complete — before insulation or wall cover

  3. 3

    Insulation / Energy

    Insulation installed per 2018 IECC with State Amendments before drywall

  4. 4

    Final

    All work complete per approved plans; Certificate of Occupancy issued for residential structures upon passing

Tips

Frequently asked questions

How long does a new residential building permit take in Caldwell?
Per the Building Safety Division's published timeframes, one- and two-family residential applications take approximately 7–10 business days for the initial plan review (may be extended by up to 5 business days based on workload). Timelines start only after the submittal is deemed complete, fees are paid, and the submission is accepted.
Do I need to check zoning before applying for a building permit in Caldwell?
Yes. The Building Safety Division requires applicants to check with the Planning & Zoning Division to verify the proposed use is compatible with the current zoning and that no other entitlements are required before submitting a building permit application.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Caldwell building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Caldwell

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.