Inspection sequence, scheduling, and re-inspection fees for building permits in Caldwell, Idaho.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
205 South 6th Ave, Caldwell, ID 83605
Phone
(208) 455-3024
Office hours
Mon–Fri (inspection requests must be called in by 7:00 AM for same-day scheduling)

Published scheduling rules

  • For concrete pours, call the inspection line early to ensure the project is ready at the requested time — rescheduling requires a next-business-day inspection. (Residential Building Permit (New Construction))
  • Call inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (Residential Electrical Permit)
  • Fire and Planning & Zoning inspections must be scheduled through the Citizenserve online portal only. (Residential Electrical Permit)
  • Call inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (Residential Plumbing Permit)
  • Call inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (Residential Mechanical / HVAC Permit)
  • Call the inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (EV Charger / EVSE Permit)
  • Inspection requests must be called in to the Inspection Line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. Requests after 7:00 AM are scheduled for the next business day. (General)
  • Fire Department and Planning & Zoning inspections must be scheduled through the Citizenserve online portal only — not by phone. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing / Foundation

    Before concrete pour — verify depth (24-inch frost line), forms, reinforcement

  2. 2

    Framing

    After structural framing, sheathing, and rough-in trades complete — before insulation or wall cover

  3. 3

    Insulation / Energy

    Insulation installed per 2018 IECC with State Amendments before drywall

  4. 4

    Final

    All work complete per approved plans; Certificate of Occupancy issued for residential structures upon passing

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing / Structural

    After framing complete, before walls covered — verify structure, blocking, egress

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before wall cover (under separate trade permits)

  3. 3

    Final

    All work complete per approved plans; Certificate of Completion issued

Applies to: Residential Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping — verify no leaks under test pressure

  2. 2

    Rough-In / Equipment

    HVAC equipment, ductwork, and gas lines rough-in before walls closed

  3. 3

    Final

    Equipment operational, combustion air verified, venting correct, controls functional

Applies to: Residential Plumbing Permit

  1. 1

    Underground / Slab Plumbing

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Electrical Rough-In

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final — Building / Structural

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    Connections, inverter installation, and interconnection verified per 2023 NEC

Applies to: Accessory Structure / Pole Building Permit

  1. 1

    Foundation / Footings

    Verify depth (24-inch frost line minimum), forms, post embedment for pole buildings

  2. 2

    Final

    Structure complete per approved plans

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Circuit wiring installed, before walls closed — verify conductor sizing and box placement

  2. 2

    Final

    EVSE connected, GFCI/AFCI protection verified per 2023 NEC

Applies to: Residential Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify conductor sizing, box placement, and service connections

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC

Final inspection only: Demolition Permit

Re-inspection fees

Residential Building Permit (New Construction)Reinspection (3rd inspection / 2nd reinspection for same work segment) · Resolution No. 300-25, Section V-C; first reinspection is no charge; reinspection fee levy is at building official's discretion
$60.00
Residential Addition / Remodel PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C; first reinspection at no charge
$60.00
Residential Electrical PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Residential Plumbing PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Residential Mechanical / HVAC PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Solar Photovoltaic (PV) PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Accessory Structure / Pole Building PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Demolition PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00

Caldwell building permits

Get alerts for Caldwell

We'll email you when Caldwell's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.