Caldwell building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Caldwell, Idaho.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
205 South 6th Ave, Caldwell, ID 83605
Phone
(208) 455-3024
Office hours
Mon–Fri (inspection requests must be called in by 7:00 AM for same-day scheduling)

Published scheduling rules

  • For concrete pours, call the inspection line early to ensure the project is ready at the requested time — rescheduling requires a next-business-day inspection. (Residential Building Permit (New Construction))
  • Call inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (Residential Electrical Permit)
  • Fire and Planning & Zoning inspections must be scheduled through the Citizenserve online portal only. (Residential Electrical Permit)
  • Call inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (Residential Plumbing Permit)
  • Call inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (Residential Mechanical / HVAC Permit)
  • Call the inspection line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. (EV Charger / EVSE Permit)
  • Inspection requests must be called in to the Inspection Line (208) 455-4605 by 7:00 AM for same-day inspection scheduling. Requests after 7:00 AM are scheduled for the next business day. (General)
  • Fire Department and Planning & Zoning inspections must be scheduled through the Citizenserve online portal only — not by phone. (General)

Inspection sequence

Applies to: Commercial Building Permit (New Construction / Addition / Non-Residential / Multi-Family)

  1. 1

    Footing / Foundation

    Before concrete pour — verify depth (24-inch frost line minimum), forms, reinforcement per stamped structural plans

  2. 2

    Framing / Structural

    After structural framing complete — verify against stamped structural plans, shear walls, special inspections per IBC Chapter 17 where required

  3. 3

    Fire

    Fire Department inspection of fire lanes, hydrants, FDC, Knox box, and any fire sprinkler/alarm/hood suppression systems (submitted and inspected under separate applications) — coordinated by the Fire Codes Team Leader

  4. 4

    Final / Certificate of Occupancy

    All Development Team disciplines (Building, Fire, Engineering, Planning & Zoning) sign off; ADA accessibility features verified; Certificate of Occupancy issued upon passing

Applies to: Commercial Tenant Improvement (TI) Permit

  1. 1

    Framing / Structural (if applicable)

    For TI scopes involving wall changes or structural modifications — verify against stamped plans before wall cover; not applicable to finish-only TI scopes

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before wall cover, under their own separate trade permits

  3. 3

    Fire

    Fire Department inspection of any fire-rated separations, hydrants/hose access, and any fire sprinkler/alarm/hood suppression systems (submitted and inspected under separate applications)

  4. 4

    Final / Certificate of Occupancy

    All applicable Development Team disciplines sign off; ADA accessibility features verified; Certificate of Occupancy (or Certificate of Completion) issued upon passing

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing / Foundation

    Before concrete pour — verify depth (24-inch frost line), forms, reinforcement

  2. 2

    Framing

    After structural framing, sheathing, and rough-in trades complete — before insulation or wall cover

  3. 3

    Insulation / Energy

    Insulation installed per 2018 IECC with State Amendments before drywall

  4. 4

    Final

    All work complete per approved plans; Certificate of Occupancy issued for residential structures upon passing

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing / Structural

    After framing complete, before walls covered — verify structure, blocking, egress

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before wall cover (under separate trade permits)

  3. 3

    Final

    All work complete per approved plans; Certificate of Completion issued

Applies to: Residential Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping — verify no leaks under test pressure

  2. 2

    Rough-In / Equipment

    HVAC equipment, ductwork, and gas lines rough-in before walls closed

  3. 3

    Final

    Equipment operational, combustion air verified, venting correct, controls functional

Applies to: Residential Plumbing Permit

  1. 1

    Underground / Slab Plumbing

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Electrical Rough-In

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final — Building / Structural

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    Connections, inverter installation, and interconnection verified per 2023 NEC

Applies to: Accessory Structure / Pole Building Permit

  1. 1

    Foundation / Footings

    Verify depth (24-inch frost line minimum), forms, post embedment for pole buildings

  2. 2

    Final

    Structure complete per approved plans

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Circuit wiring installed, before walls closed — verify conductor sizing and box placement

  2. 2

    Final

    EVSE connected, GFCI/AFCI protection verified per 2023 NEC

Applies to: Residential Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify conductor sizing, box placement, and service connections

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC

Final inspection only: Demolition Permit

Re-inspection fees

Residential Building Permit (New Construction)Reinspection (3rd inspection / 2nd reinspection for same work segment) · Resolution No. 300-25, Section V-C; first reinspection is no charge; reinspection fee levy is at building official's discretion
$60.00
Residential Addition / Remodel PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C; first reinspection at no charge
$60.00
Residential Electrical PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Residential Plumbing PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Residential Mechanical / HVAC PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Solar Photovoltaic (PV) PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Accessory Structure / Pole Building PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Demolition PermitReinspection (3rd inspection / 2nd reinspection for same segment) · Resolution No. 300-25, Section V-C
$60.00
Commercial Building Permit (New Construction / Addition / Non-Residential / Multi-Family)Reinspection (3rd inspection / 2nd reinspection for same work segment) · Resolution No. 300-25, Section V-C; first reinspection is no charge
$60.00
Commercial Tenant Improvement (TI) PermitReinspection (3rd inspection / 2nd reinspection for same work segment) · Resolution No. 300-25, Section V-C; first reinspection is no charge
$60.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Caldwell building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Caldwell building permits

Get alerts for Caldwell

We'll email you when Caldwell's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.