Required for new single-family dwellings, duplexes, zero-lot-line units, additions, remodels/repairs, and accessory structures over 200 sq ft in Blackfoot, administered by the City of Blackfoot Building & Safety Department against the building/residential code 'current edition as adopted by the state' per Municipal Code 10-2-1, plus city-specific design loads (Seismic Design Category D, 50 psf ground snow load, 30-inch frost depth, 90/105 mph wind).

Verified 2026-07-04 · Source

When you need this permit

  • Building permit required for single-family dwellings, duplexes, zero-lot-line units, remodels/repairs, additions, and accessory structures (sheds) over 200 sq ft
  • Plans reviewed against the city/state-adopted IBC/IRC/IECC editions (per Municipal Code 10-2-1's 'current edition as adopted by the state' language) plus City design loads (Seismic Design Category D; 50 psf ground snow load / 35 psf roof snow load; 90/105 mph 3-second-gust wind; 30-inch frost depth; 24-inch ice barrier underlayment)
  • Two full sets of plans (minimum 18in x 24in, maximum 24in x 36in, minimum 1/4-inch scale), pages numbered and stapled, plus a digital PDF for plan review
  • Site plan showing orientation/north arrow, setbacks, lot dimensions, easements, drainage/grading, and all existing/proposed structures
  • Energy Code Compliance: either Option 1 (REScheck Performance Approach compliance report) or Option 2 (Prescriptive Approach: R-38 attic, R-20 exterior walls, R-30 floors or R-13 perimeter walls, .35 U-value Low-E windows), clearly indicated on page 1 of plans
  • Wall bracing design compliant with IRC 602.10; engineered shear design required for any wall exceeding 10 feet tall
  • Manual S & J HVAC load calculations (including fresh-air calculations) submitted with plans
  • Flood Plain Certificate from a licensed engineer required if the property is in a flood plain
  • Project value disclosed (used to calculate the building permit fee via the Building Permit Fee Table); project value includes overhead/profit plus finish work, electrical, plumbing, HVAC, and owner-supplied items, excluding land value
  • Electrical, plumbing, and mechanical/HVAC work requires separate permit applications acquired through the State of Idaho per the City's own Permits & Applications page (which cites dbs.idaho.gov/permits/ -- as of 2026-07-16 this URL redirects to the DOPL homepage rather than a working permits page; the current live equivalents are dopl.idaho.gov/ele/, dopl.idaho.gov/hvac/, and dopl.idaho.gov/plb/) -- NOT obtained from the City Building Department (see codesAdopted conflict note regarding the City's own Fee Schedule also listing City-charged mechanical/electrical/plumbing fees)
  • Apply via the City's online Permit Applications portal or by requesting a paper Residential Building Permit Application from the Building Department

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee -- valuation $0 to $2,000City of Blackfoot Fee Schedule, Resolution No. 425 (effective 10/01/2025), Building Permit Fee Table
$100
Building Permit Fee -- valuation over $2,000 to $25,000City of Blackfoot Fee Schedule, Resolution No. 425
$69.25 for the first $2,000 plus $14.00 for each additional $1,000, or fraction thereof, to and including $25,000
Building Permit Fee -- valuation over $25,000 to $50,000City of Blackfoot Fee Schedule, Resolution No. 425
$391.75 for the first $25,000 plus $10.10 for each additional $1,000, or fraction thereof, to and including $50,000
Building Permit Fee -- valuation over $50,000 to $100,000City of Blackfoot Fee Schedule, Resolution No. 425
$643.75 for the first $50,000 plus $7.00 for each additional $1,000, or fraction thereof, to and including $100,000
Building Permit Fee -- valuation over $100,000 to $500,000City of Blackfoot Fee Schedule, Resolution No. 425
$993.75 for the first $100,000 plus $5.60 for each additional $1,000, or fraction thereof, to and including $500,000
Building Permit Fee -- valuation over $500,000 to $1,000,000City of Blackfoot Fee Schedule, Resolution No. 425
$3,233.75 for the first $500,000 plus $4.75 for each additional $1,000, or fraction thereof, to and including $1,000,000
Building Permit Fee -- valuation over $1,000,000 to $5,000,000City of Blackfoot Fee Schedule, Resolution No. 425
$5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000, or fraction thereof, to and including $5,000,000
Building Permit Fee -- valuation over $5,000,000 to $10,000,000City of Blackfoot Fee Schedule, Resolution No. 425
$20,208.75 for the first $5,000,000 plus $2.75 for each additional $1,000, or fraction thereof, to and including $10,000,000
Building Permit Fee -- valuation over $10,000,000City of Blackfoot Fee Schedule, Resolution No. 425
$33,958.75 for the first $10,000,000 plus $2.00 for each additional $1,000, or fraction thereof
Building Plan Review Fee -- Residential (single family, duplex, townhomes, mobile/manufactured homes)City of Blackfoot Fee Schedule, Resolution No. 425
15% of the Building Permit Fee
Work without a permitCity of Blackfoot Fee Schedule, Resolution No. 425
Double the cost of the permit fee
Re-inspection feeCity of Blackfoot Fee Schedule, Resolution No. 425; required when more than two visits per item are needed or work is not ready at requested time; must be paid before re-inspection is scheduled
$47.00 per inspection
Additional plan reviewCity of Blackfoot Fee Schedule, Resolution No. 425; applies when changes/additions/revisions are made to an approved plan
$47.00 per additional review
Permit Re-instatement FeeCity of Blackfoot Fee Schedule, Resolution No. 425; requestable within one year of permit expiration
Half the cost of the permit fee
Temporary Certificate of OccupancyCity of Blackfoot Residential Building Permit Application; for certain incomplete work under extenuating circumstances
$1,000 refundable fee

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction / Addition / Remodel) permit actually take in Blackfoot?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Prior to concrete pour; verify footing/stem wall dimensions and rebar per the City's 30-inch frost depth and Seismic Design Category D criteria

  2. 2

    Framing

    Structural framing per approved plans, including wall bracing compliance per IRC 602.10

  3. 3

    Final / Certificate of Occupancy

    Final inspection required before Certificate of Occupancy is issued; no occupancy allowed until the Certificate of Occupancy is issued

See the full Blackfoot inspection guide — scheduling & re-inspection fees →

Tips

  • Permits expire 180 days from issuance or the date of the last inspection; reactivation of an expired permit requires a reactivation fee and must be requested from the Building Official. Per the Fee Schedule, the Permit Re-instatement Fee is half the permit fee and must be requested within one year of expiration (does not apply to permits voided for change of ownership).
  • Electrical, plumbing, and mechanical/HVAC permits are stated by the City's own Permits & Applications page to be obtained directly through the State of Idaho, not the City -- but the City's own Fee Schedule (effective 10/01/2025) separately lists detailed City-charged Mechanical, Electrical, and Plumbing permit fee tables, which appears to conflict with that statement. Confirm directly with the Building & Safety Department at (208) 812-4198 which permits (if any) for these trades the City itself issues versus routes to DOPL before assuming either source is authoritative. Note: the City page's own cited URL for state routing (dbs.idaho.gov/permits/) is dead as of 2026-07-16 (redirects to the DOPL homepage); use dopl.idaho.gov/ele/, dopl.idaho.gov/hvac/, or dopl.idaho.gov/plb/ instead, each linking DOPL's online 'Purchase a Permit' tool.
  • The Residential Building Permit Application PDF available on the City's website appears to be an adapted template referencing Twin Falls Highway District and 'SUI zone' language not applicable to Blackfoot/Bingham County, and cites a 2012 IRC/IECC edition that is likely stale given Municipal Code 10-2-1's 'current edition as adopted by the state' language -- treat the specific code-year citation on that form with caution and confirm the currently enforced edition with the Building Official.
  • No City of Blackfoot-published plan-review SLA was found; the only governing published turnaround is the statewide Idaho Code sec 39-4117 completeness-review window (10 business days residential / 20 business days commercial).

Frequently asked questions

Per the City of Blackfoot's own Permits & Applications page, yes -- HVAC, electrical, and plumbing permit applications are obtained directly through the State of Idaho (DOPL), not from the City Building Department. The City's page cites dbs.idaho.gov/permits/, but as of 2026-07-16 that URL redirects to the DOPL homepage rather than a working permits page; use dopl.idaho.gov/ele/ (electrical), dopl.idaho.gov/hvac/ (HVAC), or dopl.idaho.gov/plb/ (plumbing) instead, each with a 'Purchase a Permit' link to DOPL's online permit tool. (Note: the City's own Fee Schedule separately lists City-charged fees for these trades; confirm directly with the Building & Safety Department at (208) 812-4198 to resolve which source governs your specific project.)

In Blackfoot, the published Building Permit Fee -- valuation $0 to $2,000 is: $100. Additional published fees: Building Permit Fee -- valuation over $2,000 to $25,000 — $69.25 for the first $2,000 plus $14.00 for each additional $1,000, or fraction thereof, to and including $25,000; Building Permit Fee -- valuation over $25,000 to $50,000 — $391.75 for the first $25,000 plus $10.10 for each additional $1,000, or fraction thereof, to and including $50,000; Building Permit Fee -- valuation over $50,000 to $100,000 — $643.75 for the first $50,000 plus $7.00 for each additional $1,000, or fraction thereof, to and including $100,000; Building Permit Fee -- valuation over $100,000 to $500,000 — $993.75 for the first $100,000 plus $5.60 for each additional $1,000, or fraction thereof, to and including $500,000; Building Permit Fee -- valuation over $500,000 to $1,000,000 — $3,233.75 for the first $500,000 plus $4.75 for each additional $1,000, or fraction thereof, to and including $1,000,000; Building Permit Fee -- valuation over $1,000,000 to $5,000,000 — $5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000, or fraction thereof, to and including $5,000,000; Building Permit Fee -- valuation over $5,000,000 to $10,000,000 — $20,208.75 for the first $5,000,000 plus $2.75 for each additional $1,000, or fraction thereof, to and including $10,000,000; Building Permit Fee -- valuation over $10,000,000 — $33,958.75 for the first $10,000,000 plus $2.00 for each additional $1,000, or fraction thereof; Building Plan Review Fee -- Residential (single family, duplex, townhomes, mobile/manufactured homes) — 15% of the Building Permit Fee; Work without a permit — Double the cost of the permit fee; Re-inspection fee — $47.00 per inspection; Additional plan review — $47.00 per additional review; Permit Re-instatement Fee — Half the cost of the permit fee; Temporary Certificate of Occupancy — $1,000 refundable fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

All permits expire 180 days from the date of issuance or the date of the last inspection, whichever is later. Expired permits require reactivation, with a reactivation fee (half the original permit fee per the Fee Schedule), requested through the Building Official within one year of expiration.

You'll need: Residential Building Permit Application; Residential Plan Review Checklist; Energy Code Compliance Documentation (REScheck report or Prescriptive Approach specification); Manual S & J HVAC Calculations. Depending on your project, Blackfoot may also ask for: Flood Plain Certificate. See the required-documents checklist on this page for details on each.

Blackfoot requires 3 inspection(s) for a residential building permit (new construction / addition / remodel), in order: Footing/Foundation, Framing, Final / Certificate of Occupancy. Schedule each through City of Blackfoot Building & Safety Department (Building Department) ((208) 812-4198 (Building & Safety Department); (208) 785-8600 opt 3 (Planning & Zoning Department, for permit application requests); (208) 785-8602 (fax, per Residential Building Permit Application form)).

Apply through City of Blackfoot Building & Safety Department (Building Department) at 157 North Broadway, Blackfoot, ID 83221. Phone: (208) 812-4198 (Building & Safety Department); (208) 785-8600 opt 3 (Planning & Zoning Department, for permit application requests); (208) 785-8602 (fax, per Residential Building Permit Application form), email: cclark@cityofblackfoot.org (Chase Clark, Building Official); mmyler@cityofblackfoot.org (Misty Myler, Building Permit Technician). Official information: https://www.cityofblackfoot.org/236/Building-Safety-Department.

Blackfoot, Idaho has adopted: Blackfoot Municipal Code 10-1-1 ('Administrative Code Adopted; Building Department Established') adopts 'the administrative code, current edition as adopted by the state ... published by the International Conference Of Building Officials,' for administration, organization, and enforcement of the technical codes governing site preparation and construction within the city. (2003 Code sec 4-01-01; amd. 2012 Code). Source: Blackfoot Municipal Code 10-1-1, American Legal Publishing (codelibrary.amlegal.com/codes/blackfootid/latest/blackfoot_id/0-0-0-4456).; Blackfoot Municipal Code 10-2-1 ('Building And Residential Codes Adopted') adopts 'the building code, current edition as adopted by the state ... published by the International Conference Of Building Officials' (excepting automatic sprinkler system requirements for 3- and 4-unit Group R buildings) and 'the residential code, current edition as adopted by the state,' as the city's code governing erection, construction, alteration, repair, demolition, occupancy, and permitting of all buildings and structures in the city. (2003 Code sec 4-02-01; amd. 2012 Code). Source: Blackfoot Municipal Code 10-2-1, American Legal Publishing (codelibrary.amlegal.com/codes/blackfootid/latest/blackfoot_id/0-0-0-4470).; Both codified sections tie the city's adopted building/residential code editions to whatever edition 'is adopted by the state' at any given time (i.e., the Idaho Building Code Board / DOPL Building Safety Program's statewide-adopted IBC/IRC cycle under the Idaho Building Code Act, Idaho Code Title 39, Chapter 41), rather than freezing a specific year in the municipal code text itself. No City of Blackfoot source was found stating a specific current IBC/IRC/IECC edition year independent of this 'as adopted by the state' language.; The City's own Residential Building Permit Application / Residential Plan Review Checklist (PDF, cityofblackfoot.org/DocumentCenter/View/89) states plans are to be designed to the '2012 IRC Code & 2012 IECC (with Idaho amendments)' -- however this document appears to be a reused/adapted template (it also references 'Twin Falls Highway District,' 'SUI zone,' and 'Twin Falls' designated flood plain areas,' which are not Blackfoot or Bingham County features), so its cited 2012 IRC/IECC edition year is treated as potentially stale/templated rather than authoritative, and is superseded per Municipal Code 10-2-1's 'current edition as adopted by the state' language. Flagged rather than relied upon for the codesAdopted edition year. Source: City of Blackfoot Residential Building Permit Application (PDF).; Idaho Division of Occupational and Professional Licenses (DOPL), Building Safety Program, administers the statewide building code framework (Idaho Building Code Act, Idaho Code Title 39, Chapter 41) and issues HVAC/mechanical, electrical, and plumbing permits directly for jurisdictions that have not assumed those trades locally. Source: DOPL Building Safety Program overview (dopl.idaho.gov/bld/). [2026-07-16 liveness re-check: the previously-cited 'DOPL Permits portal' at dbs.idaho.gov/permits/ no longer resolves to a permits page -- curl confirms it now 302-redirects to the bare dopl.idaho.gov homepage (not a specific permits/services page), consistent with DOPL's dbs.idaho.gov-to-dopl.idaho.gov domain migration. The live current pages for purchasing Electrical, HVAC, and Plumbing permits are dopl.idaho.gov/ele/, dopl.idaho.gov/hvac/, and dopl.idaho.gov/plb/ respectively, each carrying a 'Purchase a[n] [Trade] Permit' button linking to DOPL's shared ArcGIS-based online permit tool (idaho.maps.arcgis.com/apps/instant/sidebar/index.html?appid=c568d3c03d5f43f0841dcfa9c2a9537e). All three trade pages and the tool's landing shell were fetched live and returned HTTP 200 on 2026-07-16; the ArcGIS tool itself is a JavaScript-rendered app whose internal interactive content could not be verified via curl.]; The City of Blackfoot's own Permits & Applications page states verbatim: 'All HVAC, Electrical and Plumbing permit applications are acquired through the State of Idaho at https://dbs.idaho.gov/permits/.' This directly confirms the prior research's claim that Blackfoot routes mechanical (HVAC), electrical, and plumbing permitting to the state DOPL system rather than self-administering those trades -- the City issues and reviews only the Building Permit (and related general permits: demolition, retaining wall, mobile home block-set, roof repair, fence) itself. Source: City of Blackfoot Permits & Applications page (cityofblackfoot.org/166/Permits-Applications). [2026-07-16 note: this is an accurate quote of the City's own page, but the URL it cites (dbs.idaho.gov/permits/) is itself now dead -- see the live DOPL replacement pages noted in the codesAdopted entry above.]; CONFLICT NOTE (flagged, not resolved by inference): The City of Blackfoot's own Fee Schedule (Resolution No. 425, effective October 1, 2025) contains detailed 'MECHANICAL PERMITS,' 'ELECTRICAL PERMITS,' and 'PLUMBING PERMITS' fee sections with itemized city-charged fees for HVAC units, gas lines, residential/commercial electrical services, and residential/commercial plumbing -- which appears to directly contradict the Permits & Applications page's statement that all HVAC/electrical/plumbing permit applications are 'acquired through the State of Idaho.' Both documents are official City of Blackfoot publications and both were independently verified to resolve/load. This file does not guess which document is authoritative or stale; it reports the Permits & Applications page's explicit routing statement as the department's self-described intake process (consistent with the prior research finding), while separately publishing the Fee Schedule's mechanical/electrical/plumbing fee tables as-is as City-published figures, and flags this discrepancy for a human to resolve with the Building & Safety Department directly at (208) 812-4198. Sources: City of Blackfoot Fee Schedule, Resolution No. 425 (PDF, cityofblackfoot.org/DocumentCenter/View/2021/City-of-Blackfoot-Fee-Schedule-10-01-2025); City of Blackfoot Permits & Applications page (cityofblackfoot.org/166/Permits-Applications).; IRC Section 602.10 (wall bracing) compliance is explicitly required per the City's Residential Building Permit Application: 'All structures are required to be compliant with IRC section 602.10 for wall bracing... Any walls exceeding 10 feet tall are not prescriptive wall bracing and are required to be engineered for shear.' Source: City of Blackfoot Residential Building Permit Application (PDF).. Local amendments apply — see the Blackfoot overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Blackfoot building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.