Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Pocatello, Idaho.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
911 N 7th Avenue, Pocatello, ID 83201 (mailing: PO Box 4169, Pocatello, ID 83205-4169)
Phone
(208) 234-6158
Email
Office hours
Building Official: Marc Howell. Inspection scheduling hotline: (208) 234-6275 / (208) 234-6580 (erosion & sediment control inspections). Permits and Licensing Division: (208) 234-6285. Planning & Development Services (land use, ADUs, zoning): (208) 234-6184.

Published scheduling rules

  • To schedule an inspection, use the eTRAKiT portal (poca.csqrcloud.com/community-etrakit/dashboard.aspx) or the inspection hotline. (Residential Building Permit (New Construction))

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing/Foundation

    Prior to concrete pour; verify footing dimensions/rebar per the Alternative Footing and Foundation Policy (R104.11) for foundation walls, and 3-foot minimum frost depth

  2. 2

    Framing

    Structural framing per approved plans, floor/wall/roof framing, truss and floor joist details

  3. 3

    Erosion and Sediment Control (ESC) — Initial

    Requested prior to beginning grading or excavation; call (208) 234-6580

  4. 4

    Final / Certificate of Occupancy

    Final building, electrical, plumbing, and mechanical verification; final ESC inspection also required for certificate of occupancy (call 208-234-6580)

Applies to: Residential Addition / Remodel / Repair Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for additions or foundation repairs

  2. 2

    Framing

    Structural framing and connections to the existing structure per approved plans

  3. 3

    Final

    All work complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    Prior to covering wiring; verify wiring methods, box fill, and grounding per 2023 NEC

  2. 2

    Final

    Final electrical inspection prior to certificate of occupancy or service energization

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Prior to covering wiring; verify wiring methods, box fill, and grounding per 2023 NEC

  2. 2

    Final

    Charger installed, circuit labeled, final electrical inspection prior to energization

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork, gas piping, and equipment rough-in prior to cover, per 2018 IMC/IFGC

  2. 2

    Final

    Final mechanical inspection including appliance connections and combustion-air/venting verification

Applies to: Plumbing Permit

  1. 1

    Rough-In

    Prior to covering plumbing lines; verify pipe sizing, venting, and materials per the 2017 Idaho State Plumbing Code

  2. 2

    Final

    Final plumbing inspection including fixture connections and water heater installation

Re-inspection fees

Residential Addition / Remodel / Repair PermitRe-inspection · City of Pocatello Building Permit Fees schedule; must be paid prior to re-inspection
$65 per hour

Pocatello building permits

Get alerts for Pocatello

We'll email you when Pocatello's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.