Commercial Building Permit (New Construction) in Pocatello, Idaho
Required for new commercial construction and additions to commercial buildings in Pocatello (any commercial building, and any apartment building with three or more dwelling units, is 'deemed commercial' for fee purposes). Administered by the City of Pocatello Building Department against the 2018 IBC/IEBC and City of Pocatello General Design Specifications, using the same valuation-based Building Permit Fee table as residential construction but a distinct, higher Commercial Plan Review Fee (65% vs. 35%). Applications are submitted through the City's eTRAKiT portal or via the paper Commercial Development Application.
Verified 2026-08-02 · Source
When you need this permit
- Building permit required for new commercial construction and additions to commercial structures; any commercial building, and any apartment/multi-family building with three (3) or more dwelling units, is 'deemed commercial' for City fee-schedule purposes
- Plans reviewed against the 2018 IBC and 2018 IEBC as adopted by the City of Pocatello, plus the 2018 Idaho Administrative Code amendments
- Contractor performing the work must hold a City of Pocatello Class A-1 commercial builder's license ($150 fee; requires $1 Million Liability Combined Single Limit Insurance and a $50,000 License and Permit Bond); Class A-1 also authorizes Class A-2 and Class B work
- Completed Commercial Development Application with legal description, size of parcel, zoning district, existing/proposed use, building type, project description, and total estimated value of commercial construction (excluding lot)
- Commercial Plan Checklist submittal covering: vicinity map, property boundaries/lot-pad dimensions, building locations, parking facilities, rights-of-way/easements/dedications, vehicle/pedestrian/service access, landscaping plan, grading plan, sediment and erosion control plan, storm water drainage plan and calculations, utility locations (Idaho Power must be contacted for consultation if a building is within 20 feet of overhead lines), accessibility-standards compliance, fire access and turnaround (if applicable), floor plans with dimensions, electrical/plumbing/gas/mechanical plans, connection point to public sanitary sewer, elevation/footing/cross-sections, standard notes/details/drawings, and the seal and registration number of a registered professional architect or engineer
- Optional Preliminary plan review stage is available before Final submittal; items marked with an asterisk on the Commercial Plan Checklist are not required for preliminary submittals
- ESC-certified person and ESC certification number required on the application; an individual erosion and sediment control plan is required as part of the checklist
- If the building will be, or is, connected to the sanitary sewer system, a separate Wastewater Discharge Permit must be obtained from the Water Pollution Control Department's Industrial/Commercial Pretreatment Program prior to discharging — there is no fee to submit the wastewater discharge application itself
- Separate Fire and Life Safety system permits (fire hydrant/sprinkler line, fire suppression system, standpipe system, fire alarm system, commercial hood/suppression system, Knox Box) are issued by the Pocatello Fire Prevention Bureau and are NOT part of the Building Department's permit package; issuance of the Fire & Life Safety Certificate of Occupancy is contingent on these inspections passing
- Multiple identical commercial buildings on the same parcel submitted for plan review together require only one Commercial Plan Review Fee, provided site plans showing all building placements/utility placement/site improvements are submitted with the first building's application (plans for each individual building must still be submitted with each application)
- Apply online via the eTRAKiT portal (pocatello.gov/etrakit/, Commercial/Residential Development category) or submit the paper Commercial Development Application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Prior to concrete pour; verify footing/foundation details per approved commercial plans
- 2
Framing
Structural framing per approved plans, including fire-rated assemblies and occupancy-specific requirements
- 3
Fire and Life Safety System Inspections
Separate inspection track administered by the Pocatello Fire Prevention Bureau for any installed/modified fire hydrant/sprinkler lines, fire suppression, standpipe, fire alarm, or commercial hood/suppression systems; not scheduled through the Building Department
- 4
Final / Certificate of Occupancy
Final building, electrical, plumbing, and mechanical verification; a Fire & Life Safety Certificate of Occupancy from the Fire Prevention Bureau is a separate, additional contingency
See the full Pocatello inspection guide — scheduling & re-inspection fees →
Tips
- Commercial Plan Review Fee is 65% of the building permit fee, compared to 35% for residential — confirmed directly on the City's Building Permit Fees page 'Plan Review Fees' table.
- The Commercial Development Application and Commercial Plan Checklist are shared by new construction and remodel/addition/repair work — select the appropriate checkbox (NEW vs. ADDITION/REMODEL/REPAIR/FOUNDATION) on the same form.
- Fire and Life Safety system permits (sprinklers, alarms, hoods, standpipes, Knox Box) are billed and inspected separately by the Pocatello Fire Prevention Bureau, not the Building Department — budget and schedule for them independently; a Fire & Life Safety Certificate of Occupancy is a separate contingency from the building Certificate of Occupancy. Note the source notice for these fees is dated 'Updated: 10/2015' on its face, though it is the current version distributed in the City's live Commercial Development Application packet as of this entry's lastVerified date — contact the Fire Prevention Bureau at (208) 234-6203 to confirm current pricing before budgeting.
- A Wastewater Discharge Permit is required from Water Pollution Control before connecting to the sanitary sewer system; there is no fee to submit the application, but issuing the permit is contingent on inspections passing.
- The City's 'Why Build in Pocatello?' economic-development page states residential and 'small commercial projects can usually be approved without the requirement of professional design' and that the City project review committee will review a project for free — this is promotional/informational copy from a marketing page, not a fee-schedule or checklist document, and it is not the source used for any fee or requirement in this entry; it does not override the Commercial Plan Checklist's listed requirement for an architect/engineer seal and registration number on final commercial submittals, and no small-project size threshold for the design waiver is documented.
- If a building is located within 20 feet of overhead power lines, Idaho Power regulations require contacting them for consultation (208-388-2323), per the Commercial Plan Checklist.
- Multiple identical commercial buildings on the same parcel submitted together for plan review require only one Commercial Plan Review Fee, provided site plans for all buildings are submitted with the first application.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pocatello building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Pocatello.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Pocatello
Commercial Building Permit (New Construction) in other cities
Compare commercial building permit (new construction) fees across Idaho →
Look up this fee in a different city →
Now live
Build your Pocatello project checklist
Describe your project once and get every permit, document, and fee it triggers in Pocatello — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →