New Commercial Building and Commercial Additions Permit (502) — Boise, Idaho · Requirements sheet
Verified 2026-08-02 · Source: https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/commercial-construction-500/502-new-commercial-and-commercial-additions/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
New Commercial Building and Commercial Additions Permit (502) in Boise, Idaho
Required for new commercial building construction and commercial building additions in Boise. Uses the same building-permit valuation table as residential, but a distinct 65% commercial plan review fee, its own Planning pre-approval step, and its own published plan-review SLA.
Verified 2026-08-02 · Source
When you need this permit
- New commercial building construction and commercial building additions require a building permit and plan review approval (Form 502 — New Commercial and Commercial Additions)
- In almost all cases, the Planning Division must pre-approve the land use before a building permit application can be submitted — via Design Review, conditional use, variance, or zoning certificate (contact Planning at (208) 608-7100)
- A prescreen is required before the application is accepted, completed online through ePlanReview, and must include a completed #502 Submittal Checklist and a Verification of Legal Lot or Parcel form signed by the Planning Division
- An accurate certificate of value is required before prescreen approval
- Plans must meet the 2018 IBC, 2018 IEBC, and 2018 IECC as adopted by Boise (see codesAdopted)
- ePlanReview required for digital plan submission; in-person submission also available at 150 N Capitol Blvd
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing
Excavated piers, trenches, forms in place, required reinforcing steel in place — before concrete pour
- 2
Foundation
Forms and required reinforcing steel in place — before concrete pour
- 3
Wall Bracing
Bracing, sheathing, and attachments in place — before weather barrier installation
- 4
Framing/Rough-In
Roof, framing, firestopping, draftstopping, and bracing in place; all trade (electrical/plumbing/mechanical) rough-in inspections approved
- 5
Fire and Smoke Penetrations
Rated/listed joints and penetrations in fire-rated assemblies verified
- 6
Energy Efficiency
Air sealing, insulation, and window performance verified after framing/rough-in, before gypsum board installation
- 7
Fire — Fire Life Safety
Sprinklers, alarms, egress, fire access, and hydrants verified by the Fire Inspector
- 8
Final
All work complete, including any Public Works Drainage inspection and Planning zoning inspection where applicable — required before occupancy
See the full Boise inspection guide — scheduling & re-inspection fees →
Tips
- Commercial plan review is priced very differently from residential: the Building Plan Review Fee is 65% of the building permit fee for commercial work, versus 20% for one- and two-family residential — confirmed both in the Building Code Fee Schedule (item 8) and independently in the #502-B Commercial Guide.
- A Fire Plan Review Fee equal to 16% of the building permit fee may also apply, on top of the 65% Building Plan Review Fee, depending on project scope.
- In almost all cases, Planning Division land-use approval (Design Review, conditional use, variance, or zoning certificate) must be secured BEFORE a commercial building permit application can be submitted — this is a distinct, often longer, upstream process not captured in the plan-review SLA below.
- Boise publishes an actual quarterly plan-review SLA for commercial permits (the Permit Processing Timeframes report) — as of the April–June 2026 report, both New Commercial Buildings & Additions tiers (Level 1 and Level 2) were meeting their published first-review targets, though 'ready to issue' time (after review completes, before permit issuance) runs substantially longer than first-review time for both tiers.
- No separate expedited/express commercial plan-review product (i.e., a paid line-skip) was found on Boise's site as of this research — the only speed-related option confirmed for commercial permits is the optional, no-fee preliminary conference with a plan reviewer before formal submittal.
- The optional preliminary conference (contact (208) 608-7070) is recommended, not required, and helps flag major code-compliance issues before plans are formally submitted.
- After the third plan resubmittal, additional review is billed hourly ($65/hr for commercial, vs $55/hr residential) — keeping resubmittals to a minimum matters more for commercial projects.
- Large/complex commercial projects (Level 2: multi-building, multi-story, podium, high-rise, hospital, hazardous, semiconductor, industrial) are explicitly called out by PDS as its most complex review category and get a longer published target (≤45 days) than standard new commercial (≤30 days).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Boise.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Boise
New Commercial Building and Commercial Additions Permit (502) in other cities
Compare new commercial building and commercial additions permit (502) fees across Idaho →
Look up this fee in a different city →
Now live
Build your Boise project checklist
Describe your project once and get every permit, document, and fee it triggers in Boise — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →