Residential Addition / Alteration Permit in Boise, Idaho

Required for additions, structural alterations, remodels, basement finishes, decks over 12 inches above grade, retaining walls over 4 feet, and other residential alterations in Boise.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit — valuation-based per Table 1-ASame valuation table as new construction: $26.37 + $2.95/$100 (up to $2,000); $70.76 + $12.71/$1,000 ($2,001–$25,000); $362.80 + $9.30/$1,000 ($25,001–$50,000); etc.Boise Building Code Fee Schedule, Table 1-A
Residential Plan Review20% of the building permit feePer Boise Building Code Fee Schedule item 9
Reinspection Fee$55 per occurrence

Review timeline

127 business days

Boise’s published plan-review target

Inspection process

  1. 1

    Framing / Structural

    After framing is complete and before walls are covered — verify structure, connections, and blocking

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before wall cover — may be separate trade permits

  3. 3

    Insulation

    Insulation installed, vapor barrier in place — before drywall

  4. 4

    Final

    All work complete per approved plans

Tips

Frequently asked questions

Does a deck require a permit in Boise?
Yes, if the deck is more than 12 inches above grade. Apply for a Residential Addition/Alteration (406) permit online at permits.cityofboise.org or in person.
Do I need a permit to finish my basement in Boise?
Yes. Any basement finish involving framing, electrical, plumbing, or mechanical work requires a building permit (406) plus trade sub-permits as applicable.
How long does an addition/alteration permit take in Boise?
Per Boise's March–May 2026 timeframe report, Level 1 additions/alterations average 1 business day for first review. Level 2 projects average 8 business days (target: under 10 days). Ready-to-issue time averages 6–27 days depending on level.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Boise

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.