Tenant Improvement Permit — Minor (518) and Major (520) in Boise, Idaho

Required for alterations to existing commercial spaces in Boise. Minor Tenant Improvement (518) covers Level 1 (existing tenant space remodels) and Level 2 (new tenant space build-outs and existing tenant space remodels); Major Tenant Improvement (520, 'Level 3') covers any TI project that exceeds Minor scope, with staff holding final discretion over the classification.

Verified 2026-08-02 · Source

When you need this permit

  • Minor TI Level 1 — Existing Tenant Space Remodel (10 working days or less first review): offices, restaurants with an occupant load of 49 or less, and retail sales tenants with an existing Certificate of Occupancy; limited scope; minor exterior work only if previously approved by PDS Planning; not an historic building; minor structural work only; NOT allowed: increase to building area, tenant space, or occupant load, change of occupancy/use, hazardous material storage/dispensing, building upgrade agreement items, or a first-time tenant improvement
  • Minor TI Level 2 — New Tenant Space Build-Out and Existing Tenant Space Remodels (15 working days or less first review): new finish for offices, retail sales, and storage occupancies; limited remodel to existing offices/retail/storage tenant spaces; change of restaurant tenants; same exterior/historic/structural constraints as Level 1; NOT allowed: increase to building area, change of occupancy/use, hazardous material storage/dispensing, building upgrade agreement items
  • Major TI (520) — any tenant improvement that goes beyond Minor Level 1/2 scope; PDS staff has final discretion to classify a project as Minor or Major; the 520 application packet also covers converting a dwelling to commercial space
  • In some cases (e.g., exterior site/building modifications), prior Planning Division pre-approval is required before submitting the building permit application
  • A prescreen is required through ePlanReview before the application is accepted
  • An Early Start TI Permit (IBC 107.3.3.1 as amended by Boise City Code) may be requested for nonstructural interior framing in retail, office, or warehouse space storing only non-hazardous materials, letting construction begin — up to the framing inspection stage only — before the full plan review is complete; not available for structural or exterior work; requires a complete full TI application plus a separate early-start application submitted together

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation-based per Table 1-ABoise Building Code Fee Schedule, Table 1-A (Oct 2023)
Same valuation schedule as new commercial construction: $26.37 + $2.95/$100 (up to $2,000); $70.76 + $12.71/$1,000 ($2,001–$25,000); $362.80 + $9.30/$1,000 ($25,001–$50,000); $595.30 + $6.35/$1,000 ($50,001–$100,000); $913.09 + $5.17/$1,000 ($100,001+)
Building Plan Review FeeBoise Building Code Fee Schedule item 8 (Oct 2023); confirmed independently in both the #518-B and #520-B guides
65% of the building permit fee
Fire Plan Review Fee (where applicable)Per the #518-B and #520-B guides; applies depending on project scope
16% of the building permit fee
Additional plan review after the third resubmittalBoise Building Code Fee Schedule item 6 (Oct 2023)
$65 per hour (commercial rate), 1-hour minimum
Early Start TI PermitPer the Early Start Tenant Improvement Permit Process Policy (effective 12/21/21); the policy references the Fee Schedule's hourly plan-review rate but does not itemize a distinct flat dollar figure
Billed at the hourly plan review rate under the Building Code Fee Schedule; a separate interior-demolition fee (valuation-based) is added if demolition is included in the early-start scope
Reinspection Fee
$55
Erosion & Sediment Control Permit FeeContact the Permit Counter at (208) 608-7070 for an estimate; per the #518 Submittal Checklist and the Building Inspections page
Variable — applies to TI projects with exterior work and a ground-floor addition greater than 500 sq ft, or more than 2,500 sq ft of soil disturbance
ACHD Impact Fees(208) 387-6100
Variable — determined and collected separately by the Ada County Highway District
Boise City Parks, Fire & Police Impact Fees(208) 608-8133 or (208) 972-8192
Variable — contact the Impact Fee Administrator

Review timeline

Plan reviewBoise’s published plan-review target
8–47 business days

How long did your Tenant Improvement Permit — Minor (518) and Major (520) permit actually take in Boise?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing/Rough-In

    Framing, firestopping, and draftstopping in place; coordinates with all trade (electrical/plumbing/mechanical) rough-in inspections, which are scheduled under separate trade permits

  2. 2

    Fire and Smoke Penetrations

    Rated/listed joints and penetrations verified where the TI scope affects fire-rated walls, partitions, or ceilings

  3. 3

    Ceiling Grid

    Bracing verified before ceiling panels are installed — required only if a new suspended grid ceiling is part of the scope

  4. 4

    Erosion & Sediment Control Site Final

    Required only for TI projects with exterior work and a ground-floor addition greater than 500 sq ft — landscaping/stabilization and removal of temporary controls verified

  5. 5

    Final

    All work complete per approved plans, ready for occupancy

See the full Boise inspection guide — scheduling & re-inspection fees →

Tips

  • PDS staff — not the applicant — has final discretion over whether a project qualifies as Minor (518) or Major (520) Tenant Improvement; a project that looks 'minor' in scope can still be routed to the Major TI track.
  • Both Minor and Major TI share the same 65% commercial Building Plan Review Fee and potential 16% Fire Plan Review Fee as new commercial construction — 'Minor' in Minor TI refers to scope, not to a discounted fee structure.
  • The Early Start TI Permit is Boise's closest thing to an expedited option for tenant improvements: it lets nonstructural interior framing begin (up to the framing inspection stage) in retail/office/warehouse space with non-hazardous storage while the full plan review is still underway — but it is not available for structural or exterior work, and the applicant proceeds at their own risk beyond framing.
  • No separate paid 'express review' product (a true line-skip, distinct from Early Start) was found on Boise's site for tenant improvement permits as of this research.
  • Minor TI Level 1 explicitly excludes 'first-time tenant improvements' — i.e., it's for re-permitting a space that already has an existing Certificate of Occupancy, not build-outs of vacant shell space.
  • Interior TI work in spaces of 1,500 sq ft or less (for most occupancy groups, where no change of use/occupancy occurs) may qualify for an exception to the architectural-stamp requirement — plans can be prepared by others per the #518 Submittal Checklist exceptions.
  • 'Ready to issue' time — the wait after plan review is complete but before the permit is actually issued — runs 2-3x longer than first-review time at every TI level per the City's own quarterly report, so first-review speed alone understates total time to permit.

Frequently asked questions

Boise requires a tenant improvement permit — minor (518) and major (520) for: Minor TI Level 1 — Existing Tenant Space Remodel (10 working days or less first review): offices, restaurants with an occupant load of 49 or less, and retail sales tenants with an existing Certificate of Occupancy; limited scope; minor exterior work only if previously approved by PDS Planning; not an historic building; minor structural work only; NOT allowed: increase to building area, tenant space, or occupant load, change of occupancy/use, hazardous material storage/dispensing, building upgrade agreement items, or a first-time tenant improvement; Minor TI Level 2 — New Tenant Space Build-Out and Existing Tenant Space Remodels (15 working days or less first review): new finish for offices, retail sales, and storage occupancies; limited remodel to existing offices/retail/storage tenant spaces; change of restaurant tenants; same exterior/historic/structural constraints as Level 1; NOT allowed: increase to building area, change of occupancy/use, hazardous material storage/dispensing, building upgrade agreement items; Major TI (520) — any tenant improvement that goes beyond Minor Level 1/2 scope; PDS staff has final discretion to classify a project as Minor or Major; the 520 application packet also covers converting a dwelling to commercial space; In some cases (e.g., exterior site/building modifications), prior Planning Division pre-approval is required before submitting the building permit application; A prescreen is required through ePlanReview before the application is accepted; An Early Start TI Permit (IBC 107.3.3.1 as amended by Boise City Code) may be requested for nonstructural interior framing in retail, office, or warehouse space storing only non-hazardous materials, letting construction begin — up to the framing inspection stage only — before the full plan review is complete; not available for structural or exterior work; requires a complete full TI application plus a separate early-start application submitted together. If your project isn't listed, confirm with Boise Planning and Development Services — Building Division at (208) 608-7070 before starting work.

In Boise, the published Building Permit — valuation-based per Table 1-A is: Same valuation schedule as new commercial construction: $26.37 + $2.95/$100 (up to $2,000); $70.76 + $12.71/$1,000 ($2,001–$25,000); $362.80 + $9.30/$1,000 ($25,001–$50,000); $595.30 + $6.35/$1,000 ($50,001–$100,000); $913.09 + $5.17/$1,000 ($100,001+). Additional published fees: Building Plan Review Fee — 65% of the building permit fee; Fire Plan Review Fee (where applicable) — 16% of the building permit fee; Additional plan review after the third resubmittal — $65 per hour (commercial rate), 1-hour minimum; Early Start TI Permit — Billed at the hourly plan review rate under the Building Code Fee Schedule; a separate interior-demolition fee (valuation-based) is added if demolition is included in the early-start scope; Reinspection Fee — $55; Erosion & Sediment Control Permit Fee — Variable — applies to TI projects with exterior work and a ground-floor addition greater than 500 sq ft, or more than 2,500 sq ft of soil disturbance; ACHD Impact Fees — Variable — determined and collected separately by the Ada County Highway District; Boise City Parks, Fire & Police Impact Fees — Variable — contact the Impact Fee Administrator. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per Boise's April–June 2026 Permit Processing Timeframes report: TI Level 1 (Minor, existing-space remodel) averaged 8 working days first review; Level 2 (Minor, new build-out) averaged 14 days; Level 3 (Major) averaged 19 days. All three were within or at their published targets. Ready-to-issue time after review is substantially longer — averaging 16, 45, and 47 days respectively.

You'll need: Application #518 (Minor) or #520 (Major) — Tenant Improvement Permit; Submittal Checklist (#518 Minor or #520 Major, April 2025); Form #304 — Registered Design Professional in Charge. Depending on your project, Boise may also ask for: Central District Health Department (CDHD) Food Establishment forms; ACHD Impact Fee Assessment and Tenant Improvement Submittal Form; Planning & Zoning letters of approval; Commercial Photovoltaic / Solar Thermal Systems Checklist (520 only). See the required-documents checklist on this page for details on each.

Boise requires 5 inspection(s) for a tenant improvement permit — minor (518) and major (520), in order: Framing/Rough-In, Fire and Smoke Penetrations, Ceiling Grid, Erosion & Sediment Control Site Final, Final. Schedule each through Boise Planning and Development Services — Building Division ((208) 608-7070).

Apply through Boise Planning and Development Services — Building Division at 150 N Capitol Blvd, Boise, ID 83702. Phone: (208) 608-7070, email: permits@cityofboise.org. Office hours: Mon–Fri 8:00 AM – 5:00 PM (closed holidays). Official information: https://www.cityofboise.org/departments/planning-and-development-services/building/.

Minor Tenant Improvement (518) covers two levels: Level 1 (existing tenant space remodels with a Certificate of Occupancy already in place, limited scope, no increase to building area/occupant load/hazmat storage) and Level 2 (new tenant space build-outs and existing-space remodels, no increase to building area or change of occupancy). Major Tenant Improvement (520) covers anything beyond that scope, including dwelling-to-commercial conversions. PDS staff makes the final call on classification.

Possibly, via an Early Start TI Permit. It allows nonstructural interior framing work in retail, office, or warehouse space (storing only non-hazardous materials) to begin — up to the framing inspection stage — while the full plan review is still in progress. It requires a separate application submitted alongside the full TI application, is billed at the hourly plan-review rate, and is not available for structural or exterior work.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.