Solar Photovoltaic (PV) Permit in Boise, Idaho

Required for installation of rooftop or ground-mounted solar photovoltaic systems on residential properties in Boise. Requires both a building permit for structural mounting (flat $165 fee) and a separate electrical permit for wiring ($110 for the electrical portion on existing residences).

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Residential Solar PV — building permit (plan review/inspections)$165 flat feeBoise Building Code Fee Schedule item 11 (Oct 2023): 'Residential Solar Photovoltaic Systems plan review/inspections permit fee: $165'
Residential Solar PV — electrical permit (installation on existing residence)$110 (up to two inspections)Boise Electrical Code Fee Schedule, Table 3-a: 'Installation of solar panels: (up to two inspections) $110'

Review timeline

~110 business days

Typical estimate — confirm current times with the Boise building department

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final — Building / Structural

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    Electrical connections, inverter installation, and interconnection point verified

Tips

Frequently asked questions

How much does a solar permit cost in Boise?
Boise charges a flat $165 building permit fee for residential solar PV systems (covers plan review and inspections). A separate electrical permit costs $110 for the wiring portion. Total minimum permit cost is $275.
Do I need two permits for solar panels in Boise?
Yes. You need a building permit (406 with PV checklist, $165 flat fee) for the structural mounting and a separate electrical permit (424, $110) for the wiring. Both are required before work begins.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Boise

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.