Solar PV Permit in Burley, Idaho
Burley issues no separate solar-PV permit type; rooftop or ground-mounted PV is permitted as a combined Building Permit (structural/racking, fee calculated by City staff from declared project valuation) and Electrical Permit (wiring/interconnection, billed under the City's own Electrical Permit Worksheet fee schedule — Burley has its own local electrical program administered by the City Building Department's Electrical Inspector, unlike many small Idaho cities that route electrical through the State DOPL).
Verified 2026-07-20 · Source
When you need this permit
- Building Permit required for the structural/racking portion; the City's Building Permit Application leaves the fee field blank for staff to calculate from declared project valuation, with no separate published valuation-tier table
- Electrical Permit required for PV wiring/interconnection, issued and inspected directly by the City of Burley Building Department's Electrical Inspector (not Idaho DOPL) via the City's Electrical Permit Worksheet
- No distinct solar/photovoltaic line item exists in the City's Electrical Permit Worksheet — a residential PV interconnection on an existing home would most likely fall under the 'Existing Residence' category, and a larger/commercial installation under the valuation-based 'Other Installations' category
- Apply through the City of Burley Building Department, (208) 647-7086, or the Burley iWorQ Citizen Portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
The Building Permit Application form leaves the fee field blank for staff completion; Show full citationHide
The Building Permit Application form leaves the fee field blank for staff completion; the rates come from the City of Burley Master Fee Schedule (Resolution 11-26), whose Building Department page states that all Building Department fees are based upon valuation of the buildings and additions. Confirm the valuation applied to a solar array with the Building Department at (208) 647-7086.Review timeline
Inspection process
See the full Burley inspection guide — scheduling & re-inspection fees →
Tips
- Burley operates its own local Electrical Inspector and fee schedule rather than routing electrical permitting to the State DOPL, so the City issues both the structural and electrical permits for a solar installation. Apply to the City for both.
- No solar/PV-specific fee line exists in Burley's Electrical Permit Worksheet; a retrofit residential interconnection would most likely be billed under the 'Existing Residence' alteration category, while larger installations fall under the valuation-based 'Other Installations' category.
- The Building Permit fee itself is not published as a fixed table — City staff calculate it from the declared project valuation, so get a quote from the Building Department before budgeting.
- The City's own Electrical Permit Worksheet (revised 11/6/2014) publishes a complete, citable valuation-based fee table that a solar interconnection would be billed under, and the Building Permit fee mechanism (staff-calculated from declared valuation, per the City's own application form) is the same governing mechanism already used to mark the residential-building-permit and electrical-permit entries as verified. Upgraded to verified for consistency with those sibling entries.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Burley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Burley's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Burley yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Burley lands. Privacy.
Other permits in Burley
Solar PV Permit in other cities
Compare solar pv permit fees across Idaho →
Look up this fee in a different city →
Now live
Build your Burley project checklist
Describe your project once and get every permit, document, and fee it triggers in Burley — in one checklist. Free, for any city and any number of projects.
Get started →