Photovoltaic Project Permit — Buhl, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://www.cityofbuhl.us/uploads/4/7/1/1/47114749/solar_permit_application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Photovoltaic Project Permit in Buhl, Idaho
Required for installation of roof- or ground-mounted photovoltaic array systems in Buhl. The City publishes a dedicated Photovoltaic Project Permit Application with a detailed submittal checklist; the City of Buhl oversees the structural building permit only, billed under the standard 1997 Uniform Code valuation-based fee table (no distinct solar/PV fee line), while electrical, mechanical, and plumbing work require separate permits from the Idaho Division of Occupational & Professional Licenses (IDOPL), which have their own fee schedules.
Verified 2026-07-20 · Source
When you need this permit
- Contact Idaho Power before starting a solar project regarding the net metering application (Scott Gates, 208-888-2518 or netmetering@idahopower.com); Idaho Power conducts a system test after the system passes the State electrical inspection
- Separate applications and fee schedules are required for electrical, mechanical, and plumbing work — obtained through the Idaho Division of Occupational & Professional Licenses (IDOPL), not the City
- Panels and modules must be installed by a certified contractor; the State of Idaho requires a licensed electrical journeyman to complete installation beyond the converter box/AC combiner box
- Site plan required showing the PV array location/layout, electrical equipment (service, sub-panels, back-fed panels, disconnects, inverters, battery backup), outside conduit routes, and the required Rapid Shutdown Device location per NEC 690.12
- Roof plan required showing dimensions from the array to roof ridges/valleys/hips/edges, with required setbacks and access pathways (e.g., hip roofs: 3' wide clear access pathway from eave to ridge on each slope with panels)
- Structural analysis stamped by a licensed Idaho Structural Engineer required, based on International Existing Building Code Article 1103.1 (Additional Gravity Loads)
- Comprehensive one-line electrical diagram required per NEC Article 690 (General Requirements, Circuit Requirements, Disconnecting Means, Wiring Methods, Grounding, Marking, Connection to Other Sources, Energy Storage Systems), including Point of Connection type and NEC 705 load calculations
- Equipment submittals (manufacturer specs, UL listings) required for all PV equipment, racking, and grounding systems
- Pictures of existing service equipment (covers on and off) required, showing existing wiring and data labels
- Rough-In (midpoint) and Final inspections required
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough In
Called at the midpoint of installation
- 2
Final
Final inspection; Idaho Power also conducts its own system test after the State electrical inspection passes
Tips
- Buhl's Photovoltaic Project Permit Application is one of the most detailed solar-specific checklists in the region, covering site plan, roof plan with roof-type-specific access pathway diagrams (hip, single-ridge, hip-and-valley roofs), structural analysis, one-line diagram, equipment submittals, and existing-service photos — but it does not carry its own dedicated fee; the structural portion is billed on the City's standard valuation-based table.
- Three separate permits are effectively required: City structural Building Permit, plus State of Idaho (IDOPL) Electrical Permit and any needed Mechanical/Plumbing permits, each with their own fee schedule.
- Contact Idaho Power before starting the project for the net metering application — this is a distinct step from both the City and State permits.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Buhl building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Buhl
Photovoltaic Project Permit in other cities
Compare photovoltaic project permit fees across Idaho →
Look up this fee in a different city →