Tenant Improvement / Commercial Tenant Finish Permit in Greeley, Colorado

Required for interior build-out, alteration, or finish work in existing commercial space in Greeley, governed by the 2021 International Building Code (IBC, Sec. 22-31) and 2021 International Existing Building Code (IEBC, Sec. 22-236) as adopted. The City routes this work into a distinct 'Tenant finish' plan-review track (10 working days, verified) that is separate from both new commercial construction (20 working days) and the general 'Commercial or residential additions/remodels' track (also 10 working days). Uses the same valuation-based Building Permit Fee Schedule as all other Greeley building permits. Applications are submitted through eTRAKiT.

Verified 2026-08-02 · Source

When you need this permit

  • Building permit required for tenant finish, interior build-out, or alteration of existing commercial space affecting structural, fire, or life-safety elements, or a change of occupancy classification, under the 2021 IBC and 2021 IEBC as adopted (Greeley Municipal Code Secs. 22-31, 22-236)
  • Estimated project valuation must be provided at application; the building official may use the ICC Building Valuation Data square-foot table if the stated valuation appears understated (Sec. 22-34)
  • Application submitted online via eTRAKiT (trakit.greeleygov.com/etrakit/); a 2.8% convenience fee applies to credit card payments (no fee for eCheck), effective March 14, 2022
  • Project is added to the City's 'Tenant finish' plan-review list — a track the City publishes as distinct from both 'New commercial project plan review' (20 working days) and 'Additions/remodels plan review' (10 working days), even though tenant finish and additions/remodels share the same 10-working-day duration
  • The $75 flat Minor Plan Review Fee (Fee Schedule item 7) is worded to cover 'residential and commercial additions, remodels, and utility buildings under 1,000 sq ft' — it does not separately name 'tenant finish' as a category, so it is unconfirmed whether a small tenant-finish scope qualifies for the $75 minor fee versus the 65% major plan review fee; confirm classification with Building Inspection (970-350-9830) for projects under 1,000 sq ft
  • No separate tenant-improvement-specific application, checklist, or plan-submittal guide is published by the City beyond the standard eTRAKiT Building Permit Application — confirmed by direct review of the Building Permits and Inspections page's 'Project Documents' resource list, which contains only residential-scoped guides
  • Accessible route and plumbing-fixture compliance per the adopted 2017 ICC A117.1 Accessibility Code applies to commercial tenant finish work

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based (same Table 1-A schedule as all other building permits)City of Greeley 2024 Building Permit Fee Schedule; no separate tenant-improvement-only fee table is published
$23.50 minimum ($1-$500 valuation), scaling per the City's 2024 Building Permit Fee Schedule Table 1-A
Minor Plan Review Fee — residential/commercial additions, remodels, utility buildings under 1,000 sq ftCity of Greeley 2024 Building Permit Fee Schedule, item 7; wording does not explicitly name 'tenant finish' as a qualifying category — confirm applicability for small-scope tenant finish with Building Inspection
$75.00 flat
Plan Review Fee (Major)City of Greeley 2024 Building Permit Fee Schedule, item 6; applies to tenant-finish projects not qualifying for the $75 minor fee
65% of the building permit fee
City Sales TaxCity of Greeley 2024 Building Permit Fee Schedule
4.11% of 50% of total construction value

Review timeline

Plan reviewGreeley’s published plan-review target
10–10 business days

How long did your Tenant Improvement / Commercial Tenant Finish Permit permit actually take in Greeley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing/Partition

    New interior partition framing, fire-rated assemblies, and connections to existing structure per approved plans

  2. 2

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in, including any fire alarm or sprinkler tie-in, before concealment

  3. 3

    Final

    Final inspection and approval of all systems before occupancy; certificate of occupancy required before final occupancy (2021 IBC Sec. 110.6 as amended)

See the full Greeley inspection guide — scheduling & re-inspection fees →

Tips

  • Greeley publishes tenant finish as its own named review track, distinct from the generic 'Additions/remodels' commercial track, even though both run 10 working days — use the term 'tenant finish' when confirming status with Building Inspection, since the City's own process language distinguishes it from other commercial alteration work.
  • There is no dedicated tenant-improvement application, checklist, or plan-submittal guide published by the City — tenant finish projects use the same eTRAKiT Building Permit Application and the same valuation-based Table 1-A fee schedule as new construction.
  • It is unconfirmed whether the $75 flat Minor Plan Review Fee (explicitly worded for 'additions, remodels, and utility buildings under 1,000 sq ft') extends to small tenant-finish scopes, since the fee schedule does not separately name 'tenant finish' — confirm before budgeting a small build-out.
  • A change of occupancy classification (e.g., converting retail space to a restaurant or assembly use) triggers 2021 IEBC review (Sec. 22-236) in addition to the IBC, and may require additional life-safety upgrades to the existing space.

Frequently asked questions

Greeley requires a tenant improvement / commercial tenant finish permit for: Building permit required for tenant finish, interior build-out, or alteration of existing commercial space affecting structural, fire, or life-safety elements, or a change of occupancy classification, under the 2021 IBC and 2021 IEBC as adopted (Greeley Municipal Code Secs. 22-31, 22-236); Estimated project valuation must be provided at application; the building official may use the ICC Building Valuation Data square-foot table if the stated valuation appears understated (Sec. 22-34); Application submitted online via eTRAKiT (trakit.greeleygov.com/etrakit/); a 2.8% convenience fee applies to credit card payments (no fee for eCheck), effective March 14, 2022; Project is added to the City's 'Tenant finish' plan-review list — a track the City publishes as distinct from both 'New commercial project plan review' (20 working days) and 'Additions/remodels plan review' (10 working days), even though tenant finish and additions/remodels share the same 10-working-day duration; The $75 flat Minor Plan Review Fee (Fee Schedule item 7) is worded to cover 'residential and commercial additions, remodels, and utility buildings under 1,000 sq ft' — it does not separately name 'tenant finish' as a category, so it is unconfirmed whether a small tenant-finish scope qualifies for the $75 minor fee versus the 65% major plan review fee; confirm classification with Building Inspection (970-350-9830) for projects under 1,000 sq ft; No separate tenant-improvement-specific application, checklist, or plan-submittal guide is published by the City beyond the standard eTRAKiT Building Permit Application — confirmed by direct review of the Building Permits and Inspections page's 'Project Documents' resource list, which contains only residential-scoped guides; Accessible route and plumbing-fixture compliance per the adopted 2017 ICC A117.1 Accessibility Code applies to commercial tenant finish work. If your project isn't listed, confirm with City of Greeley Building Inspection (Community Development) at (970) 350-9830 before starting work.

In Greeley, the published Building Permit Fee — valuation-based (same Table 1-A schedule as all other building permits) is: $23.50 minimum ($1-$500 valuation), scaling per the City's 2024 Building Permit Fee Schedule Table 1-A. Additional published fees: Minor Plan Review Fee — residential/commercial additions, remodels, utility buildings under 1,000 sq ft — $75.00 flat; Plan Review Fee (Major) — 65% of the building permit fee; City Sales Tax — 4.11% of 50% of total construction value. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

10 working days, per the City's published 'Commercial timeline' on the Building Permits and Inspections page ('Tenant finish plan review - 10 working days'), distinct from the 20-working-day new commercial construction track.

You'll need: Building Permit Application; Construction Drawings. Depending on your project, Greeley may also ask for: IEBC Compliance / Change-of-Occupancy Documentation. See the required-documents checklist on this page for details on each.

Greeley requires 3 inspection(s) for a tenant improvement / commercial tenant finish permit, in order: Framing/Partition, MEP Rough-In, Final. Schedule each through City of Greeley Building Inspection (Community Development) ((970) 350-9830).

Apply through City of Greeley Building Inspection (Community Development) at 1100 10th Street, Greeley, CO 80631. Phone: (970) 350-9830, email: Building.Inspection@greeleygov.com. Office hours: Monday - Friday, 7:00 AM - 5:00 PM; appointments strongly recommended (Building Inspections, 1100 10th Street, Greeley, CO 80631). Official information: https://greeleyco.gov/business/construction-and-growth/building-permits-and-inspections.

Greeley, Colorado has adopted: Colorado is a home-rule state: there is no single mandatory statewide building code edition — each municipality adopts and amends its own codes. The only statewide floors are the building energy code (HB22-1362, effective 7/1/2023, requiring local governments that adopt an energy code to meet or exceed a specified electric- and solar-ready code baseline) and specific state statutes (e.g., ADU enabling legislation). Confirm your city's own adopted edition; this file documents Greeley's own program, verified directly from the Greeley Municipal Code (Title 22) via library.municode.com/co/greeley.; City of Greeley runs its own Building Inspection Division (part of Community Development) and administers its own permitting within Greeley city limits — it is not a Weld County program. Source: City of Greeley Building Permits and Inspections page.; 2021 International Building Code (IBC) — adopted by reference, Greeley Municipal Code Sec. 22-31, effective 1-1-2023 per Ord. No. 25, 2022; 2021 International Residential Code (IRC) — adopted by reference, Sec. 22-76, effective 1-1-2023 per Ord. No. 25, 2022; governs detached one- and two-family dwellings and townhouses up to 3 stories; 2021 International Existing Building Code (IEBC) — adopted by reference, Sec. 22-236, effective 1-1-2023; 2021 International Property Maintenance Code (IPMC) — adopted by reference, Sec. 22-192, effective 1-1-2023; 2021 International Mechanical Code (IMC) — adopted by reference, Sec. 22-161, effective 1-1-2023; 2021 International Plumbing Code (IPC) — adopted by reference, Sec. 22-306, effective 1-1-2023 (Greeley uses the International Plumbing Code, NOT the Uniform Plumbing Code); 2021 International Fuel Gas Code (IFGC) — adopted by reference, Sec. 22-347, effective 1-1-2023; 2021 International Energy Conservation Code (IECC) — adopted by reference, Sec. 22-286, effective 1-1-2023; 2021 International Fire Code (IFC) — adopted by reference, Sec. 22-454, effective 1-1-2023, with local amendments including NFPA 855-20 (stationary energy storage systems) and added Appendices B and C (fire-flow requirements, hydrant locations); 2023 National Electrical Code (NEC/NFPA 70) — adopted by reference, Sec. 22-377, per Ord. No. 37, 2023 (9-19-2023); superseded the previously adopted 2020 NEC; 2017 ICC A117.1 Accessibility Code — referenced on the City's Building Inspection Resources / Code Information page; All codes amended per Greeley Municipal Code Title 22 (Buildings and Construction), Chapters 2-12; consolidated under Ord. No. 25, 2022 (adoptions effective 1-1-2023) with the electrical code separately updated to the 2023 NEC by Ord. No. 37, 2023; Source: Greeley Municipal Code, Title 22, via library.municode.com/co/greeley (Chapters 2-12), cross-verified against the City's Building Permits and Inspections page 'Code Information' list. Local amendments apply — see the Greeley overview page for the full list.

Yes. The City's Building Permits and Inspections page names 'Tenant finish' as its own plan-review track, separate from new commercial construction and from the general commercial/residential additions-remodels track, with a published 10-working-day plan review timeline. It uses the same eTRAKiT application and valuation-based fee schedule as other building permits — there is no dedicated tenant-improvement application form or fee table.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Greeley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.