Tenant Improvement / Commercial Tenant Finish Permit — Greeley, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://greeleyco.gov/business/construction-and-growth/building-permits-and-inspections
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Tenant Improvement / Commercial Tenant Finish Permit in Greeley, Colorado
Required for interior build-out, alteration, or finish work in existing commercial space in Greeley, governed by the 2021 International Building Code (IBC, Sec. 22-31) and 2021 International Existing Building Code (IEBC, Sec. 22-236) as adopted. The City routes this work into a distinct 'Tenant finish' plan-review track (10 working days, verified) that is separate from both new commercial construction (20 working days) and the general 'Commercial or residential additions/remodels' track (also 10 working days). Uses the same valuation-based Building Permit Fee Schedule as all other Greeley building permits. Applications are submitted through eTRAKiT.
Verified 2026-08-02 · Source
When you need this permit
- Building permit required for tenant finish, interior build-out, or alteration of existing commercial space affecting structural, fire, or life-safety elements, or a change of occupancy classification, under the 2021 IBC and 2021 IEBC as adopted (Greeley Municipal Code Secs. 22-31, 22-236)
- Estimated project valuation must be provided at application; the building official may use the ICC Building Valuation Data square-foot table if the stated valuation appears understated (Sec. 22-34)
- Application submitted online via eTRAKiT (trakit.greeleygov.com/etrakit/); a 2.8% convenience fee applies to credit card payments (no fee for eCheck), effective March 14, 2022
- Project is added to the City's 'Tenant finish' plan-review list — a track the City publishes as distinct from both 'New commercial project plan review' (20 working days) and 'Additions/remodels plan review' (10 working days), even though tenant finish and additions/remodels share the same 10-working-day duration
- The $75 flat Minor Plan Review Fee (Fee Schedule item 7) is worded to cover 'residential and commercial additions, remodels, and utility buildings under 1,000 sq ft' — it does not separately name 'tenant finish' as a category, so it is unconfirmed whether a small tenant-finish scope qualifies for the $75 minor fee versus the 65% major plan review fee; confirm classification with Building Inspection (970-350-9830) for projects under 1,000 sq ft
- No separate tenant-improvement-specific application, checklist, or plan-submittal guide is published by the City beyond the standard eTRAKiT Building Permit Application — confirmed by direct review of the Building Permits and Inspections page's 'Project Documents' resource list, which contains only residential-scoped guides
- Accessible route and plumbing-fixture compliance per the adopted 2017 ICC A117.1 Accessibility Code applies to commercial tenant finish work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing/Partition
New interior partition framing, fire-rated assemblies, and connections to existing structure per approved plans
- 2
MEP Rough-In
Mechanical, electrical, and plumbing rough-in, including any fire alarm or sprinkler tie-in, before concealment
- 3
Final
Final inspection and approval of all systems before occupancy; certificate of occupancy required before final occupancy (2021 IBC Sec. 110.6 as amended)
See the full Greeley inspection guide — scheduling & re-inspection fees →
Tips
- Greeley publishes tenant finish as its own named review track, distinct from the generic 'Additions/remodels' commercial track, even though both run 10 working days — use the term 'tenant finish' when confirming status with Building Inspection, since the City's own process language distinguishes it from other commercial alteration work.
- There is no dedicated tenant-improvement application, checklist, or plan-submittal guide published by the City — tenant finish projects use the same eTRAKiT Building Permit Application and the same valuation-based Table 1-A fee schedule as new construction.
- It is unconfirmed whether the $75 flat Minor Plan Review Fee (explicitly worded for 'additions, remodels, and utility buildings under 1,000 sq ft') extends to small tenant-finish scopes, since the fee schedule does not separately name 'tenant finish' — confirm before budgeting a small build-out.
- A change of occupancy classification (e.g., converting retail space to a restaurant or assembly use) triggers 2021 IEBC review (Sec. 22-236) in addition to the IBC, and may require additional life-safety upgrades to the existing space.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Greeley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Greeley
Tenant Improvement / Commercial Tenant Finish Permit in other cities
Compare tenant improvement / commercial tenant finish permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Greeley project checklist
Describe your project once and get every permit, document, and fee it triggers in Greeley — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →