Change of Use / Change of Occupancy in Greeley, Colorado

Greeley requires a permit for any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or CHANGE OCCUPANCY of a building or structure, consistent with the City's adopted building code permit-requirement language (Municipal Code Title 22, Building Code). Applications and plans are submitted in PDF format through eTRAKiT, where Building Inspection checks for completeness and calculates the plan review fee (payable in full before entering the review queue); the applicant then responds to any redline/correction comments, pays remaining permit fees upon approval, downloads the issued permit, and requests inspections before final approval and occupancy. Depending on project scope, separate reviews from Planning, Engineering, Water and Sewer, Floodplain, and Fire divisions may also apply.

Reviewed 2026-08-13 · Source

When you need this permit

  • A permit is required for any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change occupancy of a building or structure, per the City's adopted building code permit-requirement language
  • Application and plans are prepared in PDF format and submitted through eTRAKiT
  • Building Inspection checks the submittal for completeness and calculates the plan review fee, which must be paid in full before the project is accepted into the plan review queue
  • The applicant responds to any redlines or correction comments; after approval, remaining permit fees are paid and the issued permit is downloaded before inspections can be requested
  • Depending on project scope, separate reviews may be required from Planning, Engineering, Water and Sewer, Floodplain, Fire, and other City divisions
  • A new Certificate of Occupancy is generally required when a building's use classification changes, regardless of whether structural work accompanies the change, consistent with Colorado's home-rule Certificate of Occupancy framework

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review FeeMust be paid in full before the project enters the plan review queue; additional permit fees are paid upon approval
Calculated by Building Inspection upon submittal; not published as a standalone change-of-use figure

Review timeline

Plan review
Not published — contact the department

How long did your Change of Use / Change of Occupancy permit actually take in Greeley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection / Certificate of Occupancy

    Required before final approval and occupancy under the new use classification

See the full Greeley inspection guide — scheduling & re-inspection fees →

Tips

  • Greeley's plan review fee must be paid in FULL before your submittal even enters the review queue — budget for this upfront cost before expecting review to begin.
  • A change-of-occupancy project can trigger reviews from multiple City divisions beyond Building Inspection (Planning, Engineering, Water and Sewer, Floodplain, Fire) depending on scope — confirm which divisions apply early to avoid surprise delays.

Frequently asked questions

Greeley requires a change of use / change of occupancy permit for: A permit is required for any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change occupancy of a building or structure, per the City's adopted building code permit-requirement language; Application and plans are prepared in PDF format and submitted through eTRAKiT; Building Inspection checks the submittal for completeness and calculates the plan review fee, which must be paid in full before the project is accepted into the plan review queue; The applicant responds to any redlines or correction comments; after approval, remaining permit fees are paid and the issued permit is downloaded before inspections can be requested; Depending on project scope, separate reviews may be required from Planning, Engineering, Water and Sewer, Floodplain, Fire, and other City divisions; A new Certificate of Occupancy is generally required when a building's use classification changes, regardless of whether structural work accompanies the change, consistent with Colorado's home-rule Certificate of Occupancy framework. If your project isn't listed, confirm with City of Greeley Building Inspection (Community Development) at (970) 350-9830 before starting work.

In Greeley, the published Plan Review Fee is: Calculated by Building Inspection upon submittal; not published as a standalone change-of-use figure. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Greeley does not publish a plan-review timeline for this permit. Contact City of Greeley Building Inspection (Community Development) at (970) 350-9830 for current turnaround.

You'll need: Building Permit Application (eTRAKiT, PDF submittal). See the required-documents checklist on this page for details on each.

Greeley requires 1 inspection(s) for a change of use / change of occupancy permit, in order: Final Inspection / Certificate of Occupancy. Schedule each through City of Greeley Building Inspection (Community Development) ((970) 350-9830).

Apply through City of Greeley Building Inspection (Community Development) at 1100 10th Street, Greeley, CO 80631. Phone: (970) 350-9830, email: Building.Inspection@greeleygov.com. Office hours: Monday - Friday, 7:00 AM - 5:00 PM; appointments strongly recommended (Building Inspections, 1100 10th Street, Greeley, CO 80631). Official information: https://greeleyco.gov/business/construction-and-growth/building-permits-and-inspections.

Greeley, Colorado has adopted: Colorado is a home-rule state: there is no single mandatory statewide building code edition — each municipality adopts and amends its own codes. The only statewide floors are the building energy code (HB22-1362, effective 7/1/2023, requiring local governments that adopt an energy code to meet or exceed a specified electric- and solar-ready code baseline) and specific state statutes (e.g., ADU enabling legislation). Confirm your city's own adopted edition; this file documents Greeley's own program, verified directly from the Greeley Municipal Code (Title 22) via library.municode.com/co/greeley.; City of Greeley runs its own Building Inspection Division (part of Community Development) and administers its own permitting within Greeley city limits — it is not a Weld County program. Source: City of Greeley Building Permits and Inspections page.; 2021 International Building Code (IBC) — adopted by reference, Greeley Municipal Code Sec. 22-31, effective 1-1-2023 per Ord. No. 25, 2022; 2021 International Residential Code (IRC) — adopted by reference, Sec. 22-76, effective 1-1-2023 per Ord. No. 25, 2022; governs detached one- and two-family dwellings and townhouses up to 3 stories; 2021 International Existing Building Code (IEBC) — adopted by reference, Sec. 22-236, effective 1-1-2023; 2021 International Property Maintenance Code (IPMC) — adopted by reference, Sec. 22-192, effective 1-1-2023; 2021 International Mechanical Code (IMC) — adopted by reference, Sec. 22-161, effective 1-1-2023; 2021 International Plumbing Code (IPC) — adopted by reference, Sec. 22-306, effective 1-1-2023 (Greeley uses the International Plumbing Code, NOT the Uniform Plumbing Code); 2021 International Fuel Gas Code (IFGC) — adopted by reference, Sec. 22-347, effective 1-1-2023; 2021 International Energy Conservation Code (IECC) — adopted by reference, Sec. 22-286, effective 1-1-2023; 2021 International Fire Code (IFC) — adopted by reference, Sec. 22-454, effective 1-1-2023, with local amendments including NFPA 855-20 (stationary energy storage systems) and added Appendices B and C (fire-flow requirements, hydrant locations); 2023 National Electrical Code (NEC/NFPA 70) — adopted by reference, Sec. 22-377, per Ord. No. 37, 2023 (9-19-2023); superseded the previously adopted 2020 NEC; 2017 ICC A117.1 Accessibility Code — referenced on the City's Building Inspection Resources / Code Information page; All codes amended per Greeley Municipal Code Title 22 (Buildings and Construction), Chapters 2-12; consolidated under Ord. No. 25, 2022 (adoptions effective 1-1-2023) with the electrical code separately updated to the 2023 NEC by Ord. No. 37, 2023; Source: Greeley Municipal Code, Title 22, via library.municode.com/co/greeley (Chapters 2-12), cross-verified against the City's Building Permits and Inspections page 'Code Information' list. Local amendments apply — see the Greeley overview page for the full list.

Yes. A permit is required for any owner or authorized agent who intends to change the occupancy of a building or structure, processed through the standard eTRAKiT building-permit application and review process.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Greeley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.