EV Charger / EVSE Permit — Pocatello, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://pocatello.gov/871/Building-Permit-Fees
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Pocatello, Idaho
The City of Pocatello has no EV-charger-specific permit type or fee line. The City's Building Permit Fees schedule lists itemized electrical fee categories (New Residential Electrical by square footage, Existing Residence service/circuit work, Service Upgrade or Service Change, Temporary Service, Solar Photovoltaic Electrical Service, Industrial/Commercial Services, Electric Signs, Carnivals/Circuses) but no EV-charger, electric-vehicle, or EVSE line item — confirmed by direct review of the published fee schedule page. An EV charger circuit is filed as ordinary residential electrical work: a new dedicated circuit at an existing residence (the 'Existing residence — service/circuit work' fee), or a 'Service upgrade or service change' fee if a panel upgrade is needed to support the charger. Work is governed by the 2023 NEC as adopted by the City and applied for through the eTRAKiT portal.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the EV charger circuit installation, filed as ordinary residential electrical work
- Governed by the 2023 NEC as adopted by the City of Pocatello
- Electrical contractors must present a copy of their State of Idaho (DOPL) electrical contractor license; the City does not issue a separate city electrical contractor license Contractor
- Apply through the eTRAKiT portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Prior to covering wiring; verify wiring methods, box fill, and grounding per 2023 NEC
- 2
Final
Charger installed, circuit labeled, final electrical inspection prior to energization
See the full Pocatello inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated EV-charger permit fee line in Pocatello — a new EVSE circuit at an existing home is billed as ordinary 'Existing residence — service/circuit work' ($65 plus $10 per additional branch circuit); a panel/service upgrade to support the charger is billed separately at $65.
- As a local government requiring building permits, Pocatello is bound by Idaho Code § 39-4117, which requires written notice of a completeness determination within 10 business days for residential applications and 20 business days for commercial applications — this is a completeness-review deadline, not a full-approval deadline.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pocatello building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Pocatello's permit history is searchable by address
5,857 permits in our copy of Pocatello's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Pocatello has issued.
None of Pocatello's records carry an issued date, so this history cannot be filtered or sorted by date. The permits are here and searchable by address — but “when” is not a question they can answer.
Other permits in Pocatello
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Idaho →
Look up this fee in a different city →
Related guides
Now live
Build your Pocatello project checklist
Describe your project once and get every permit, document, and fee it triggers in Pocatello — in one checklist. Free, for any city and any number of projects.
Get started →