Unincorporated Bannock County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Bannock County, Idaho.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
5500 S. 5th Avenue, Pocatello, ID 83204
Phone
208-236-7230
Office hours
Monday–Thursday 8:00 AM – 5:00 PM, Friday 8:00 AM – 1:00 PM; closed all federal holidays

Published scheduling rules

  • Call 208-236-7090 to request an inspection. A permit must be issued and active before an inspection can be requested. A 24-hour notice is required; requests made after hours are processed the next business day. Inspections occur Monday–Thursday 8:00 AM–5:00 PM and Friday 8:00 AM–1:00 PM. Specific inspection times cannot be requested. (Residential Building Permit (New Construction / Addition))
  • Call 208-236-7090 to request an inspection; a permit must be issued and active first, and 24-hour notice is required. The County does not publish a commercial-specific inspection checklist — required inspection stages for a given project are determined by the approved stamped plans. (Commercial Building Permit (New Construction, Addition, Demolition, Change of Occupancy, Remodel/Tenant Improvement))

Inspection sequence

Applies to: Commercial Building Permit (New Construction, Addition, Demolition, Change of Occupancy, Remodel/Tenant Improvement)

  1. 1

    Footing

    Foundation excavation and footing form/rebar inspection prior to pour

  2. 2

    Framing

    Structural framing, wall/roof sheathing, and rough-ins complete before insulation or wall cover

  3. 3

    Final

    All work complete per approved stamped plans before occupancy or Certificate of Occupancy

Applies to: Residential Building Permit (New Construction / Addition)

  1. 1

    Footing

    Foundation excavation and footing form/rebar inspection prior to pour

  2. 2

    Framing

    Structural framing, wall/roof sheathing, and rough-ins complete before insulation or wall cover

  3. 3

    Final

    All work complete per approved plans before occupancy

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Structural/Mounting Final (County)

    Racking attachment, roof penetration sealing, and structural load compliance verified by Bannock County

  2. 2

    Electrical Interconnection (DOPL, separate permit)

    Conduit, disconnects, inverter, and interconnection point verified by a DOPL-assigned inspector under the separate state electrical permit

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Bannock County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Bannock County building permits

Get alerts for Unincorporated Bannock County

We'll email you when Unincorporated Bannock County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.