Inspection sequence

Applies to: Commercial Building Permit (New Construction / Addition / Remodel / Tenant Improvement)

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend to the local minimum depth of 36 inches; required whether the project is new commercial construction or a TI/remodel involving foundation work

  2. 2

    Framing

    After framing and rough-in trades, before insulation or wall cover

  3. 3

    Final

    All work complete per approved engineered plans; required before certificate of occupancy is issued

Applies to: Residential Building Permit (New Construction / Addition / Remodel)

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend to the local minimum depth of 36 inches

  2. 2

    Framing

    After framing and rough-in trades, before insulation or wall cover

  3. 3

    Final

    All work complete per approved plans; required before certificate of occupancy is issued

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Soda Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Soda Springs building permits

Get alerts for Soda Springs

We'll email you when Soda Springs's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.