Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Elmore County, Idaho.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
2280 American Legion Blvd, Mountain Home, ID 83647
Phone
208-587-2142
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Published scheduling rules

  • Elmore County spans a huge elevation range (Mountain Home valley floor up through Featherville, Pine, Atlanta, and Rocky Bar in the mountains) — footing depth, snow load, and inspection scheduling all vary by elevation zone. Structures above ~5,000 ft (above Tollgate) require an engineer-stamped 120 lbs/sq ft snow load / 115 mph wind report. (General)

Inspection sequence

Applies to: Commercial Building Permit (New Construction / Tenant Improvement)

  1. 1

    Footing/Foundation

    Verify footing depth and foundation layout before backfill

  2. 2

    Framing/Structural

    After structural framing complete and before wall cover

  3. 3

    Final

    All work complete per approved, stamped plans

Applies to: Residential Building Permit (New Construction / Addition)

  1. 1

    Footing/Foundation

    Verify footing depth per local zone (24"/30"/36" below frost line depending on elevation) and foundation layout before backfill

  2. 2

    Framing

    After framing, sheathing, and rough-in trades complete, before insulation or wall cover

  3. 3

    Final

    All work complete per approved plans; property address marker must be installed by the county before final inspection

Applies to: Agricultural Building Exemption (Notice of Proposed New Agricultural Building)

  1. 1

    Site/Setback Inspection

    Confirms conformity with road setbacks, County Ordinance setbacks, and utility setbacks; the structure itself is NOT inspected for IBC/IRC compliance since it is exempt

  2. 2

    Random Compliance Inspection (within 12 months)

    May occur within 12 months after final approval to confirm the structure's use remains agricultural in nature; if a non-agricultural use is found, the owner must obtain all required permits and pass all applicable inspections

Applies to: EV Charger / EVSE Permit

  1. 1

    Electrical Rough/Final (Idaho DOPL, state permit)

    Conductor sizing, breaker/panel work, grounding, and EVSE equipment connection verified under the separate state electrical permit — not performed by Elmore County

  2. 2

    Structural Final (County, only if applicable)

    Required only if the EV charger installation is paired with new county-permitted construction (carport, garage, accessory structure)

Applies to: Manufactured Home Placement Permit

  1. 1

    Foundation/Set

    Verify permanent foundation and blocking/anchoring per 2018 Idaho Manufactured Home Installation Standards

  2. 2

    Final

    Utility connections, skirting, and address marker verified; electrical/plumbing tie-ins inspected separately by Idaho DOPL

Re-inspection fees

Residential Building Permit (New Construction / Addition)Re-inspection Fee (beyond 2 failed inspections) · Fee Schedule effective October 15, 2025; also stated in Building Permit Application as $50 deducted from deposit after the second failed inspection of the same type
$50.00 per inspection

Unincorporated Elmore County building permits

Get alerts for Unincorporated Elmore County

We'll email you when Unincorporated Elmore County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.