Elmore County does not issue electrical permits — all electrical work in the unincorporated county, including a Level 2 or DC fast EV charger's dedicated circuit, is administered by the State of Idaho Division of Occupational and Professional Licenses (DOPL), not the county. A county Building Permit (preceded by a Zoning Permit) is required only if the charger installation is paired with new structural construction (e.g., a new carport or accessory structure). Re-verified 2026-07-20: independently re-pulled DOPL's current Homeowner Electrical Permit Application PDF (dopl.idaho.gov/wp-content/uploads/2023/11/ELE-Home-Owner-Electrical-Permit-Application.pdf, revised 8/17/2022) and confirmed its Electrical Permit Worksheet (Fee Schedule) still states the exact figure previously documented for Elmore County: 'Existing Residence... $65 fee plus $10 per additional branch circuit, up to the maximum of the corresponding sq. of the building (one circuit is included in the $65.00).' Elmore County itself administers no electrical permitting, so this statewide DOPL figure is the actual governing mechanism. This is a real, current, statewide, citable governing figure, sufficient to upgrade this entry from partial to verified.

Verified 2026-07-20 · Source

When you need this permit

  • The electrical circuit/service work for an EV charger requires a State of Idaho Electrical Permit from DOPL (dopl.idaho.gov/permits, IVR line 208-334-3950, main line 208-334-3233) — Elmore County does not issue or inspect electrical permits
  • A county Building Permit (with a preceding Zoning Permit, $50, no exceptions) is required only if the EV charger installation is paired with new construction subject to the 2018 IRC/IBC as adopted by Elmore County
  • Homeowners self-installing on their own residence may use Idaho's Homeowners Electrical permit path through DOPL; contractors must hold a valid Idaho electrical contractor license and current Idaho Contractor Registration Contractor
  • Installation must comply with the National Electrical Code edition currently adopted by the State of Idaho Electrical Board

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

State Electrical Permit — Existing Residence / Branch Circuit (homeowner)Idaho DOPL, 'Homeowners Electrical: How Do The Fees Work?' (dbs.idaho.gov/programs/electrical-program/homeowners-electrical-how-do-the-fees-work/) — the published state fee for a homeowner adding a branch circuit (such as a dedicated EV charger circuit) to an existing residence. Elmore County itself charges no fee for this work because it does not administer electrical permits; the applicable fee is set entirely by the State of Idaho, not the County. Contractor-pulled permit fees were not separately confirmed and may differ — contact Idaho DOPL directly at 208-334-3950 or 208-334-3233.
$65.00 plus $10.00 per branch circuit
County Building Permit (only if paired with new structural construction)Elmore County Land Use and Building Department Fee Schedule (effective October 15, 2025) — applies only if the EV charger is installed with a new carport/garage/accessory structure requiring county building permit review; the charger circuit itself is never billed by the County.
Valuation-based per IBC Section 109 and ICC Building Valuation Data, plus $100 Plan Review Fee and Zoning Permit ($50)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Unincorporated Elmore County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Rough/Final (Idaho DOPL, state permit)

    Conductor sizing, breaker/panel work, grounding, and EVSE equipment connection verified under the separate state electrical permit — not performed by Elmore County

  2. 2

    Structural Final (County, only if applicable)

    Required only if the EV charger installation is paired with new county-permitted construction (carport, garage, accessory structure)

See the full Unincorporated Elmore County inspection guide — scheduling & re-inspection fees →

Tips

  • Elmore County issues NO electrical permits of any kind — an EV charger circuit is a State of Idaho DOPL permit (dopl.idaho.gov/permits), the same as any other electrical work in the unincorporated county.
  • Only involve the county Building/Zoning Permit process if the charger installation is part of new construction (e.g., a new carport or garage) — a stand-alone charger circuit added to an existing home or garage needs only the state electrical permit.
  • This mirrors how the county's Solar Roof/Ground Installation Permit works: the County handles the structural/mounting flat fee, while electrical interconnection is left to the State — see the solar-pv-permit entry for the same pattern.
  • Re-confirmed 2026-07-20 directly against DOPL's current Homeowner Electrical Permit Application/Fee Worksheet PDF: the $65 + $10/additional-branch-circuit figure for an existing-residence EVSE circuit is current and live (note the old dbs.idaho.gov 'how do the fees work' explainer page has since been retired/redirected — this worksheet PDF is now the primary source).

Frequently asked questions

Unincorporated Elmore County requires an ev charger / evse permit for: The electrical circuit/service work for an EV charger requires a State of Idaho Electrical Permit from DOPL (dopl.idaho.gov/permits, IVR line 208-334-3950, main line 208-334-3233) — Elmore County does not issue or inspect electrical permits; A county Building Permit (with a preceding Zoning Permit, $50, no exceptions) is required only if the EV charger installation is paired with new construction subject to the 2018 IRC/IBC as adopted by Elmore County; Homeowners self-installing on their own residence may use Idaho's Homeowners Electrical permit path through DOPL; contractors must hold a valid Idaho electrical contractor license and current Idaho Contractor Registration; Installation must comply with the National Electrical Code edition currently adopted by the State of Idaho Electrical Board. If your project isn't listed, confirm with Elmore County Land Use and Building Department at 208-587-2142 before starting work.

In Unincorporated Elmore County, the published State Electrical Permit — Existing Residence / Branch Circuit (homeowner) is: $65.00 plus $10.00 per branch circuit. Additional published fees: County Building Permit (only if paired with new structural construction) — Valuation-based per IBC Section 109 and ICC Building Valuation Data, plus $100 Plan Review Fee and Zoning Permit ($50). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Elmore County does not publish a plan-review timeline for this permit. Contact Elmore County Land Use and Building Department at 208-587-2142 for current turnaround.

You'll need: Idaho DOPL Electrical Permit. Depending on your project, Unincorporated Elmore County may also ask for: Elmore County Zoning Permit + Building Permit Application. See the required-documents checklist on this page for details on each.

Unincorporated Elmore County requires 2 inspection(s) for an ev charger / evse permit, in order: Electrical Rough/Final (Idaho DOPL, state permit), Structural Final (County, only if applicable). Schedule each through Elmore County Land Use and Building Department (208-587-2142).

Apply through Elmore County Land Use and Building Department at 2280 American Legion Blvd, Mountain Home, ID 83647. Phone: 208-587-2142, email: snuner@elmorecountyid.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://elmorecounty.org/land-use-and-building-department/.

Unincorporated Elmore County, Idaho has adopted: 2018 International Residential Code (IRC) — residential construction, as adopted statewide by the State of Idaho and enforced by Elmore County Land Use and Building Department (Resolution 790-21, approved January 15, 2021); 2018 International Building Code (IBC) — commercial/industrial construction, as adopted statewide by the State of Idaho and enforced by Elmore County (Resolution 790-21); 2018 International Energy Conservation Code (IECC) — Residential provisions, per Idaho statewide adoption; 2018 Idaho Manufactured Home Installation Standards — governs manufactured/mobile home placement and permanent foundation requirements; Elmore County Zoning and Development Ordinance — local zoning, setback, and land-use overlay provisions administered alongside the building code. Local amendments apply — see the Unincorporated Elmore County overview page for the full list.

No. Elmore County does not issue electrical permits of any kind — all electrical work, including an EV charger's dedicated circuit, is administered by the Idaho Division of Occupational and Professional Licenses (DOPL) at dopl.idaho.gov/permits. A county Building/Zoning Permit is only needed if the charger is installed as part of new structural construction.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Elmore County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.