Inspection sequence, scheduling, and re-inspection fees for building permits in Heyburn, Idaho.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
941 18th Street, P.O. Box 147, Heyburn, ID 83336 (residential permit application header also prints ZIP 83303-1907; the city's own website and general contact pages consistently use 83336)
Phone
208-679-8158
Office hours
Monday–Friday, 9:00 AM to 5:00 PM, per heyburn.id.gov/planning-building. Fax 208-679-2438. Building Inspector: Jerome Fagaldefeg (jfagaldefeg@heyburncity.org); Building Official: Tony Morley (tmorley@heyburncity.org); Community Development Director serves as the appointed Building Official per Heyburn City Code 2-1-1(B).
Website
Official site

Inspection sequence

Applies to: Residential Home Permit (New Construction — Single Family, Duplex, Zero Lot Line, Townhouse)

  1. 1

    Foundation

    Foundation inspection per the cross-section, footing, j-bolt, stem wall, and rebar details required on the Residential New Home Checklist.

  2. 2

    Framing

    Framing inspection covering floor joists, wall bracing design, roof framing/truss layout, and header/beam sizing per the checklist.

  3. 3

    Final / Certificate of Occupancy

    Final inspection required before a Certificate of Occupancy is issued; no occupancy is allowed and utilities will not be enabled until the Certificate of Occupancy is issued, per the Residential Home Permit Application. A temporary C of O is available for incomplete work under extenuating circumstances (e.g., frozen ground) for a $1,000 refundable fee.

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection

  2. 2

    City Final Inspection (Building)

    Racking/roof-penetration attachment and structural compliance verified; a Certificate of Occupancy is required before utilities are enabled, per the City's application form

Final inspection only: EV Charger / EVSE Permit

Heyburn building permits

Get alerts for Heyburn

We'll email you when Heyburn's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.