Solar Photovoltaic (PV) Permit — Heyburn, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/wp-content/uploads/2023/11/ELE-Contractor-Electrical-Permit-Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Heyburn, Idaho
Required for installation of rooftop or ground-mount solar photovoltaic systems within Heyburn city limits. Requires a City Building Permit (structural/racking, valuation-based on Project Value per the City's Residential Home Permit Application) plus a State of Idaho electrical permit (wiring/interconnection) issued by the Division of Occupational and Professional Licenses (DOPL) -- Heyburn's own Residential Home Permit Application states directly that 'Additional permits are required for electrical, plumbing and mechanical installations,' and electrical work in Heyburn is handled by the state, not the City. The state's Contractor Electrical Permit Worksheet has a dedicated checkbox and valuation-based fee formula for 'Solar, Renewable Energy, power generation, power production, or energy storage systems.'
Verified 2026-07-20 · Source
When you need this permit
- City Residential Home Permit Application submitted to the Building Department for the structural/racking scope; fee is based on the applicant-certified Project Value (defined by the City as including overhead, profit, finish work, electrical, plumbing, and owner-supplied items)
- Per the City's own application form: 'Additional permits are required for electrical, plumbing and mechanical installations' -- confirming the wiring/interconnection scope needs a separate permit
- Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed), not a City permit
- On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system
- All City building permit applications and permits expire 180 days from date of receipt/issuance/last inspection, per the City's Residential Home Permit Application notice
- Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection
- 2
City Final Inspection (Building)
Racking/roof-penetration attachment and structural compliance verified; a Certificate of Occupancy is required before utilities are enabled, per the City's application form
See the full Heyburn inspection guide — scheduling & re-inspection fees →
Tips
- Heyburn splits solar permitting across two agencies: the City issues the structural Building Permit, but the State of Idaho (DOPL, dbs.idaho.gov) issues the electrical permit -- the City's own application form explicitly states additional permits are required for electrical installations.
- The City's building-permit fee is calculated from a self-certified 'Project Value' rather than a published dollar table -- get a written fee estimate from the Building Department before budgeting.
- On the state electrical permit worksheet, be sure to check the dedicated 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box -- this routes the project to the correct valuation-based fee formula.
- Both City permit applications and issued permits expire after 180 days of inactivity in Heyburn -- don't let a solar project stall mid-review.
- Re-chase pass (2026-07-20): downloaded and read the current State of Idaho DOPL Application for Contractor Permit / Electrical Permit Worksheet (Fee Schedule) PDF directly from dopl.idaho.gov — live today, and its 'OTHER INSTALLATIONS including COMMERCIAL/INDUSTRIAL/SOLAR/RENEWABLE ENERGY' section matches this entry's tiered formula verbatim: (system cost x 0.02) + $60 up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000; ((system cost - $100,000) x 0.005) + $1,160 over $100,001. This DOPL fee schedule is the explicit, statewide, currently-in-force state mechanism for the PV/renewable-energy electrical scope in any Idaho city (including this one) that has not independently certified its own electrical inspection program.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Heyburn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Heyburn
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →
Look up this fee in a different city →