Required for installation of rooftop or ground-mount solar photovoltaic systems within Heyburn city limits. Requires a City Building Permit (structural/racking, valuation-based on Project Value per the City's Residential Home Permit Application) plus a State of Idaho electrical permit (wiring/interconnection) issued by the Division of Occupational and Professional Licenses (DOPL) -- Heyburn's own Residential Home Permit Application states directly that 'Additional permits are required for electrical, plumbing and mechanical installations,' and electrical work in Heyburn is handled by the state, not the City. The state's Contractor Electrical Permit Worksheet has a dedicated checkbox and valuation-based fee formula for 'Solar, Renewable Energy, power generation, power production, or energy storage systems.'

Verified 2026-07-20 · Source

When you need this permit

  • City Residential Home Permit Application submitted to the Building Department for the structural/racking scope; fee is based on the applicant-certified Project Value (defined by the City as including overhead, profit, finish work, electrical, plumbing, and owner-supplied items)
  • Per the City's own application form: 'Additional permits are required for electrical, plumbing and mechanical installations' -- confirming the wiring/interconnection scope needs a separate permit
  • Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed), not a City permit
  • On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system
  • All City building permit applications and permits expire 180 days from date of receipt/issuance/last inspection, per the City's Residential Home Permit Application notice
  • Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Building Permit Fee (Project-Value-based)The City's Residential Home Permit Application states Project Value 'is used to calculate fees for the building permit' but the application form itself contains no printed dollar-figure fee table, consistent with this corpus's existing residential-building-permit entry for Heyburn, which documents this same unresolved gap. No dedicated solar/photovoltaic building fee line is published. Contact the Building Department at 208-679-8158 (option 2) for a current quote.
Not published — contact the department
State DOPL Electrical Permit -- Solar/Renewable Energy, up to $10,000 system costIdaho DOPL Contractor Electrical Permit Worksheet (Fee Schedule), Rev. 8/17/2022 -- a state fee, not collected by the City of Heyburn
(total system cost x 0.02) + $60
State DOPL Electrical Permit -- Solar/Renewable Energy, $10,001-$100,000 system costIdaho DOPL Contractor Electrical Permit Worksheet, Rev. 8/17/2022
((system cost - $10,000) x 0.01) + $260
State DOPL Electrical Permit -- Solar/Renewable Energy, over $100,001 system costIdaho DOPL Contractor Electrical Permit Worksheet, Rev. 8/17/2022; renewable energy installations require a plan check prior to final inspection
((system cost - $100,000) x 0.005) + $1,160

Review timeline

Plan reviewTypical estimate — confirm current times with the Heyburn building department
~Up to 21 business days

How long did your Solar Photovoltaic (PV) Permit permit actually take in Heyburn?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection

  2. 2

    City Final Inspection (Building)

    Racking/roof-penetration attachment and structural compliance verified; a Certificate of Occupancy is required before utilities are enabled, per the City's application form

See the full Heyburn inspection guide — scheduling & re-inspection fees →

Tips

  • Heyburn splits solar permitting across two agencies: the City issues the structural Building Permit, but the State of Idaho (DOPL, dbs.idaho.gov) issues the electrical permit -- the City's own application form explicitly states additional permits are required for electrical installations.
  • The City's building-permit fee is calculated from a self-certified 'Project Value' rather than a published dollar table -- get a written fee estimate from the Building Department before budgeting.
  • On the state electrical permit worksheet, be sure to check the dedicated 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box -- this routes the project to the correct valuation-based fee formula.
  • Both City permit applications and issued permits expire after 180 days of inactivity in Heyburn -- don't let a solar project stall mid-review.
  • Re-chase pass (2026-07-20): downloaded and read the current State of Idaho DOPL Application for Contractor Permit / Electrical Permit Worksheet (Fee Schedule) PDF directly from dopl.idaho.gov — live today, and its 'OTHER INSTALLATIONS including COMMERCIAL/INDUSTRIAL/SOLAR/RENEWABLE ENERGY' section matches this entry's tiered formula verbatim: (system cost x 0.02) + $60 up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000; ((system cost - $100,000) x 0.005) + $1,160 over $100,001. This DOPL fee schedule is the explicit, statewide, currently-in-force state mechanism for the PV/renewable-energy electrical scope in any Idaho city (including this one) that has not independently certified its own electrical inspection program.

Frequently asked questions

Heyburn requires a solar photovoltaic (pv) permit for: City Residential Home Permit Application submitted to the Building Department for the structural/racking scope; fee is based on the applicant-certified Project Value (defined by the City as including overhead, profit, finish work, electrical, plumbing, and owner-supplied items); Per the City's own application form: 'Additional permits are required for electrical, plumbing and mechanical installations' -- confirming the wiring/interconnection scope needs a separate permit; Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed), not a City permit; On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system; All City building permit applications and permits expire 180 days from date of receipt/issuance/last inspection, per the City's Residential Home Permit Application notice; Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet. If your project isn't listed, confirm with City of Heyburn Building Department (Community Development) at 208-679-8158 before starting work.

Plan review for a solar photovoltaic (pv) permit in Heyburn typically runs Up to 21 business days. This is an estimate, not a published figure — confirm current review times with City of Heyburn Building Department (Community Development) at 208-679-8158.

You'll need: City of Heyburn Residential Home Permit Application; Idaho DOPL Contractor (or Homeowner) Electrical Permit Application. See the required-documents checklist on this page for details on each.

Heyburn requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: State Electrical Inspection, City Final Inspection (Building). Schedule each through City of Heyburn Building Department (Community Development) (208-679-8158).

Apply through City of Heyburn Building Department (Community Development) at 941 18th Street, P.O. Box 147, Heyburn, ID 83336 (residential permit application header also prints ZIP 83303-1907; the city's own website and general contact pages consistently use 83336). Phone: 208-679-8158, email: cdd@heyburncity.org. Office hours: Monday–Friday, 9:00 AM to 5:00 PM, per heyburn.id.gov/planning-building. Fax 208-679-2438. Building Inspector: Jerome Fagaldefeg (jfagaldefeg@heyburncity.org); Building Official: Tony Morley (tmorley@heyburncity.org); Community Development Director serves as the appointed Building Official per Heyburn City Code 2-1-1(B)..

Heyburn, Idaho has adopted: 2018 International Residential Code (IRC), with Idaho amendments — per Heyburn's own Residential Home Permit Application Plan Submittal Requirements: 'Plans to be designed to the 2018 IRC Code & 2018 IECC. (with Idaho amendments)' (heyburn.id.gov, 2023 Residential New Home Permit application, page 2).; 2018 International Energy Conservation Code (IECC), with Idaho amendments — same source as above.; 2018 International Building Code (IBC), with amendments — Heyburn City Code Title 2, Chapter 1, Section 2-1-1(A) adopts by reference 'the following recognized codes as currently adopted by the State of Idaho,' and the State of Idaho's own currently-published adopted-codes list (Idaho DOPL, 'Idaho Adopted Codes,' dopl.idaho.gov/wp-content/uploads/2025/06/2025-Updated-Idaho-Adopted-Codes.pdf) lists the 2018 IBC with amendments as the current state building code.; 2018 International Existing Building Code (IEBC) — per the same Idaho DOPL 'Idaho Adopted Codes' publication, incorporated into Heyburn's code by the automatic state-code-reference mechanism in Heyburn City Code 2-1-1(A).; 2018 International Mechanical Code (IMC) and 2018 International Fuel Gas Code (IFGC) — per the same Idaho DOPL 'Idaho Adopted Codes' publication.; 2017 Idaho State Plumbing Code (based on the 2015 Uniform Plumbing Code) — per the same Idaho DOPL 'Idaho Adopted Codes' publication.; 2023 National Electrical Code (NEC), with amendments — per the same Idaho DOPL 'Idaho Adopted Codes' publication.; IMPORTANT — code-adoption mechanism: Heyburn City Code 2-1-1(A) (amd. Ord. 2026-721, 3-25-2026; Ord. 2026-722, 4-22-2026; codelibrary.amlegal.com/codes/heyburnid/latest/heyburn_id/0-0-0-15510) states verbatim: 'The following recognized codes as currently adopted by the State of Idaho are adopted as the official building codes of the City of Heyburn. Each code shall be deemed superseded by successive versions of such codes as they are adopted or approved by the State of Idaho effective on the 1st day of January the year following the date any such codes are made effective for the State of Idaho, unless a different date is required by state statute.' This means Heyburn's adopted editions track the State of Idaho's current adopted editions automatically, rather than being independently re-adopted by city ordinance edition-by-edition. The city's own 2023-dated Residential and Commercial permit application PDFs both independently confirm the 2018 IRC/2018 IECC editions currently in force, consistent with the state list.; NOTE: No Heyburn-specific local amendment TEXT to the IRC/IBC (e.g., a snow-load or seismic design value table, or textual deviations from the model code sections) was found published separately from the state-level amendments referenced above, as of 2026-07-04. Omitted rather than invented.. Local amendments apply — see the Heyburn overview page for the full list.

The State of Idaho Division of Occupational and Professional Licenses (DOPL), not the City of Heyburn. The City's own Residential Home Permit Application states directly that additional permits are required for electrical installations, and the City does not run its own electrical permitting program.

Based on the total cost of the electrical system, per DOPL's Contractor Electrical Permit Worksheet: (system cost x 0.02) + $60 for systems up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000. Applicants must check the dedicated Solar/Renewable Energy box on the worksheet.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Heyburn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.