New or Addition Commercial Building Permit (Commercial/Non-Residential/Multi-Family) in Heyburn, Idaho

Required for new complete buildings, additions, multi-family (3+ dwelling units), and shell buildings (with or without interior walls) in the City of Heyburn. A pre-submittal meeting is required on all new and addition commercial projects. Governed by the state-referenced 2018 IBC per Heyburn City Code 2-1-1(A).

Verified 2026-07-04 · Source

When you need this permit

  • Pre-submittal meeting required on all new and addition commercial projects (call to schedule)
  • Civil Site Plan (required separate from architectural site plan): legal description, property lines/setbacks, right-of-way details, fire department access (20 ft wide, 75,000-lb load capacity, within 150 ft of exterior walls), fire hydrants within 1000 feet, grading plan, utility services, parking layout, storm drainage design and calculations (stamped by Idaho Registered Civil Engineer or Landscape Architect), geotechnical report, water/sewer tap sizes, flood plain indication
  • Architectural Site Plan (required in addition to civil site plan): structure locations/distances, IFC-regulated material storage areas, landscaping, exterior lighting, setbacks/easements, trash enclosure/mechanical screening, parking lot design per City Code Title 8 Chapter 9
  • Code/Plan Analysis using the application's example Code Analysis form, separately for each building
  • Com Check Energy Analysis prepared by an Idaho licensed architect or engineer
  • Foundation Plan, Floor Plan, Structural Plans, and Foundation/Structural/Shear Engineering Calculations, all stamped by an Idaho Registered Engineer or Architect (calculations required for all new construction and additions; cannot be a deferred submittal for metal buildings, stair drawings, or permanently fixed furniture)
  • Electrical Plans, Mechanical Plans & Ventilation Calculations, Plumbing Plans (with grease/sand interceptor sizing per Idaho State/Uniform Plumbing Code)
  • Additional Handicap Accessibility Information per current IBC and ANSI A117.1
  • Statement of special inspections per IBC 1704.1.1, with a final report submitted before start of work
  • Completed Wastewater Survey and Sewer Capacity Fee Worksheet
  • Health District letter of approval required prior to permit issuance for any building where food is prepared

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan reviewHeyburn’s published plan-review target
Up to 42 business days

How long did your New or Addition Commercial Building Permit (Commercial/Non-Residential/Multi-Family) permit actually take in Heyburn?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full Heyburn inspection guide — scheduling & re-inspection fees →

    Tips

    • A pre-submittal meeting is mandatory for all new and addition commercial projects — call the Building Department to schedule before submitting plans.
    • Fire sprinkler plans and elevator plans must be submitted to the State of Idaho for review, separate from the city's own commercial plan review.
    • All permits (commercial and residential alike) expire 180 days from issuance or the date of the last inspection; any commercial application not issued or picked up after 180 days becomes null and void.
    • When a commercial project contains multiple buildings on one site, a separate permit and its own set of plans is required for each building, unless the buildings are identical or it is a storage-unit complex — contact the Building Department for specifics before submitting plans.

    Frequently asked questions

    Heyburn requires a new or addition commercial building permit (commercial/non-residential/multi-family) for: Pre-submittal meeting required on all new and addition commercial projects (call to schedule); Civil Site Plan (required separate from architectural site plan): legal description, property lines/setbacks, right-of-way details, fire department access (20 ft wide, 75,000-lb load capacity, within 150 ft of exterior walls), fire hydrants within 1000 feet, grading plan, utility services, parking layout, storm drainage design and calculations (stamped by Idaho Registered Civil Engineer or Landscape Architect), geotechnical report, water/sewer tap sizes, flood plain indication; Architectural Site Plan (required in addition to civil site plan): structure locations/distances, IFC-regulated material storage areas, landscaping, exterior lighting, setbacks/easements, trash enclosure/mechanical screening, parking lot design per City Code Title 8 Chapter 9; Code/Plan Analysis using the application's example Code Analysis form, separately for each building; Com Check Energy Analysis prepared by an Idaho licensed architect or engineer; Foundation Plan, Floor Plan, Structural Plans, and Foundation/Structural/Shear Engineering Calculations, all stamped by an Idaho Registered Engineer or Architect (calculations required for all new construction and additions; cannot be a deferred submittal for metal buildings, stair drawings, or permanently fixed furniture); Electrical Plans, Mechanical Plans & Ventilation Calculations, Plumbing Plans (with grease/sand interceptor sizing per Idaho State/Uniform Plumbing Code); Additional Handicap Accessibility Information per current IBC and ANSI A117.1; Statement of special inspections per IBC 1704.1.1, with a final report submitted before start of work; Completed Wastewater Survey and Sewer Capacity Fee Worksheet; Health District letter of approval required prior to permit issuance for any building where food is prepared. If your project isn't listed, confirm with City of Heyburn Building Department (Community Development) at 208-679-8158 before starting work.

    Per the city's own Commercial Building Permit Application, initial review of a complete submittal is not expected to exceed 4-6 weeks, though revisions or workload can extend this. A pre-submittal meeting is required before applying.

    You'll need: New or Addition Commercial Building Permit Application; (New & Addition) Commercial/Non-Residential/Multi-Family Plan Review Checklist; Sewer Capacity Fee Worksheet; Sample Plans Analysis Form. See the required-documents checklist on this page for details on each.

    Apply through City of Heyburn Building Department (Community Development) at 941 18th Street, P.O. Box 147, Heyburn, ID 83336 (residential permit application header also prints ZIP 83303-1907; the city's own website and general contact pages consistently use 83336). Phone: 208-679-8158, email: cdd@heyburncity.org. Office hours: Monday–Friday, 9:00 AM to 5:00 PM, per heyburn.id.gov/planning-building. Fax 208-679-2438. Building Inspector: Jerome Fagaldefeg (jfagaldefeg@heyburncity.org); Building Official: Tony Morley (tmorley@heyburncity.org); Community Development Director serves as the appointed Building Official per Heyburn City Code 2-1-1(B)..

    Heyburn, Idaho has adopted: 2018 International Residential Code (IRC), with Idaho amendments — per Heyburn's own Residential Home Permit Application Plan Submittal Requirements: 'Plans to be designed to the 2018 IRC Code & 2018 IECC. (with Idaho amendments)' (heyburn.id.gov, 2023 Residential New Home Permit application, page 2).; 2018 International Energy Conservation Code (IECC), with Idaho amendments — same source as above.; 2018 International Building Code (IBC), with amendments — Heyburn City Code Title 2, Chapter 1, Section 2-1-1(A) adopts by reference 'the following recognized codes as currently adopted by the State of Idaho,' and the State of Idaho's own currently-published adopted-codes list (Idaho DOPL, 'Idaho Adopted Codes,' dopl.idaho.gov/wp-content/uploads/2025/06/2025-Updated-Idaho-Adopted-Codes.pdf) lists the 2018 IBC with amendments as the current state building code.; 2018 International Existing Building Code (IEBC) — per the same Idaho DOPL 'Idaho Adopted Codes' publication, incorporated into Heyburn's code by the automatic state-code-reference mechanism in Heyburn City Code 2-1-1(A).; 2018 International Mechanical Code (IMC) and 2018 International Fuel Gas Code (IFGC) — per the same Idaho DOPL 'Idaho Adopted Codes' publication.; 2017 Idaho State Plumbing Code (based on the 2015 Uniform Plumbing Code) — per the same Idaho DOPL 'Idaho Adopted Codes' publication.; 2023 National Electrical Code (NEC), with amendments — per the same Idaho DOPL 'Idaho Adopted Codes' publication.; IMPORTANT — code-adoption mechanism: Heyburn City Code 2-1-1(A) (amd. Ord. 2026-721, 3-25-2026; Ord. 2026-722, 4-22-2026; codelibrary.amlegal.com/codes/heyburnid/latest/heyburn_id/0-0-0-15510) states verbatim: 'The following recognized codes as currently adopted by the State of Idaho are adopted as the official building codes of the City of Heyburn. Each code shall be deemed superseded by successive versions of such codes as they are adopted or approved by the State of Idaho effective on the 1st day of January the year following the date any such codes are made effective for the State of Idaho, unless a different date is required by state statute.' This means Heyburn's adopted editions track the State of Idaho's current adopted editions automatically, rather than being independently re-adopted by city ordinance edition-by-edition. The city's own 2023-dated Residential and Commercial permit application PDFs both independently confirm the 2018 IRC/2018 IECC editions currently in force, consistent with the state list.; NOTE: No Heyburn-specific local amendment TEXT to the IRC/IBC (e.g., a snow-load or seismic design value table, or textual deviations from the model code sections) was found published separately from the state-level amendments referenced above, as of 2026-07-04. Omitted rather than invented.. Local amendments apply — see the Heyburn overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-04.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Heyburn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

    This one’s complicated · Get an expediter

    Tell us about your project and we’ll connect you with a permit expediter who works in Heyburn.

    PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.