Lewiston building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Lewiston, Idaho.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
215 D Street, Lewiston, ID 83501 (P.O. Box 617, Lewiston, ID 83501)
Phone
(208) 746-1318, option 1 for Permit Representatives
Office hours
Monday-Friday, 8:00 AM to 5:00 PM. Building Official: Jeff Wolfe, (509) 254-3275, jwolfe@cityoflewiston.org. Permit Representatives: Lorrie Tanguay, (208) 746-1318 ext. 7203; Adrian Miller, (208) 746-1318 ext. 7263.

Inspection sequence

Applies to: Residential New Home Building Permit (New Single Family Dwelling/Duplex)

  1. 1

    Foundation/Footing

    Required prior to concrete pour, consistent with the adopted 2018 IRC.

  2. 2

    Rough-In (Electrical, Mechanical, Plumbing)

    Trade rough-in inspections for the separately permitted electrical, mechanical, and plumbing scopes.

  3. 3

    Framing

    Structural framing inspection after rough-ins are signed off.

  4. 4

    Final

    Final building and trade inspections prior to occupancy.

Applies to: Solar PV Permit (Alternative Energy)

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, consistent with the adopted 2023 NEC.

  2. 2

    Framing/Structural (if a building permit applies)

    Racking and roof-penetration/structural attachment inspection prior to cover.

  3. 3

    Final

    Final electrical inspection; system energized and verified.

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring, panel, and grounding inspection consistent with the adopted 2023 NEC.

  2. 2

    Final

    Final electrical inspection.

Applies to: Mechanical Permit (HVAC, Gas Work)

  1. 1

    Rough Mechanical

    Ductwork, gas line, and equipment inspection consistent with the adopted 2018 IMC.

  2. 2

    Final

    Final mechanical inspection.

Applies to: Plumbing Permit

  1. 1

    Underground/Rough-In

    Pipe slope, materials, and cleanouts verified before walls/slab closed.

  2. 2

    Final

    Final plumbing inspection.

Applies to: Swimming Pool Permit

  1. 1

    Electrical/Bonding

    Pool bonding grid and electrical protection, billed per inspection under the Electrical Permit Fees schedule.

  2. 2

    Final

    Final building inspection.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lewiston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Lewiston building permits

Get alerts for Lewiston

We'll email you when Lewiston's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.