Inspection sequence, scheduling, and re-inspection fees for building permits in Polson, Montana.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
106 1st Street East, Polson, MT 59860
Phone
(406) 883-8214
Office hours
City Hall main line (406) 883-8200, fax (406) 883-8238. Building Official: Lynda Benson, (406) 883-8216. Community Development Director: Rob Edington, (406) 883-8213. Applications may be submitted by mail (City of Polson, 106 1st Street East, Polson, MT 59860) or by email to bp@cityofpolson.com. The City also directs applicants to apply online at GovWell.com.

Inspection sequence

Applies to: Zoning Conformance & Building Permit (New Construction / Addition / Remodel)

  1. 1

    Foundation

    Before concrete pour, per department inspection sheet requirements

  2. 2

    Framing

    Structural framing per approved plans before walls are closed

  3. 3

    Final

    Completed work verified against approved plans; a Certificate of Compliance and Occupancy is issued only after the department inspection sheet is submitted and signed off by each required department

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2020 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    EVSE circuit wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Charger installed, circuit labeled, protections verified per 2020 NEC

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork, gas piping, and mechanical equipment rough-in before walls closed

  2. 2

    Final

    Equipment operational, clearances and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough-In

    After pipes installed, before walls closed

  2. 2

    Final

    All fixtures connected, water heater and venting verified, no leaks

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Final electrical/building inspection preceding sign-off

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Polson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Polson building permits

Get alerts for Polson

We'll email you when Polson's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.