Demolition / Building Move Permit in Libby, Montana
Required for demolition or removal of any structure within Libby city limits, and for moving a structure, using the same Libby Building Permit Application with 'Demolition' or 'Move' checked under Type of Project. A DEQ-required asbestos inspection applies before demolition given Libby's documented asbestos/vermiculite legacy.
Verified 2026-07-03 · Source
When you need this permit
- Complete the Libby Building Permit Application with 'Demolition' or 'Move' checked under Type of Project, including a description of the nature of the project and estimated cost
- Per the Montana Asbestos Control Act (ARM 17.74.354) and a Montana DEQ memorandum distributed within the City's own Building Permit Requirements packet: an asbestos inspection by a DEQ-accredited (licensed) asbestos inspector is REQUIRED prior to building demolition, renovation, or remodeling activities, to determine whether asbestos-containing materials (ACM) are present
- Contact the Lincoln County Asbestos Resource Program (LCARP) hotline at (406) 291-5335, or submit a Property Evaluation Notification (PEN) form at lcarp.org/pen-form, for guidance and property status information specific to Libby's known asbestos/vermiculite contamination history
- Owner/applicant must confirm utility disconnection and site cleanup consistent with general City building-permit practice; a written verification from utility companies is good practice though not separately codified in the City's packet the way Billings documents it
- Violations of the Montana Asbestos Control Act carry penalties of $10,000 to $25,000 per day per the DEQ memorandum
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition Asbestos Clearance
DEQ-accredited asbestos inspection must be completed and any required abatement addressed before demolition/renovation activities begin, per the Montana Asbestos Control Act and ARM 17.74.354.
- 2
Final
Site verified as cleared/restored consistent with the City's general Final Inspection practice.
See the full Libby inspection guide — scheduling & re-inspection fees →
Tips
- Libby has a well-documented history of vermiculite/asbestos contamination; the Lincoln County Asbestos Resource Program (LCARP) offers free guidance, a Property Evaluation Notification (PEN) form, and property status letters — call (406) 291-5335 or visit lcarp.org before beginning any demolition, remodeling, or excavation project.
- No fixed demolition bond amount (unlike Billings' $10,000 site bond) was found published for Libby — confirm bonding/insurance and current fee amounts directly with the Building Inspector at (406) 291-9629.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Libby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Libby
Demolition / Building Move Permit in other cities
Compare demolition / building move permit fees across Montana →
Look up this fee in a different city →
Now live
Build your Libby project checklist