Demolition / Building Move Permit — Troy, Montana · Requirements sheet
Verified 2026-07-04 · Source: https://cityoftroymontana.com/wp-content/uploads/2023/10/Building-Permit-Application-2022.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition / Building Move Permit in Troy, Montana
Required for demolition or removal of any structure within Troy city limits, and for moving a structure, using the same City of Troy Building Permit Application with 'Demolition' or 'Move' checked under Type of Project. An asbestos/vermiculite inspection requirement applies before demolition, per the City's own packet and the Montana Asbestos Control Act.
Verified 2026-07-04 · Source
When you need this permit
- Complete the City of Troy Building Permit Application with 'Demolition' or 'Move' checked under Type of Project, including a description of the nature of the project and estimated cost
- Per ARM 17.74.354 and the City's own Building Permit Requirements packet: prior to any demolition or renovation, the owner/operator must ensure the facility is thoroughly inspected by a department-accredited asbestos inspector to determine whether asbestos-containing materials (including vermiculite) are present
- Contact the Asbestos Resource Program (ARP) Hotline at (406) 291-5335 before starting any job with potential asbestos exposure risk, per the City's own packet
- If vermiculite is found: for small quantities, wet the material and call the ARP Hotline (do not use a regular vacuum; HEPA vacuums are effective on small indoor quantities); for larger quantities, do not disturb the material — leave it alone and call the ARP Hotline
- During demolition: use water to moisten the area, rinse equipment used in the work area, keep debris wet and covered with a tarp during transport, and dispose of debris according to local, state, and federal landfill requirements, per the City's own packet
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition Asbestos Clearance
Department-accredited asbestos inspection must be completed and any required precautions addressed before demolition/renovation activities begin, per ARM 17.74.354 and the City's own packet.
- 2
Final
Site verified as cleared/restored consistent with the City's general Final Inspection practice.
See the full Troy inspection guide — scheduling & re-inspection fees →
Tips
- Troy sits within the same Lincoln County vermiculite/asbestos-legacy area as Libby; the City's own Building Permit Requirements packet devotes two full pages to ARP Hotline guidance and vermiculite handling — call (406) 291-5335 before beginning any demolition, remodeling, or excavation project.
- No fixed demolition bond amount was found published for Troy — confirm bonding/insurance and current fee amounts directly with Building Inspector David Jones at (406) 295-9851.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Troy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Troy
Demolition / Building Move Permit in other cities
Compare demolition / building move permit fees across Montana →