Demolition / Building Move Permit in Troy, Montana

Required for demolition or removal of any structure within Troy city limits, and for moving a structure, using the same City of Troy Building Permit Application with 'Demolition' or 'Move' checked under Type of Project. An asbestos/vermiculite inspection requirement applies before demolition, per the City's own packet and the Montana Asbestos Control Act.

Verified 2026-07-04 · Source

When you need this permit

  • Complete the City of Troy Building Permit Application with 'Demolition' or 'Move' checked under Type of Project, including a description of the nature of the project and estimated cost
  • Per ARM 17.74.354 and the City's own Building Permit Requirements packet: prior to any demolition or renovation, the owner/operator must ensure the facility is thoroughly inspected by a department-accredited asbestos inspector to determine whether asbestos-containing materials (including vermiculite) are present
  • Contact the Asbestos Resource Program (ARP) Hotline at (406) 291-5335 before starting any job with potential asbestos exposure risk, per the City's own packet
  • If vermiculite is found: for small quantities, wet the material and call the ARP Hotline (do not use a regular vacuum; HEPA vacuums are effective on small indoor quantities); for larger quantities, do not disturb the material — leave it alone and call the ARP Hotline
  • During demolition: use water to moisten the area, rinse equipment used in the work area, keep debris wet and covered with a tarp during transport, and dispose of debris according to local, state, and federal landfill requirements, per the City's own packet

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building/Demolition permit fee — valuation-based (same table)City of Troy Building Permit Requirements packet, Permit Fees table; no separate demolition-specific fee or bond amount was found published for Troy — this is reported as a genuine small-town publication gap after direct review of the City's packet, not an invented figure
$24 minimum ($1-$500 valuation), scaling per the City of Troy Permit Fees table

Review timeline

Plan review
Not published — contact the department

How long did your Demolition / Building Move Permit permit actually take in Troy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Demolition Asbestos Clearance

    Department-accredited asbestos inspection must be completed and any required precautions addressed before demolition/renovation activities begin, per ARM 17.74.354 and the City's own packet.

  2. 2

    Final

    Site verified as cleared/restored consistent with the City's general Final Inspection practice.

See the full Troy inspection guide — scheduling & re-inspection fees →

Tips

  • Troy sits within the same Lincoln County vermiculite/asbestos-legacy area as Libby; the City's own Building Permit Requirements packet devotes two full pages to ARP Hotline guidance and vermiculite handling — call (406) 291-5335 before beginning any demolition, remodeling, or excavation project.
  • No fixed demolition bond amount was found published for Troy — confirm bonding/insurance and current fee amounts directly with Building Inspector David Jones at (406) 295-9851.

Frequently asked questions

Yes. Use the City of Troy Building Permit Application with 'Demolition' or 'Move' checked. Because Troy sits within the same Lincoln County vermiculite/asbestos-contamination legacy area as Libby, an asbestos inspection is also required before demolition per ARM 17.74.354 — contact the Asbestos Resource Program Hotline at (406) 291-5335.

In Troy, the published Building/Demolition permit fee — valuation-based (same table) is: $24 minimum ($1-$500 valuation), scaling per the City of Troy Permit Fees table. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Troy does not publish a plan-review timeline for this permit. Contact City of Troy Building Department — Building Inspector David Jones; city-certified for Building (B), RESIDENTIAL ONLY, plus Swimming Pool (SP) permits. Commercial building permits, and Electrical, Plumbing, and Mechanical permits for ALL project types (residential and commercial), within Troy city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 295-4151 for current turnaround.

You'll need: City of Troy Building Permit Application (Demolition/Move); Asbestos Inspection Documentation. See the required-documents checklist on this page for details on each.

Troy requires 2 inspection(s) for a demolition / building move permit, in order: Pre-Demolition Asbestos Clearance, Final. Schedule each through City of Troy Building Department — Building Inspector David Jones; city-certified for Building (B), RESIDENTIAL ONLY, plus Swimming Pool (SP) permits. Commercial building permits, and Electrical, Plumbing, and Mechanical permits for ALL project types (residential and commercial), within Troy city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. ((406) 295-4151).

Apply through City of Troy Building Department — Building Inspector David Jones; city-certified for Building (B), RESIDENTIAL ONLY, plus Swimming Pool (SP) permits. Commercial building permits, and Electrical, Plumbing, and Mechanical permits for ALL project types (residential and commercial), within Troy city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at 301 E. Kootenai Avenue, Troy, MT 59935. Phone: (406) 295-4151, email: citytroy@troymt.net. Office hours: City Hall, 301 E. Kootenai Ave., Troy, MT 59935; Monday-Friday, 8:00 am to 5:00 pm (closed weekends/holidays); general line (406) 295-4151, email citytroy@troymt.net. Building Inspector David Jones direct line (406) 295-9851, email building.inspector@troymt.net.. Official information: https://cityoftroymontana.com/troy-city-council/city-hall/.

Troy, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; non-certified trades and non-certified project scopes in a partially-certified jurisdiction fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs (bsd.dli.mt.gov/building-codes-permits).; Troy is a Montana DLI-certified jurisdiction for Building (B), RESIDENTIAL ONLY, plus Swimming Pool (SP), within city limits; certified official on file with DLI: David Jones, (406) 295-9851. Verified directly against the DLI Building Codes Bureau's 'Montana Certified Local Government Program' roster PDF (fetched via browser-header curl and read directly with pdftotext, not taken on secondhand summary): 'Troy | B (residential only), SP | David Jones | 295-9851 | City Limits'. This means COMMERCIAL building permits within Troy city limits, and Electrical/Plumbing/Mechanical permits for ALL project types (residential and commercial), are issued DIRECTLY by the Montana DLI Building Codes Bureau, not the City. Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf; The City of Troy's own 'Building Permit Requirements' packet (dated February 7, 2023, filename Building Permit Application 2022.docx/pdf) references the '2009 IBC-IRC' on its Inspection Record card ('REMEMBER 2009 IBC-IRC required the permit holder to notify the building official when work is ready for inspection') — the City's packet has not been refreshed to reference the current 2021-edition code, even though the statewide code in force is now the 2021 edition. This is reported as an observed inconsistency in the City's own published document, not an invented fact — directly parallel to the same inconsistency found in Libby's packet.; Per the Montana DLI Building Codes Bureau's Current Codes page (statewide effective date June 11, 2022, applicable to all certified and state-enforced jurisdictions alike): 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 ISPSC, 2021 UPC, 2020 NEC, 2017 ICC A117.1 Accessibility. Source: bsd.dli.mt.gov/building-codes-permits/current-codes; Troy's own Building Permit Requirements packet does not separately name IECC, IEBC, or ISPSC edition years the way Libby's City page does — the City's packet references only the general 'City, State, and National regulations' framing and the 2009 IBC-IRC inspection-card citation noted above. No additional code-edition citations were found on the City's own materials beyond what is reported here; omitted rather than inferred.. Local amendments apply — see the Troy overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Troy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.