Electric Vehicle (EV) Charger Permit (State-Issued) — Troy, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/building-codes-permits/permit-applications/electrical-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charger Permit (State-Issued) in Troy, Montana
Electrical permits for ALL project types within Troy city limits (Troy is only DLI-certified for Building/Residential and Swimming Pool, not Electrical) are issued directly by the Montana DLI Building Codes Bureau in Helena, under the 2020 NEC — an EV charger/EVSE circuit installation therefore follows the same state Electrical Permit mechanism documented in the Electrical Permit (State-Issued) entry. The Bureau's own Application for Residential Electrical Permit (BCP-1) fee table has no dedicated EV-charger line item; the closest applicable category is 'H. 1 additional circuit or piece of equipment' ($45) or 'G. 2-3 additional circuits or pieces of equipment' ($70) if no panel/service change is involved, or the service-amperage-based categories already documented in the Electrical Permit (State-Issued) entry if the installation requires a panel/service upgrade.
Verified 2026-07-20 · Source
When you need this permit
- Application for Residential Electrical Permit (BCP-1) must be signed and dated by the licensed electrical contractor's person in charge, per the same process documented in the Electrical Permit (State-Issued) entry
- Payment must be submitted with the application; incomplete applications are returned unprocessed
- Applicant selects the applicable 'Type of Work' category on the state form — for a standalone EV charger circuit with no service/panel change, this is '1 additional circuit or piece of equipment' ($45) or '2-3 additional circuits or pieces of equipment' ($70); a panel upgrade to support the charger instead falls under the service-amperage-based categories already documented in the Electrical Permit (State-Issued) entry
- Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431
- No Troy-specific or DLI-published EV-charger-specific line item exists — this entry cites the closest real, applicable statewide fee categories rather than an invented EV-specific figure
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Montana Building Codes Bureau, Application for Residential Electrical Permit (BCP-1) — no dedicated EV-charger line exists; Show full citationHide
Montana Building Codes Bureau, Application for Residential Electrical Permit (BCP-1) — no dedicated EV-charger line exists; this is the closest applicable 'Single Family Interior/Exterior Wire or Rewire' category for a single added circuit. Note this differs from the $65 'renewable energy system' fee documented in the Solar PV Permit entry, since an EV charger consumes rather than generates power and is not a net-metering/generating system under Mont. Admin. r. 24.301.461.Review timeline
Inspection process
See the full Troy inspection guide — scheduling & re-inspection fees →
Tips
- EV charger permits for any Troy city-limits address are issued by the STATE Building Codes Bureau in Helena, not the city — mail applications and payment to PO Box 200517, Helena, MT 59620-0517, or apply online at ebiz.mt.gov.
- The BCP-1 form has no dedicated EV-charger checkbox — select the closest applicable 'Type of Work' category (most commonly '1 additional circuit or piece of equipment,' $45) rather than assuming a made-up EV-specific fee. Do not confuse this with the $65 renewable-energy-system fee documented in the Solar PV Permit entry, which applies to generating systems, not EV chargers.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Troy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Troy's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Troy yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Troy lands. Privacy.
Other permits in Troy
Electric Vehicle (EV) Charger Permit (State-Issued) in other cities
Compare electric vehicle (ev) charger permit (state-issued) fees across Montana →
Look up this fee in a different city →
Related guides
Now live
Build your Troy project checklist
Describe your project once and get every permit, document, and fee it triggers in Troy — in one checklist. Free, for any city and any number of projects.
Get started →