EV Charger / EVSE Permit (State-Issued Electrical Permit) — City of Deer Lodge, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/ApplicationResidentialElectrical.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (State-Issued Electrical Permit) in City of Deer Lodge, Montana
Installation of a Level 2 (or higher) electric vehicle charging station in the City of Deer Lodge is billed and issued under the same State Electrical Permit already documented on this file's electrical-permit entry — the Montana DLI Building Codes Bureau's BCP-1 Application for Residential (or Commercial) Electrical Permit has NO distinct EV-charger/EVSE line item; the form's fee schedule is organized entirely by service amperage, circuit count, and change-of-service type. A residential EV charger circuit is billed under the generic 'Interior/Exterior Wire or Rewire' circuit-addition tiers (or a 'Residential Change of Service' fee if the panel/service is also being upgraded to support the charger), the same mechanism used for any other new residential circuit. Because Deer Lodge is not DLI-certified for electrical, this is issued directly by the state Bureau, not the City Building Inspector.
Verified 2026-07-20 · Source
When you need this permit
- State electrical permits are required on all electrical work performed in Montana except in cities/counties/towns certified to issue electrical permits — the City of Deer Lodge is NOT certified for electrical, so an EV charging station circuit or dedicated EVSE outlet requires a State Electrical Permit
- Work must be performed by a Montana-licensed electrical contractor, or by the homeowner personally on their own owner-occupied home under a Homeowner Electrical Permit Owner-builder
- Confirmed directly against the BCP-1 Application for Residential Electrical Permit PDF: the form contains no separate 'EV charger,' 'electric vehicle,' or 'EVSE' fee line — an EV charger circuit is priced the same as any other new circuit or service change
- If installing a new charger requires upgrading the electrical panel or service size, the applicable 'Residential Change of Service' or amperage-tier fee (already documented on this file's electrical-permit entry) applies instead of/in addition to the circuit-addition fee
- Apply online at https://aca-prod.accela.com/bcb/ or mail the paper application with payment to: Department of Labor & Industry, Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Must be requested with 48 hours' notice before covering up work
- 2
Final
Charger circuit/outlet installed, GFCI/breaker sized correctly, energized; requires 48 hours' notice
See the full City of Deer Lodge inspection guide — scheduling & re-inspection fees →
Tips
- There is no distinct 'EV charger permit' in Deer Lodge or anywhere in Montana's state electrical permitting system — an EV charging circuit is simply a State Electrical Permit priced under the same circuit-addition or change-of-service fee tiers used for any other residential or commercial electrical work.
- The City of Deer Lodge Building Inspector does not process this permit at all; it is issued directly by the Montana DLI Building Codes Bureau since Deer Lodge is not electrical-certified.
- If the charger requires a panel upgrade, budget for the higher 'Residential Change of Service' fee tier rather than just the $45 single-circuit fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Deer Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of Deer Lodge
EV Charger / EVSE Permit (State-Issued Electrical Permit) in other cities
Compare ev charger / evse permit (state-issued electrical permit) fees across Montana →
Look up this fee in a different city →