Electric Vehicle (EV) Charger / EVSE Permit in Columbia Falls, Montana

Columbia Falls has no dedicated EV charger/EVSE-specific application, checklist, or fee line published -- confirmed against the City's Permits & Applications page (Building, Electrical, Mechanical, Plumbing Permit Applications) and its Electrical Permit Application form itself, mirroring the same gap already documented for the solar-pv-permit entry in this file. Columbia Falls is a Montana DLI-certified jurisdiction for Electrical, so this permit is issued and inspected locally by the City (unlike non-certified Montana jurisdictions such as Choteau and Colstrip elsewhere in this dataset, where it is issued by the state). An EVSE circuit installation is billed under the City's own itemized Electrical Permit fee schedule, governed by the 2020 NEC.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for EVSE circuit installation within Columbia Falls city limits, governed by the 2020 NEC
  • Issued and inspected locally by the City of Columbia Falls (Montana DLI-certified for electrical permitting)
  • No EV-charger-specific application, checklist, or fee line item was located; the closest itemized category is the City's amperage-service-based Single Family Dwelling fee tiers

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

A. Single Family Dwelling or Cabin (includes garage if wired at same time) -- 100 to 200 amp serviceCity of Columbia Falls Electrical Permit Application, Type A; includes temporary service and a maximum of 3 inspections. No dedicated EV/EVSE circuit-addition line item was found -- a standalone EVSE circuit that does not involve a new/upgraded service does not clearly map to a named fee tier on this form, confirmed directly on 2026-07-20
$200.00

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger / EVSE Permit permit actually take in Columbia Falls?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough / Final Electrical Inspection

    City electrical inspection of the EVSE circuit and connection (up to 3 inspections included per Type A permit)

See the full Columbia Falls inspection guide — scheduling & re-inspection fees →

Tips

  • Columbia Falls' Electrical Permit form is itemized by amperage service (e.g., $200 for 100-200 amp single-family service), not by individual circuit -- a standalone EVSE circuit addition that doesn't change the service size does not clearly correspond to a named fee tier; confirm the exact fee with Caleb Sobczak, Building/Planning/Public Works Technician, at (406) 892-4432 before applying.

Frequently asked questions

Columbia Falls requires an electric vehicle (ev) charger / evse permit for: Electrical permit required for EVSE circuit installation within Columbia Falls city limits, governed by the 2020 NEC; Issued and inspected locally by the City of Columbia Falls (Montana DLI-certified for electrical permitting); No EV-charger-specific application, checklist, or fee line item was located; the closest itemized category is the City's amperage-service-based Single Family Dwelling fee tiers. If your project isn't listed, confirm with City of Columbia Falls Building Department (Building, Planning & Public Works) at (406) 892-4391 before starting work.

No. Columbia Falls has no dedicated EV/EVSE permit or fee line. An EVSE circuit is billed under the City's itemized Electrical Permit fee schedule, which is organized by service amperage (e.g., $200.00 for 100-200 amp single-family service) rather than by individual circuit.

Columbia Falls does not publish a plan-review timeline for this permit. Contact City of Columbia Falls Building Department (Building, Planning & Public Works) at (406) 892-4391 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Columbia Falls requires 1 inspection(s) for an electric vehicle (ev) charger / evse permit, in order: Rough / Final Electrical Inspection. Schedule each through City of Columbia Falls Building Department (Building, Planning & Public Works) ((406) 892-4391).

Apply through City of Columbia Falls Building Department (Building, Planning & Public Works) at 130 6th St West, Columbia Falls, MT 59912. Phone: (406) 892-4391, email: sobczakc@cityofcolumbiafalls.com. Office hours: City Hall, 130 6th St West, Columbia Falls, MT 59912. Building/Planning/Public Works Clerk: Caleb Sobczak, (406) 892-4432, sobczakc@cityofcolumbiafalls.com. All building, electrical, mechanical, and plumbing permit applications begin at City Hall by contacting the Building Clerk; actual building inspections are scheduled directly with the City of Whitefish Building Department, (406) 863-2410, buildingdept@cityofwhitefish.gov, under a contractual inspection-services agreement between the two cities. Source: City of Columbia Falls Building Inspection & Code Enforcement page, cityofcolumbiafalls.org/1204/Building-Inspection-Code-Enforcement. Official information: https://www.cityofcolumbiafalls.org/1240/Permits-Applications.

Columbia Falls, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code (building, plumbing, electrical, mechanical, swimming pool, wildland-urban interface, etc.); a certified local program's adopted code 'may include only codes adopted by the Building Codes Bureau' (ARM 24.301.202). Non-certified trades/areas fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs and Current Codes pages (bsd.dli.mt.gov/building-codes-permits).; Columbia Falls is a Montana DLI-certified jurisdiction for Building (B), Plumbing (P), Electrical (E), Mechanical (M), Swimming Pool (SP), AND Wildland-Urban Interface (W) within Columbia Falls city limits — the fullest certification tier on the statewide DLI list (matched only by Whitefish and Bozeman). Certified Building Official of record: Tad Lisowski, per the DLI 'CITY CODES BUILDING OFFICIAL PHONE JURISDICTION' certified-jurisdictions PDF (bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf), updated 04/22/2026. Legend on that PDF: B = Building, P = Plumbing, M/G = Medical Gas, E = Electrical, M = Mechanical, SP = Pool, W = WUI (Wildland-Urban Interface). Tad Lisowski is also the certified building official of record for Whitefish, consistent with the two cities' shared building-inspection arrangement.; The City of Columbia Falls has adopted all 2021 building-related codes (2021 IBC, IRC, IEBC, IMC, IFGC, IECC, ISPSC editions as adopted statewide, effective June 11, 2022) per 'Administrative Order 2022 Building Code Adoption,' referenced on the City's Permits & Applications page. Source: City of Columbia Falls Permits & Applications page, cityofcolumbiafalls.org/1240/Permits-Applications.; 2021 International Building Code (IBC) — effective statewide June 11, 2022; adopted by City of Columbia Falls per Administrative Order 2022 Building Code Adoption; 2021 International Residential Code (IRC) — effective statewide June 11, 2022; adopted by City of Columbia Falls per Administrative Order 2022 Building Code Adoption; 2021 International Existing Building Code (IEBC) — effective statewide June 11, 2022; state-adopted edition applicable within Columbia Falls' certified Building program; 2021 International Mechanical Code (IMC) — effective statewide June 11, 2022; adopted by City of Columbia Falls per Administrative Order 2022 Building Code Adoption; 2021 International Fuel Gas Code (IFGC) — effective statewide June 11, 2022; state-adopted edition applicable within Columbia Falls' certified Mechanical program; 2021 International Energy Conservation Code (IECC) — effective statewide June 11, 2022; adopted by City of Columbia Falls per Administrative Order 2022 Building Code Adoption; the City's Building Permit Application requires ResCheck or the Prescriptive Method for energy-code compliance; 2021 Uniform Plumbing Code (UPC) — effective statewide June 11, 2022; state-adopted edition applicable within Columbia Falls' certified Plumbing program (Montana uses the Uniform Plumbing Code, not the International Plumbing Code); 2020 National Electrical Code (NEC) — effective statewide June 11, 2022; applicable within Columbia Falls' certified Electrical program per the City's Electrical Permit Application, which cites Title 50, Chapter 60, MCA and ARM 24.301.421/24.301.203; 2021 International Swimming Pool and Spa Code (ISPSC) — effective statewide June 11, 2022; Columbia Falls is DLI-certified for swimming pool (SP) permitting; 2021 International Fire Code (IFC) — state-adopted edition; the City's Building Permit Application references a 'Fire Prevention Program Fee' as a distinct line item collected with building permit fees; Wildland-Urban Interface (WUI) code provisions — Columbia Falls holds DLI 'W' certification, meaning the City (not the state) enforces WUI code requirements within city limits. Source: Montana DLI Building Codes Bureau certified-jurisdictions PDF.. Local amendments apply — see the Columbia Falls overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Columbia Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.