EV Charger / EVSE Permit in Anaconda-Deer Lodge, Montana
Required for installation of a residential electric vehicle charging circuit in Anaconda-Deer Lodge. Electrical permitting is NOT locally certified here — like all electrical work, an EV charger permit is issued and inspected directly by the Montana Department of Labor & Industry, Building Codes Bureau, under the 2020 National Electrical Code. The Bureau's fee schedule (BCP-1, Rev. 11/25) has no EV-charger/EVSE-specific line item — an EV charger circuit added to existing wiring is billed under the 'Interior/Exterior Wire or Rewire' category by number of added circuits.
Verified 2026-07-20 · Source
When you need this permit
- State electrical permit required — Anaconda-Deer Lodge (Deer Lodge County) is not certified for electrical, so all electrical work requires a State Electrical Permit from the Building Codes Bureau
- Work must be performed by a Montana-licensed electrical contractor, or by the homeowner personally on their own owner-occupied home under a Homeowner Electrical Permit Owner-builder
- Applied for online at aca-prod.accela.com/bcb or by mail to the Building Codes Bureau
- 48 hours' notice required before rough-in and final inspections
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
BCP-1 (Rev. 11/25). Both the $45 and $120 figures re-confirmed live 2026-07-20 by fetching bsd.dli.mt.gov/_docs/building-codes-permits/ApplicationResidentialElectrical.pdf directly (ARM 24.301.431, Rev. Show full citationHide
BCP-1 (Rev. 11/25). Both the $45 and $120 figures re-confirmed live 2026-07-20 by fetching bsd.dli.mt.gov/_docs/building-codes-permits/ApplicationResidentialElectrical.pdf directly (ARM 24.301.431, Rev. 11/25) — line H reads '1 additional circuit or piece of equipment.....................$45' and line E reads '4+circuits & change of serv &/or interior panel...........$120', both unchanged.Review timeline
Inspection process
- 1
Rough-In
Must be requested with 48 hours' notice before covering up work
- 2
Final
Charger installed, circuit verified, unit energized; requires 48 hours' notice
See the full Anaconda-Deer Lodge inspection guide — scheduling & re-inspection fees →
Tips
- Like all electrical work in Anaconda-Deer Lodge, an EV charger permit is a STATE permit issued by the Montana Building Codes Bureau in Helena, not by the county Building Inspector.
- No EV-specific fee exists — a standalone EV charger circuit is billed at the flat $45 'one additional circuit' rate; if a panel or service upgrade is also needed, the $120 'change of service and/or interior panel' tier applies instead.
- A homeowner may wire their own owner-occupied home under a Homeowner Electrical Permit; all other work requires a Montana-licensed electrical contractor. Owner-builder
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Anaconda-Deer Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Anaconda-Deer Lodge's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Anaconda-Deer Lodge yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Anaconda-Deer Lodge lands. Privacy.
Other permits in Anaconda-Deer Lodge
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Montana →
Look up this fee in a different city →
Related guides
Now live
Build your Anaconda-Deer Lodge project checklist
Describe your project once and get every permit, document, and fee it triggers in Anaconda-Deer Lodge — in one checklist. Free, for any city and any number of projects.
Get started →