EV Charger / EVSE Installation Permit — Billings, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://www.billingsmt.gov/DocumentCenter/View/1026/Electrical-Permit-Fees
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Installation Permit in Billings, Montana
Billings has no separate EV charger/EVSE permit category. A dedicated circuit for a home Level 2 EV charger is billed under the City of Billings Electrical Permit Fees schedule's existing 'Interior Rewire Only or New Addition to Home' line item, issued by the City of Billings Building Division (Billings is a Montana DLI-certified local jurisdiction for electrical permitting).
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for installing a new dedicated circuit, receptacle, or hardwired connection for an EV charger — governed by the 2020 NEC as adopted by the City of Billings (Administrative Order #150)
- No distinct 'EV charger' or 'EVSE' line item appears on the City's published Electrical Permit Fees schedule; the applicable category is 'Interior Rewire Only or New Addition to Home' for a circuit added to an existing panel with capacity, or 'Residential Change of Service' if the electrical service/panel must be upsized
- Apply through the CityView Portal (cityview.billingsmt.gov/Portal/)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In / Final
Same inspection sequence as any electrical permit: wiring and box placement before walls closed, then final device/panel verification per 2020 NEC
See the full Billings inspection guide — scheduling & re-inspection fees →
Tips
- Billings does not publish a distinct EV charger/EVSE fee line — apply for a standard electrical permit through the CityView Portal and select the rewire/addition or change-of-service category matching your project scope.
- If a new accessory structure (e.g., detached garage) houses the charger, the Private Property Accessory Building fee category applies instead.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Billings building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Billings
EV Charger / EVSE Installation Permit in other cities
Compare ev charger / evse installation permit fees across Montana →
Look up this fee in a different city →
Related guides
Now live
Build your Billings project checklist
Describe your project once and get every permit, document, and fee it triggers in Billings — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →