Certificate of Occupancy — Billings, Montana · Requirements sheet
Verified 2026-07-22 · Source: https://www.billingsmt.gov/132/Certificate-of-Occupancy
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Certificate of Occupancy in Billings, Montana
Billings does not offer a separate, standalone 'change of use' permit application or fee. A Certificate of Occupancy notifies owners, buyers, or other interested parties that required inspections have been performed and the structure complies with adopted building codes; it is issued as the final step of whichever building/trade permit(s) cover the underlying construction or use-change work, funded through the permit fees already paid for that work — not through a distinct change-of-use product. For remodels and small additions, the City may issue a Certificate of Final Inspection instead.
Verified 2026-07-22 · Source
When you need this permit
- A Certificate of Occupancy notifies owners, buyers, or other interested parties that required inspections have been performed and the structure is in compliance with the adopted building codes
- Issued after the applicable building/trade permit(s) have been obtained, all required inspections completed, and any code deficiencies identified during construction corrected
- Inspections and plan reviews supporting the Certificate of Occupancy are funded through the building permit fee already paid by the builder or applicant — the City does not publish an additional standalone 'change of use' or Certificate of Occupancy issuance fee
- For remodels and small additions, the City may issue a Certificate of Final Inspection instead of a full Certificate of Occupancy, confirming all required inspections are complete
- All required inspections and a Certificate of Occupancy must be obtained prior to transferring water service billing information for the property
- Final inspection must be requested through the Building Division with a minimum 24-hour notice; where the project includes fire protection systems, additional time must be reserved for system acceptance testing and fire-protection sub-contractors must be present on site
- No distinct 'change of use' or 'change of occupancy' permit type, application form, or fee schedule is published by the City of Billings Building Division; City Code Sec. 6-301(3) (legacy Uniform Building Code amendment, Section 1806) references a 'permit for change in occupancy or number of stories' only in the narrow context of certain reduced-depth slab-on-grade foundations, and does not establish a general change-of-use permit product
- A use change involving construction work is instead handled through whichever building/trade permit(s) cover that scope of work (e.g., the Residential or Commercial Building Permit for remodeling/tenant improvements), with the Certificate of Occupancy issued at completion of that permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection (Certificate of Occupancy)
All required trade and building inspections for the underlying permit(s) complete; project reviewed for adopted-code compliance; minimum 24-hour notice required; fire-protection sub-contractors must be on site if the project includes fire protection systems
See the full Billings inspection guide — scheduling & re-inspection fees →
Tips
- Billings has no separate change-of-use permit or fee — a use change involving construction is handled through the applicable building/trade permit for that scope of work, and the Certificate of Occupancy is issued when that permit's inspections are complete.
- Request the final inspection with at least 24 hours' notice, and budget extra time (plus on-site fire-protection sub-contractors) if the project includes sprinkler or alarm systems.
- All required inspections and the Certificate of Occupancy must be obtained before water service billing can be transferred for the property.
- For remodels and small additions, ask the Building Division whether a Certificate of Final Inspection (rather than a full Certificate of Occupancy) applies to your project.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Billings building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Billings
Certificate of Occupancy in other cities
Compare certificate of occupancy fees across Montana →
Look up this fee in a different city →