Certificate of Occupancy / Change of Use Permit in Artesia, New Mexico
Required before any change in the use or occupancy of land, or any change of use or occupancy in an existing building (other than for single-family dwelling purposes), and before any new building may be occupied, within Artesia city limits, per City Code of Ordinances Title 9 (Zoning), Chapter 13, Sec. 9-13-4. Also issued as the final step of the City's standard building-permit process once all required trade inspections are approved.
Verified 2026-07-22 · Source
When you need this permit
- No change in the use or occupancy of land, nor any change of use or occupancy in an existing building other than for single-family dwelling purposes, shall be made, nor shall any new building be occupied, until a certificate of occupancy has been issued by the building inspector/code enforcement officer, per Sec. 9-13-4(A)(1)
- No building or premises shall be occupied until the certificate of occupancy (and, where applicable, the underlying building permit) has been issued, per Sec. 9-13-4(A)(2)
- Every certificate of occupancy must state that 'the new occupancy complies with all provisions of this title,' per Sec. 9-13-4(B)
- The building inspector/code enforcement officer keeps certificate-of-occupancy records on file and provides copies on request to persons with a proprietary or tenancy interest in the affected property, per Sec. 9-13-4(C)
- For new construction and additions/alterations processed on the standard Building Permit track, the Certificate of Occupancy is issued as the final step once the final general construction inspection is approved, and final electrical, plumbing, and mechanical inspections have already been completed -- see this file's Residential and Commercial Building Permit entries
- Per the City's own FAQ, the Certificate of Occupancy confirms work meets applicable codes and is required before occupancy and for most mortgage lending
- For a manufactured home, the final Certificate of Occupancy is issued by the State of New Mexico Manufactured Housing Division, not the City, following City inspection of electrical, plumbing, and setbacks -- see this file's Manufactured Home Permit entry
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final General Construction Inspection
Confirms the new occupancy or change of use complies with all provisions of Title 9 (Zoning) and, where applicable, that final electrical, plumbing, and mechanical inspections have already been approved; the Certificate of Occupancy is issued once this inspection is approved
See the full Artesia inspection guide — scheduling & re-inspection fees →
Tips
- A Certificate of Occupancy is required even for a pure change of use in an EXISTING building with no construction taking place -- e.g., converting a retail space to a restaurant -- not just for new construction; the only exemption in Sec. 9-13-4 is for single-family dwelling purposes.
- For new construction and remodels processed through the standard Building Permit track, the Certificate of Occupancy is issued once the final general construction inspection is approved, with no separate standalone application needed -- see this file's Residential and Commercial Building Permit entries.
- Manufactured homes are the one documented exception: the final Certificate of Occupancy for a manufactured home is issued by the State of New Mexico Manufactured Housing Division, not the City -- see this file's Manufactured Home Permit entry.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Artesia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Artesia
Certificate of Occupancy / Change of Use Permit in other cities
Compare certificate of occupancy / change of use permit fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Artesia project checklist
Describe your project once and get every permit, document, and fee it triggers in Artesia — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →