Required for new single-family and two-family dwelling construction within Artesia city limits. The City of Artesia issues the permit directly through its Community Development Department / Planning & Zoning Division -- there is no separate New Mexico CID submittal step for work inside city limits, since Artesia self-administers under the dynamic 'latest edition adopted by the state' code-adoption clauses in its own Title 8 ordinance.

Verified 2026-07-18 · Source

When you need this permit

  • Building permit required before any regulated building or structure is erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted, or demolished, per the City's 'Residential Building Permit Guide' (citing NMRBC R106.1)
  • Limited exemptions exist (e.g., detached accessory structures 120 sq ft or less used as tool/storage sheds still require a plan-review permit; retaining walls 4 ft or less; decks 200 sq ft or less that are not more than 30 inches above grade and not attached at a required egress door) -- per NMRBC R105.2 as cited in the City's own guide; even exempted work still requires separate electrical/plumbing/mechanical permits where applicable
  • Complete a Building Permit Application (universal City form covering Building/Electrical/Plumbing/Mechanical/Gas/Fence/Sign/Lane-Alley Closure/Other) identifying owner, contractor (with NM State license number and classification) or a notarized Homeowner's Responsibilities checklist, responsible design professional, project description, valuation, and total square footage
  • Submit two (2) complete sets of building plans plus two (2) plot plans (residential); the City's plan-submission instructions state plans should be scaled to 1/4in = 1ft-0in on paper no smaller than 11in x 17in, while a separate residential plan-requirements handout states a 1/8in minimum scale -- both documents are current on the City's site and are not fully reconciled with each other, so confirm the required scale with Planning & Zoning before submitting
  • A signed copy of the contract between the project owner and the contractor must be submitted with the application; project valuation for fee purposes is based on Municipal Code Title 8 Chapter 1
  • Zoning approval from the City of Artesia or Eddy County may be required and must be obtained before submitting the building permit application, depending on the project's location
  • A separate septic-tank permit from the local New Mexico Environment Department office is required if an individual liquid-waste system is being modified or installed (not part of the City's own building permit)
  • Professional (architect/structural engineer) seals are required for certain construction types per NMAC 14.5.2.10(B) as cited in the City's guide (e.g., steel-stud/structural-steel construction, all pre-fabricated/pre-manufactured/component structures, wood foundations, retaining walls over 3 ft, second-story additions, and alternative materials/methods), but are not required for ordinary 1-2 story single-family/duplex construction absent such conditions

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee -- valuation $1,000City of Artesia Building Permit Fee schedule (Municipal Code Title 8 Chapter 1), artesianm.gov/DocumentCenter/View/1763 -- no printed effective date on the PDF itself; fee schedule is set by City Council resolution per Code of Ordinances Sec. 8-1-6
$50.00
Building Permit Fee -- valuation $10,000City of Artesia Building Permit Fee schedule, artesianm.gov/DocumentCenter/View/1763
$76.00
Building Permit Fee -- valuation $25,000City of Artesia Building Permit Fee schedule, artesianm.gov/DocumentCenter/View/1763
$130.00
Building Permit Fee -- valuation $50,000City of Artesia Building Permit Fee schedule, artesianm.gov/DocumentCenter/View/1763
$220.00
Building Permit Fee -- valuation $100,000City of Artesia Building Permit Fee schedule, artesianm.gov/DocumentCenter/View/1763
$400.00
Building Permit Fee -- valuation over $100,000City of Artesia Building Permit Fee schedule states: '* Over $100,000: Fee = $400 + (Total - 100.00/1000) or *Add $1 per $1,000 over' -- transcribed verbatim; artesianm.gov/DocumentCenter/View/1763
$400.00 plus $1.00 per additional $1,000 of valuation over $100,000

Review timeline

Plan reviewArtesia’s published plan-review target
2+ business days

How long did your Residential Building Permit (New Construction) permit actually take in Artesia?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    After excavation of footings and placement of any required reinforcing steel; the Ufer ground must be installed near the proposed electrical service panel location; anchor bolts and other foundation materials must be on the job

  2. 2

    Concrete Slab or Under-Floor

    After all in-slab or under-floor building service equipment, conduit, piping, and accessories are in place, but before concrete is placed or floor sheathing/sub-floor is installed

  3. 3

    Frame

    After roof, framing, fire blocking and bracing are complete, all pipes/chimneys/vents are complete, and rough electrical, plumbing, and mechanical inspections have been approved

  4. 4

    Weather Resistive Barrier

    After installation of the appropriate weather-resistive barrier and before it is covered

  5. 5

    Final

    After finish grading and completion; final electrical, plumbing, and mechanical inspections must be completed first; a Certificate of Occupancy is issued once the final general construction inspection is approved

See the full Artesia inspection guide — scheduling & re-inspection fees →

Tips

  • Artesia has expansive clay soils; the City's 'Policy for Residential Foundations' either requires an engineered geotechnical foundation design or, in lieu of one, a specific prescriptive foundation (24in native-soil removal and compaction, monolithic slab rebar mat, 18in x 24in perimeter footings) -- budget for this regardless of which path is chosen.
  • The universal Building Permit Application covers Building, Electrical, Plumbing, Mechanical, Gas, Fence, Sign, and Lane/Alley Closure permit types on one form -- check the correct 'Permit Type' box; project valuation is explicitly NOT required for electrical/plumbing/mechanical/gas permit types on the same form.
  • Plan reviews are conducted specifically on Tuesdays and Thursdays; submitting just before one of those days may speed the first review cycle.
  • Work must begin within 180 days of permit issuance or the permit expires and a new permit and fee are required, per the City's FAQ.

Frequently asked questions

Artesia requires a residential building permit (new construction) for: Building permit required before any regulated building or structure is erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted, or demolished, per the City's 'Residential Building Permit Guide' (citing NMRBC R106.1); Limited exemptions exist (e.g., detached accessory structures 120 sq ft or less used as tool/storage sheds still require a plan-review permit; retaining walls 4 ft or less; decks 200 sq ft or less that are not more than 30 inches above grade and not attached at a required egress door) -- per NMRBC R105.2 as cited in the City's own guide; even exempted work still requires separate electrical/plumbing/mechanical permits where applicable; Complete a Building Permit Application (universal City form covering Building/Electrical/Plumbing/Mechanical/Gas/Fence/Sign/Lane-Alley Closure/Other) identifying owner, contractor (with NM State license number and classification) or a notarized Homeowner's Responsibilities checklist, responsible design professional, project description, valuation, and total square footage; Submit two (2) complete sets of building plans plus two (2) plot plans (residential); the City's plan-submission instructions state plans should be scaled to 1/4in = 1ft-0in on paper no smaller than 11in x 17in, while a separate residential plan-requirements handout states a 1/8in minimum scale -- both documents are current on the City's site and are not fully reconciled with each other, so confirm the required scale with Planning & Zoning before submitting; A signed copy of the contract between the project owner and the contractor must be submitted with the application; project valuation for fee purposes is based on Municipal Code Title 8 Chapter 1; Zoning approval from the City of Artesia or Eddy County may be required and must be obtained before submitting the building permit application, depending on the project's location; A separate septic-tank permit from the local New Mexico Environment Department office is required if an individual liquid-waste system is being modified or installed (not part of the City's own building permit); Professional (architect/structural engineer) seals are required for certain construction types per NMAC 14.5.2.10(B) as cited in the City's guide (e.g., steel-stud/structural-steel construction, all pre-fabricated/pre-manufactured/component structures, wood foundations, retaining walls over 3 ft, second-story additions, and alternative materials/methods), but are not required for ordinary 1-2 story single-family/duplex construction absent such conditions. If your project isn't listed, confirm with City of Artesia Community Development Department -- Planning & Zoning Division / Building Inspection (self-administering city building department; permits are issued directly by the City, not routed through the NM Construction Industries Division) at (575) 748-8298 (Planning & Zoning / Permit Technician Elida Martinez); Don Plotner, Res. Building/Plumbing/Mechanical Inspector (listed elsewhere on the City site as 'Chief Building Official'), (575) 748-8295; Fire Marshal Brenden Harvey (575) 746-5051 for the fire-department sign-off required on many non-1-and-2-family-home permits before starting work.

In Artesia, the published Building Permit Fee -- valuation $1,000 is: $50.00. Additional published fees: Building Permit Fee -- valuation $10,000 — $76.00; Building Permit Fee -- valuation $25,000 — $130.00; Building Permit Fee -- valuation $50,000 — $220.00; Building Permit Fee -- valuation $100,000 — $400.00; Building Permit Fee -- valuation over $100,000 — $400.00 plus $1.00 per additional $1,000 of valuation over $100,000. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City's own Residential Permit Application Procedure: 'Plan reviews are done on Tuesdays and Thursdays. Depending on your project, the permit may take from 2 days to several weeks to be issued.' The City states no firm maximum -- complex projects can take considerably longer than the 2-day minimum. Source: City of Artesia, artesianm.gov/DocumentCenter/View/63.

You'll need: Building Permit Application; Construction Drawings / Site Plan (2 sets); Signed Owner-Contractor Contract. Depending on your project, Artesia may also ask for: Homeowner's Responsibilities Checklist (notarized). See the required-documents checklist on this page for details on each.

Artesia requires 5 inspection(s) for a residential building permit (new construction), in order: Foundation, Concrete Slab or Under-Floor, Frame, Weather Resistive Barrier, Final. Schedule each through City of Artesia Community Development Department -- Planning & Zoning Division / Building Inspection (self-administering city building department; permits are issued directly by the City, not routed through the NM Construction Industries Division) ((575) 748-8298 (Planning & Zoning / Permit Technician Elida Martinez); Don Plotner, Res. Building/Plumbing/Mechanical Inspector (listed elsewhere on the City site as 'Chief Building Official'), (575) 748-8295; Fire Marshal Brenden Harvey (575) 746-5051 for the fire-department sign-off required on many non-1-and-2-family-home permits).

Apply through City of Artesia Community Development Department -- Planning & Zoning Division / Building Inspection (self-administering city building department; permits are issued directly by the City, not routed through the NM Construction Industries Division) at Planning & Zoning physical address per the City's current Building Permits and Building Inspection webpages: 15 E Compress Rd., Artesia, NM 88210 (mailing: PO Box 1310, Artesia, NM 88211-1310). Note: the City's own materials are not fully consistent on this point -- the City's live FAQ (artesianm.gov/Faq.aspx?QID=199 and related Q's) separately states 'the Permit office is located at 119 S Roselawn STE 303,' and the Building Permit Application form and several plan-requirement/policy PDFs (Community Development Department letterhead) list 801 W. Bush Ave. / 801 Bush St., Artesia, NM 88210. All three addresses appear on current or recently-dated official City of Artesia materials; confirm the current in-person intake location by phone before visiting.. Phone: (575) 748-8298 (Planning & Zoning / Permit Technician Elida Martinez); Don Plotner, Res. Building/Plumbing/Mechanical Inspector (listed elsewhere on the City site as 'Chief Building Official'), (575) 748-8295; Fire Marshal Brenden Harvey (575) 746-5051 for the fire-department sign-off required on many non-1-and-2-family-home permits, email: buildingpermits@artesianm.gov. Office hours: Monday through Friday, 7:30 a.m. to 4:30 p.m. Fax: (575) 746-8502. Plan reviews are conducted on Tuesdays and Thursdays specifically, per the City's own Residential and Commercial Permit Application Procedure documents.. Official information: https://www.artesianm.gov/280/Building-Permits.

Artesia, New Mexico has adopted: The City of Artesia Code of Ordinances, Title 8 'Building Regulations,' Chapter 1 'Building Codes; Fees' (current through Ord. O-1135, passed 8-13-2024, per amlegal.com's currency statement), was retrieved and reviewed section-by-section this pass via codelibrary.amlegal.com. Sec. 8-1-1 (Building Code) and Sec. 8-1-2 (Residential Code) each provide: 'The city adopts by this section all conditions, provisions, limitations and terms of the latest edition of the building [or residential] code adopted by the state, and all amendments thereto' (Ord. 911, 2-12-2013) -- i.e., a dynamic, 'latest edition adopted by the state' reference rather than a fixed year, the same self-administering pattern independently verified for Carlsbad (also in Eddy County). Sec. 8-1-3 (Plumbing and Mechanical Code) adopts, in the same dynamic language, 'the latest edition of the plumbing and mechanical code adopted by the state' (Ord. 911, 2-12-2013). Source: City of Artesia Code of Ordinances 8-1-1, 8-1-2, 8-1-3, codelibrary.amlegal.com/codes/artesianm/latest/artesia_nm/; Because Sec. 8-1-1/8-1-2/8-1-3 reference the state's currently-adopted codes rather than a fixed edition, the operative statewide-minimum codes Artesia currently enforces are the same current CID-enforced cycle independently verified for Carlsbad (per CID's Building Permit Guide for Residential Construction, rev. 10/2024, and NMAC Title 14): 2021 New Mexico Commercial Building Code (based on 2021 IBC) -- NMAC 14.7.2; 2021 New Mexico Residential Building Code (based on 2021 IRC) -- NMAC 14.7.3; 2021 New Mexico Residential Energy Conservation Code -- NMAC 14.7.6 (effective 7/30/2024); 2021 New Mexico Commercial Energy Code -- NMAC 14.7.9 (effective 7/30/2024); 2021 New Mexico Existing Building Code -- NMAC 14.7.7; 2021 New Mexico Plumbing Code -- NMAC 14.8.2; 2021 New Mexico Mechanical Code -- NMAC 14.9.2; 2020 New Mexico Electrical Code (based on 2020 NEC) -- NMAC 14.10.4. Separately, the City's own 'Residential Building Permit Guide' plan-submittal PDF (DocumentCenter/View/54) still lists a stale 'APPLICABLE CODES' block naming the 2009 NM Commercial/Residential Building Code, 2009 IBC/IRC, 2009 NM Energy Conservation Code, 2009 NM Plumbing and Mechanical Code, and a 2014 NM Electrical Code -- the same 'un-updated legacy PDF text vs. dynamic ordinance clause' pattern already documented for Carlsbad's Chapter 8; the dynamic ordinance language controls, not the stale PDF table. Source: City of Artesia 'Residential Building Permit Guide,' artesianm.gov/DocumentCenter/View/54; NM RLD/CID Building Permit Guide for Residential Construction, rev. 10/2024 (rld.nm.gov); Sec. 8-1-4 (Fire and Safety Codes) separately and specifically adopts 'the international fire code, 2015 edition, including appendices B, C and D' with City-specific amendments to Sections 101.1 (jurisdiction name insert), 109.4 (violation = misdemeanor, $500, 90 days), 105.7 (Required Construction Permits, rewritten), 105.7.9 (Gates/Fences/Barricades near fire apparatus roads/hydrants), 105.7.13 (Fire Hydrants), 105.7.19 (Means of Egress, added), and 105.7.20 (Demolitions, added: 'A permit is required for the demolition of any structure ... including but not limited to, buildings, fire department access roads, bridges, or towers'). Source: City of Artesia Code of Ordinances 8-1-4, codelibrary.amlegal.com/codes/artesianm/latest/artesia_nm/; Sec. 8-1-7 (Existing Building Code) adopts 'all conditions, provisions, limitations and terms of the latest edition of the International Existing Building Code adopted by the State, and all amendments thereto; known as the New Mexico Existing Building Code (NMEBC)' (dated 2019 in the ordinance history). Sec. 8-1-9 (National Electrical Code) and Sec. 8-1-10 (National Electric Safety Code) each separately adopt 'the latest edition' of those national documents (Ord. 911, 2-12-2013), while Sec. 8-1-11 (State Electrical Code and Electrical Safety Code) separately adopts 'the New Mexico Electrical Code (14.10.4 NMAC)' (Ord. 911, 2-12-2013) -- three overlapping electrical-code sections as codified, rather than a single citation. Source: City of Artesia Code of Ordinances 8-1-7, 8-1-9, 8-1-10, 8-1-11, codelibrary.amlegal.com/codes/artesianm/latest/artesia_nm/; Sec. 8-1-8 (Property Maintenance Code) adopts the International Property Maintenance Code, 2018 edition (Ord. 1045, 1-8-2019), with an extensive table of City-specific amendments, including Sec. 102.7 ('All references in the IPMC to the International Building Code shall be deemed references to the latest edition of the New Mexico Commercial Building Code (NMCBC)' and parallel deeming clauses for NMRBC/NMEBC/NMPC/NMMC/NMEC/NMECC) and Sec. 103.2/103.3 designating the City's Chief Building Official as 'the code official' and the City's code enforcement officer, building inspector, and planning and zoning administrator as deputies. Source: City of Artesia Code of Ordinances 8-1-8, codelibrary.amlegal.com/codes/artesianm/latest/artesia_nm/; Sec. 8-1-6 (Fees) provides that 'The City Council shall establish by resolution a schedule of fees, charges and expenses for building, plumbing, mechanical and electrical permits and inspections,' rather than codifying the fee tables directly in the ordinance text -- this matches the three standalone fee-schedule PDFs published on the City's own Fees page (artesianm.gov/279/Fees), each headed 'Municipal Code Title 8 Chapter 1' but carrying no printed effective date of their own. Source: City of Artesia Code of Ordinances 8-1-6; Building Permit Fee (PDF), Electrical Permit Fee (PDF), and Plumbing Mechanical Permit Fee (PDF), artesianm.gov/279/Fees. Local amendments apply — see the Artesia overview page for the full list.

Yes, but it requires completing and having notarized a 'Homeowner's Responsibilities' checklist acknowledging the risks and limitations of a Homeowner's Permit (e.g., a homeowner may not perform electrical or plumbing work without passing a homeowner's exam, and may never perform HVAC or gas work under a Homeowner's Permit). Source: City of Artesia, artesianm.gov/DocumentCenter/View/169.