EV Charger / EVSE Permit — Artesia, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.artesianm.gov/DocumentCenter/View/1764
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Artesia, New Mexico
Required for installation of a residential electric vehicle charging circuit in Artesia. Filed on the universal Building Permit Application with 'Electrical' checked, billed under the City's flat amperage-based Electrical Fee Schedule. The schedule (Municipal Code Title 8 Chapter 1) has no EV-charger/EVSE-specific line item — a Level 2 EV charger circuit that is not a service change is billed under the schedule's 'For items not listed' catch-all fee.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the new EV charger circuit, per the City's 'Do I Need A Permit?' chart
- Project valuation is explicitly not required for electrical permits — this is a flat fee schedule, not valuation-based
- If the install also constitutes a service change (e.g. panel/service upgrade), the flat $45.00 'Service change only' line item applies instead
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring and box placement before walls are closed
- 2
Final
Charger installed, circuit verified, unit energized
See the full Artesia inspection guide — scheduling & re-inspection fees →
Tips
- Artesia's Electrical Fee Schedule has no EV charger/EVSE-specific fee — a standard EV charger circuit that isn't a service change falls under the flat $45.00 'For items not listed' catch-all line item.
- If the install requires a panel/service upgrade, the $45.00 'Service change only' fee (or the applicable amperage tier if the whole service is being upsized) applies instead.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Artesia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Artesia
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across New Mexico →
Look up this fee in a different city →
Related guides
Now live
Build your Artesia project checklist
Describe your project once and get every permit, document, and fee it triggers in Artesia — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →