New Residential Building Permit (New Construction / Addition / Accessory Building) in Bloomfield, New Mexico

Required for new single-family residential construction, additions, and accessory buildings within Bloomfield. Although Bloomfield's Planning and Zoning Department is the first point of contact for zoning compliance, the actual building permit for structures within Bloomfield city limits is issued and inspected by the San Juan County Building Division, which administers building permitting for the City of Bloomfield under its cross-jurisdictional program.

Verified 2026-07-18 · Source

When you need this permit

  • New residential construction, addition, or accessory building (detached storage sheds/garages) within Bloomfield city limits — per San Juan County Building Division's New Residential Permit Application Checklist (revised 07/19/2023)
  • Planning/Zoning approval from the City of Bloomfield Planning and Zoning Department is required (checklist item 9) before or alongside the County building permit, since Bloomfield is one of the jurisdictions (with Aztec and Kirtland) where zoning approval applies
  • Must comply with the 2021 New Mexico Residential Building Code (2021 IRC as amended)
  • Site address must be assigned by San Juan County, City of Bloomfield, or City of Aztec addressing
  • New Mexico's homeowner permit exemption (14.5.2 NMAC) allows a property owner to obtain the permit for their own primary residence without a contractor license, provided the homeowner performs the major portion of the work Contractor
  • Floodplain approval required if applicable
  • A separate City of Bloomfield Building and Zoning Compliance Application ($25 fee) is also required at the City level for zoning/address/setback verification

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeSan Juan County Building Department page (sjcounty.net/government/community-development/building-department), 'Plan Review' section: 'Building Permit Fee: valuation of project x .005.' Project valuations are determined using the latest ICC Building Valuation Data for new construction/additions, or contract price for alterations/repairs.
Project valuation × 0.005
Building Plan Review FeeSan Juan County Building Department page, applies to buildings/structures requiring an Architect or Engineer seal under NMAC 14.5.2.9/14.5.2.10 and the Architectural Act (61-15-9 NMSA 1978); charged in addition to the Building Permit Fee.
Project valuation × 0.0012
Building and Zoning Compliance Application (City of Bloomfield)City of Bloomfield Planning & Zoning Fees 2022 schedule (bloomfieldnm.gov/media/466), 'Building and Zoning Compliance Application' line item.
$25.00

Review timeline

Plan reviewBloomfield’s published plan-review target
14–14 business days

How long did your New Residential Building Permit (New Construction / Addition / Accessory Building) permit actually take in Bloomfield?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing

    Forms and rebar in place prior to placement of concrete.

  2. 2

    Foundation Wall / Monolithic Slab

    Concrete block, ICF block, or concrete forms with reinforcement in place prior to placement of concrete.

  3. 3

    Electrical Under Slab

    Raceway runs prior to covering trench.

  4. 4

    Plumbing Under Slab

    DWV with test prior to covering trench; in-floor heat with air test.

  5. 5

    Slab on Grade

    After electrical and plumbing under-slab inspections, prior to placement of concrete.

  6. 6

    Rough Electrical

    Electric service, feeders, and branch circuits complete to termination.

  7. 7

    Rough Plumbing

    DWV top-out through roof with test, gas piping with test, water piping with test.

  8. 8

    Rough Heating and Ventilation

    Appliance vents through roof, trunk line and taps installed, combustion air provided, exhaust ducts complete.

  9. 9

    Framing

    After rough electrical, plumbing, and mechanical are complete and approved; windows in place; foundation and roof vents installed; air barrier requirements complete.

  10. 10

    Insulation

    Exterior walls complete; ceiling complete if batted.

  11. 11

    Electrical Final

    Panel board labeled, cover plate on, switches/outlets connected, fixtures in place.

  12. 12

    Plumbing Final

    Fixtures in place, water supply functional, gas appliances installed and connected.

  13. 13

    Mechanical Final

    Gas appliances connected and operational, vent terminations complete, grills in place, cooling units functional.

  14. 14

    Building Final

    Last inspection prior to occupancy approval; a Certificate of Occupancy is required before use or occupancy.

See the full Bloomfield inspection guide — scheduling & re-inspection fees →

Tips

  • Inspections must be requested at least 24 hours in advance by calling the San Juan County Building Division at (505) 334-4313.
  • A storage shed under 120 square feet (generally 10' x 12') does not require a building permit, per the County Building Department's published FAQ; a carport does require one.
  • Confirm the applicable zoning district's setbacks with Bloomfield Planning & Zoning (505-632-6304) before design — e.g., the City's R-1 district requires a 7,000 sq ft minimum lot, 25-foot front setback (29 feet if no sidewalk), 5.5-foot side setback, and 20-foot rear setback, which differ from the County's unincorporated-area baseline.
  • Detached storage sheds and garages are regulated as 'Residential Accessory Structures'; homes, habitable pool houses, and mother-in-law suites are regulated as 'New Residential' under the County's checklist.
  • Permits issued by San Juan County expire one year from issuance and may be renewed for one additional year, prior to expiration, for half the original permit fee.

Frequently asked questions

Bloomfield requires a new residential building permit (new construction / addition / accessory building) for: New residential construction, addition, or accessory building (detached storage sheds/garages) within Bloomfield city limits — per San Juan County Building Division's New Residential Permit Application Checklist (revised 07/19/2023); Planning/Zoning approval from the City of Bloomfield Planning and Zoning Department is required (checklist item 9) before or alongside the County building permit, since Bloomfield is one of the jurisdictions (with Aztec and Kirtland) where zoning approval applies; Must comply with the 2021 New Mexico Residential Building Code (2021 IRC as amended); Site address must be assigned by San Juan County, City of Bloomfield, or City of Aztec addressing; New Mexico's homeowner permit exemption (14.5.2 NMAC) allows a property owner to obtain the permit for their own primary residence without a contractor license, provided the homeowner performs the major portion of the work; Floodplain approval required if applicable; A separate City of Bloomfield Building and Zoning Compliance Application ($25 fee) is also required at the City level for zoning/address/setback verification. If your project isn't listed, confirm with City of Bloomfield Planning and Zoning Department (building-permit first point of contact and zoning authority) — actual building, electrical, plumbing, and mechanical permits for structures within Bloomfield city limits are issued and inspected by the San Juan County Building Division, which administers building permitting for the City of Aztec, the City of Bloomfield, and the Town of Kirtland in addition to unincorporated San Juan County. at (505) 632-6304 (Bloomfield Planning & Zoning Director Crystal Martinez); (505) 632-6300 (City of Bloomfield main line); (505) 334-4313 (San Juan County Building Division, for building/electrical/plumbing/mechanical permits and inspections) before starting work.

In Bloomfield, the published Building Permit Fee is: Project valuation × 0.005. Additional published fees: Building Plan Review Fee — Project valuation × 0.0012; Building and Zoning Compliance Application (City of Bloomfield) — $25.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

San Juan County's New Residential Permit Application Checklist states a minimum of two (2) weeks for plan review after all required documents are submitted; this is a published floor, not a guaranteed maximum.

You'll need: New Residential Permit Application Checklist; Application for Building and Zoning Compliance. See the required-documents checklist on this page for details on each.

Bloomfield requires 14 inspection(s) for a new residential building permit (new construction / addition / accessory building), in order: Footing, Foundation Wall / Monolithic Slab, Electrical Under Slab, Plumbing Under Slab, Slab on Grade, Rough Electrical, Rough Plumbing, Rough Heating and Ventilation, Framing, Insulation, Electrical Final, Plumbing Final, Mechanical Final, Building Final. Schedule each through City of Bloomfield Planning and Zoning Department (building-permit first point of contact and zoning authority) — actual building, electrical, plumbing, and mechanical permits for structures within Bloomfield city limits are issued and inspected by the San Juan County Building Division, which administers building permitting for the City of Aztec, the City of Bloomfield, and the Town of Kirtland in addition to unincorporated San Juan County. ((505) 632-6304 (Bloomfield Planning & Zoning Director Crystal Martinez); (505) 632-6300 (City of Bloomfield main line); (505) 334-4313 (San Juan County Building Division, for building/electrical/plumbing/mechanical permits and inspections)).

Apply through City of Bloomfield Planning and Zoning Department (building-permit first point of contact and zoning authority) — actual building, electrical, plumbing, and mechanical permits for structures within Bloomfield city limits are issued and inspected by the San Juan County Building Division, which administers building permitting for the City of Aztec, the City of Bloomfield, and the Town of Kirtland in addition to unincorporated San Juan County. at City of Bloomfield Planning and Zoning: 915 N. 1st Street, P.O. Box 1839, Bloomfield, NM 87413. San Juan County Building Division: 100 South Oliver Drive, Aztec, NM 87410.. Phone: (505) 632-6304 (Bloomfield Planning & Zoning Director Crystal Martinez); (505) 632-6300 (City of Bloomfield main line); (505) 334-4313 (San Juan County Building Division, for building/electrical/plumbing/mechanical permits and inspections), email: No department email is published on the City's Planning and Zoning page as of 2026-07-18 (a staff 'Email' contact link is provided but does not resolve to a visible address; phone is the published contact method); communitydevelopment@sjcounty.net (San Juan County Community Development, per the County's online permitting portal). Office hours: City of Bloomfield Planning & Zoning: Monday–Thursday 7:00 am–5:30 pm; Friday closed. San Juan County Building Division: reachable at (505) 334-4313; all inspections must be requested at least 24 hours in advance (commercial and residential building permit applications both state 'a minimum of 24 hours is required for an inspection notification').. Official information: https://www.bloomfieldnm.gov/planning-and-zoning.

Bloomfield, New Mexico has adopted: 2021 New Mexico Commercial Building Code (2021 NM Commercial & Residential Building Code) — per San Juan County Building Division's Design Criteria and Commercial Buildings Permit Application (revised 07/31/2023), which governs construction within the City of Bloomfield under the County's building-permit administration.; 2021 New Mexico Residential Building Code (2021 IRC as amended) — per San Juan County Building Division's New Residential Permit Application Checklist (revised 07/19/2023).; 2021 International Building Code; 2021 New Mexico Existing Building Code (2021 International Existing Building Code as amended); 2021 New Mexico Commercial and Residential Energy Conservation Code (2021 IECC as amended); ICC/ANSI A117.1-2017 Accessible and Usable Buildings and Facilities; 2021 New Mexico Plumbing and Mechanical Code; 2021 Uniform Mechanical Code; 2021 Uniform Plumbing Code; 2021 International Fire Code; 2020 National Electrical Code (NFPA 70) / 2020 New Mexico Electrical Code; 2012 Uniform Solar Energy Code; 2012 Uniform Swimming Pool, Spa and Hot Tub Code; 2017 NFPA 58 (Liquefied Petroleum Gas Code); 2018 NFPA 54 (National Fuel Gas Code). Local amendments apply — see the Bloomfield overview page for the full list.

San Juan County's Building Division issues and inspects the building permit for structures within Bloomfield city limits, under the County's cross-jurisdictional building program covering Aztec, Bloomfield, and Kirtland. Bloomfield's own Planning and Zoning Department separately requires its own Building and Zoning Compliance Application ($25) to verify zoning, setbacks, and address — both are needed.