Inspection sequence, scheduling, and re-inspection fees for building permits in Bloomfield, New Mexico.

Verified 2026-07-18 · Source

How to schedule

Inspections are requested through the building department below.

Address
City of Bloomfield Planning and Zoning: 915 N. 1st Street, P.O. Box 1839, Bloomfield, NM 87413. San Juan County Building Division: 100 South Oliver Drive, Aztec, NM 87410.
Phone
(505) 632-6304 (Bloomfield Planning & Zoning Director Crystal Martinez); (505) 632-6300 (City of Bloomfield main line); (505) 334-4313 (San Juan County Building Division, for building/electrical/plumbing/mechanical permits and inspections)
Office hours
City of Bloomfield Planning & Zoning: Monday–Thursday 7:00 am–5:30 pm; Friday closed. San Juan County Building Division: reachable at (505) 334-4313; all inspections must be requested at least 24 hours in advance (commercial and residential building permit applications both state 'a minimum of 24 hours is required for an inspection notification').

Published scheduling rules

  • Inspections must be requested at least 24 hours in advance by calling the San Juan County Building Division at (505) 334-4313. (New Residential Building Permit (New Construction / Addition / Accessory Building))

Inspection sequence

Applies to: New Residential Building Permit (New Construction / Addition / Accessory Building)

  1. 1

    Footing

    Forms and rebar in place prior to placement of concrete.

  2. 2

    Foundation Wall / Monolithic Slab

    Concrete block, ICF block, or concrete forms with reinforcement in place prior to placement of concrete.

  3. 3

    Electrical Under Slab

    Raceway runs prior to covering trench.

  4. 4

    Plumbing Under Slab

    DWV with test prior to covering trench; in-floor heat with air test.

  5. 5

    Slab on Grade

    After electrical and plumbing under-slab inspections, prior to placement of concrete.

  6. 6

    Rough Electrical

    Electric service, feeders, and branch circuits complete to termination.

  7. 7

    Rough Plumbing

    DWV top-out through roof with test, gas piping with test, water piping with test.

  8. 8

    Rough Heating and Ventilation

    Appliance vents through roof, trunk line and taps installed, combustion air provided, exhaust ducts complete.

  9. 9

    Framing

    After rough electrical, plumbing, and mechanical are complete and approved; windows in place; foundation and roof vents installed; air barrier requirements complete.

  10. 10

    Insulation

    Exterior walls complete; ceiling complete if batted.

  11. 11

    Electrical Final

    Panel board labeled, cover plate on, switches/outlets connected, fixtures in place.

  12. 12

    Plumbing Final

    Fixtures in place, water supply functional, gas appliances installed and connected.

  13. 13

    Mechanical Final

    Gas appliances connected and operational, vent terminations complete, grills in place, cooling units functional.

  14. 14

    Building Final

    Last inspection prior to occupancy approval; a Certificate of Occupancy is required before use or occupancy.

Applies to: Commercial Building Permit (New Construction / Addition / Alteration)

  1. 1

    Footing

    Forms and rebar in place prior to placement of concrete.

  2. 2

    Foundation Wall / Monolithic Slab

    Reinforcement in place prior to placement of concrete.

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Rough-in trades complete to termination, with required tests.

  4. 4

    Framing

    After rough-in trades are complete and approved.

  5. 5

    Fire Department Inspection

    Applicable to commercial construction only.

  6. 6

    Building Final

    Last inspection prior to occupancy approval; a Certificate of Occupancy is required.

Applies to: Electrical Permit

  1. 1

    Electrical Under Slab

    Raceway runs prior to covering trench (new construction).

  2. 2

    Rough Electrical

    Service, feeders, and branch circuits complete to termination.

  3. 3

    Electrical Final

    Panel board labeled, cover plate on, switches/outlets connected, fixtures in place.

Applies to: Plumbing Permit

  1. 1

    Plumbing Under Slab

    DWV with test prior to covering trench; in-floor heat with air test.

  2. 2

    Rough Plumbing

    DWV top-out through roof with test, gas piping with test, water piping with test.

  3. 3

    Plumbing Final

    Fixtures in place, water supply functional, gas appliances installed and connected.

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Fire Protection System Inspection

    San Juan County Fire Department/Fire Marshal's Office inspection of the installed sprinkler, alarm, extinguishing, standpipe, or cooking-hood system for code compliance; billed per the Inspection Fees table by square footage, with the initial inspection including one re-inspection.

  2. 2

    Fire Department Inspection (new commercial construction)

    Where the fire-protection system is installed as part of new commercial construction, this coincides with the Fire Department Inspection step already documented in this file's commercial-building-permit inspection sequence.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Heating and Ventilation

    Appliance vents through roof, trunk line and taps installed, combustion air provided, exhaust ducts complete.

  2. 2

    Mechanical Final

    Gas appliances connected and operational, vent terminations complete, return/supply grills in place, cooling units functional.

Re-inspection fees

Electrical PermitReinspection Fee · San Juan County Electrical Permit Application, revised 04/11/2023.
$75.00
Plumbing PermitReinspection Fee · San Juan County Plumbing Permit Application, revised 04/11/2023.
$75.00
Mechanical / HVAC PermitReinspection Fee · San Juan County Mechanical Permit Application, revised 04/11/2023.
$75.00
Fire Sprinkler & Fire Alarm System PermitRe-Inspection Fee · San Juan County Fire Department Inspection Pricing List — the initial inspection includes one re-inspection.
$75.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-18.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bloomfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Bloomfield building permits

Get alerts for Bloomfield

We'll email you when Bloomfield's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.