Solar PV Permit — Bloomfield, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.sjcounty.net/home/showpublisheddocument/6349/638187078672500000
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Bloomfield, New Mexico
Required for installation of rooftop or ground-mounted solar photovoltaic systems in Bloomfield. The City has no local building-inspection staff and contracts with the San Juan County Building Division for plan review and inspections; San Juan County's Electrical Permit Application explicitly lists 'Solar PV System' as its own fee category (per-kW rate), while the structural/racking portion is billed under the County's standard valuation-based Building Permit Fee, plus the City's own $25 Building and Zoning Compliance Application fee.
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit required for the PV system itself — San Juan County's Electrical Permit Application (revised 04/11/2023) explicitly lists 'Solar PV Systems' among the work types requiring a permit, billed at a dedicated per-kW rate
- Building Permit required for the structural/racking portion, billed at project valuation × 0.005 (San Juan County Building Department)
- Building Plan Review Fee (valuation × 0.0012) applies if the installation requires an Architect or Engineer seal under NMAC 14.5.2.9/14.5.2.10
- City of Bloomfield Building and Zoning Compliance Application ($25.00) required as the City's own administrative step, per the 2022 Planning & Zoning Fees schedule
- Must comply with the 2020 New Mexico Electrical Code (2020 NEC as amended); New Mexico's homeowner permit exemption (14.5.2 NMAC) applies to the owner's own primary residence
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Bloomfield inspection guide — scheduling & re-inspection fees →
Tips
- Bloomfield is one of the few jurisdictions in this corpus with a genuinely dedicated, per-kW solar PV fee line ($25/kW up to 160kW, then $5/kW) rather than billing solar under a generic amperage or valuation table — confirm the system's kW rating (DC or AC, per the County's form) before budgeting.
- Three separate fees apply: the County's per-kW Solar PV electrical fee, the County's valuation-based Building Permit fee for racking/structural work, and the City's own flat $25 Building and Zoning Compliance Application fee.
- Bloomfield has no local building department — all substantive plan review and inspection is done by the San Juan County Building Division, the same office that serves neighboring Aztec.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bloomfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bloomfield
Solar PV Permit in other cities
Compare solar pv permit fees across New Mexico →
Look up this fee in a different city →