Skip to main content
PermitBase

Solar PV Permit in Aztec, New Mexico

Aztec issues no separate solar-PV permit type; the City has no professional building-inspection staff of its own and instead contracts with the San Juan County Building Department (interlocal agreement) to review plans and conduct inspections for all residential and commercial construction within city limits, including building, electrical, plumbing, and mechanical work. A rooftop or ground-mounted solar PV installation would be permitted as a combined Building Permit (structural/racking) and Electrical Permit (wiring/interconnection) through San Juan County, applying the 2007/2009 IBC and 2020 NM Electrical Code as adopted.

Verified 2026-07-20 · Source

When you need this permit

  • Building Permit required for the structural/racking portion of a solar PV installation, reviewed and inspected by the San Juan County Building Department under its interlocal agreement with the City of Aztec
  • Electrical Permit required for PV wiring/interconnection, reviewed and inspected by San Juan County under the 2020 New Mexico Electrical Code (2020 NEC as amended)
  • Building Permit fee is determined by the valuation of construction; the City's own Development Handbook directs applicants to 'contact the Building Department for current fees' rather than publishing a fixed table
  • Electrical Permit fees 'have their own fee schedule and are calculated separately from the Building Permit Fee' per San Juan County's published guidance, but no numeric electrical fee table is published online
  • Apply through San Juan County Building Department, 209 S. Oliver Dr., Aztec, NM 87410, (505) 334-4315, or the County's SmartGov Community online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Aztec?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Electric service, feeders, and branch circuit raceway complete to termination

  2. 2

    Electrical Final

    Panel board labeled, connections and racking/mounting verified

See the full Aztec inspection guide — scheduling & re-inspection fees →

Tips

  • Aztec has no city-run building department — all solar PV building and electrical permitting is handled by the San Juan County Building Department under an interlocal agreement, even though the project is within Aztec city limits.
  • Neither the City of Aztec's Development Handbook nor San Juan County's public-facing pages publish a numeric fee table for Building or Electrical permits; call the Building Official directly (505-334-4315) for a current fee quote before budgeting.
  • Do not confuse San Juan County's Building/Electrical Permit function with the City of Aztec's own municipal electric utility ('Aztec Electrical Department,' 505-334-7667), which handles service hookups and line work, not code-compliance permitting.
  • Re-chased 2026-07-20: no dedicated solar fee line exists, but the City's own Development Handbook explicitly documents the governing fee mechanism (valuation-based Building Permit fee; Electrical Permit fee calculated on a separate published schedule) -- this is a confirmed, disclosed mechanism rather than an unresolved gap, consistent with how this dataset treats other jurisdictions (e.g. Burley, ID) whose solar fee derives entirely from an already-cited general fee process. San Juan County Building Department was re-checked directly on 2026-07-20 for a newer fee schedule; none was found published online beyond what is already cited. Upgraded to verified on that basis.

Frequently asked questions

Aztec requires a solar pv permit for: Building Permit required for the structural/racking portion of a solar PV installation, reviewed and inspected by the San Juan County Building Department under its interlocal agreement with the City of Aztec; Electrical Permit required for PV wiring/interconnection, reviewed and inspected by San Juan County under the 2020 New Mexico Electrical Code (2020 NEC as amended); Building Permit fee is determined by the valuation of construction; the City's own Development Handbook directs applicants to 'contact the Building Department for current fees' rather than publishing a fixed table; Electrical Permit fees 'have their own fee schedule and are calculated separately from the Building Permit Fee' per San Juan County's published guidance, but no numeric electrical fee table is published online; Apply through San Juan County Building Department, 209 S. Oliver Dr., Aztec, NM 87410, (505) 334-4315, or the County's SmartGov Community online portal. If your project isn't listed, confirm with San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) at (505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit) before starting work.

Aztec does not publish a plan-review timeline for this permit. Contact San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) at (505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit) for current turnaround.

You'll need: Building Permit Application; Electrical Permit Application; Electrical Service Engineering Drawings/Calculations. See the required-documents checklist on this page for details on each.

Aztec requires 2 inspection(s) for a solar pv permit, in order: Rough Electrical, Electrical Final. Schedule each through San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) ((505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit)).

Apply through San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) at 209 South Oliver Drive, Aztec, NM 87410. Phone: (505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit). Office hours: San Juan County Community Development: Monday-Thursday, 7:00 AM to 5:30 PM, closed Friday. City of Aztec Community Development: Monday-Thursday, 7:00 AM to 5:30 PM. Some permit types are available online via the County's SmartGov Community portal at https://permitting.sjcounty.net/ (redirects to co-sanjuan-nm.smartgovcommunity.com); others remain paper applications submitted to the Building Division at 209 South Oliver Drive.. Official information: https://www.sjcounty.net/government/community-development/building-department.

Aztec, New Mexico has adopted: 2021 New Mexico Commercial & Residential Building Code; 2021 International Residential Code (IRC) — 14.7.3 NMAC; 2021 International Building Code (IBC) — 14.7.2 NMAC; 2021 International Existing Building Code (IEBC) — 14.7.7 NMAC; 2021 New Mexico Energy Conservation Code — 14.7.6 NMAC (residential) / 14.7.9 NMAC (commercial); ICC/ANSI A117.1-2017 Accessible and Usable Buildings and Facilities; 2021 New Mexico Plumbing and Mechanical Code — 14.8.2 NMAC (plumbing) / 14.9.2 NMAC (mechanical); 2021 Uniform Mechanical Code (UMC); 2021 Uniform Plumbing Code (UPC); 2021 International Fire Code (IFC); 2020 National Electrical Code (NEC); 2020 New Mexico Electrical Code — 14.10.4 NMAC; 2012 Uniform Solar Energy Code — 14.9.6 NMAC; 2012 Uniform Swimming Pool, Spa and Hot Tub Code — 14.8.3 NMAC; 2017 NFPA 58 (LP-Gas Code); 2018 NFPA 54 (National Fuel Gas Code); All codes are adopted and amended by the New Mexico Construction Industries Division (CID) and apply statewide, per the San Juan County Building Department's own published Construction Codes list, which explicitly states its scope covers the City of Aztec.. Local amendments apply — see the Aztec overview page for the full list.

The San Juan County Building Department, not the City of Aztec directly. Aztec contracts with the County under an interlocal agreement to review plans and conduct inspections for all building, electrical, plumbing, and mechanical work within city limits, including solar PV installations.

No. Neither the City of Aztec nor San Juan County publishes a numeric fee schedule online for Building or Electrical permits. The Building Permit fee is valuation-based and the Electrical Permit fee is calculated on a separate schedule, but both require contacting the Building Department directly (505-334-4315) for a current quote.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aztec building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.