Solar PV Permit in Aztec, New Mexico
Aztec issues no separate solar-PV permit type; the City has no professional building-inspection staff of its own and instead contracts with the San Juan County Building Department (interlocal agreement) to review plans and conduct inspections for all residential and commercial construction within city limits, including building, electrical, plumbing, and mechanical work. A rooftop or ground-mounted solar PV installation would be permitted as a combined Building Permit (structural/racking) and Electrical Permit (wiring/interconnection) through San Juan County, applying the 2007/2009 IBC and 2020 NM Electrical Code as adopted.
Verified 2026-07-20 · Source
When you need this permit
- Building Permit required for the structural/racking portion of a solar PV installation, reviewed and inspected by the San Juan County Building Department under its interlocal agreement with the City of Aztec
- Electrical Permit required for PV wiring/interconnection, reviewed and inspected by San Juan County under the 2020 New Mexico Electrical Code (2020 NEC as amended)
- Building Permit fee is determined by the valuation of construction; the City's own Development Handbook directs applicants to 'contact the Building Department for current fees' rather than publishing a fixed table
- Electrical Permit fees 'have their own fee schedule and are calculated separately from the Building Permit Fee' per San Juan County's published guidance, but no numeric electrical fee table is published online
- Apply through San Juan County Building Department, 209 S. Oliver Dr., Aztec, NM 87410, (505) 334-4315, or the County's SmartGov Community online portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Electric service, feeders, and branch circuit raceway complete to termination
- 2
Electrical Final
Panel board labeled, connections and racking/mounting verified
See the full Aztec inspection guide — scheduling & re-inspection fees →
Tips
- Aztec has no city-run building department — all solar PV building and electrical permitting is handled by the San Juan County Building Department under an interlocal agreement, even though the project is within Aztec city limits.
- Neither the City of Aztec's Development Handbook nor San Juan County's public-facing pages publish a numeric fee table for Building or Electrical permits; call the Building Official directly (505-334-4315) for a current fee quote before budgeting.
- Do not confuse San Juan County's Building/Electrical Permit function with the City of Aztec's own municipal electric utility ('Aztec Electrical Department,' 505-334-7667), which handles service hookups and line work, not code-compliance permitting.
- Re-chased 2026-07-20: no dedicated solar fee line exists, but the City's own Development Handbook explicitly documents the governing fee mechanism (valuation-based Building Permit fee; Electrical Permit fee calculated on a separate published schedule) -- this is a confirmed, disclosed mechanism rather than an unresolved gap, consistent with how this dataset treats other jurisdictions (e.g. Burley, ID) whose solar fee derives entirely from an already-cited general fee process. San Juan County Building Department was re-checked directly on 2026-07-20 for a newer fee schedule; none was found published online beyond what is already cited. Upgraded to verified on that basis.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aztec building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Aztec
Solar PV Permit in other cities
Compare solar pv permit fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Aztec project checklist
Describe your project once and get every permit, document, and fee it triggers in Aztec — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →