Electrical Permit in Aztec, New Mexico

Required for electrical wiring, service changes, and installations within Aztec city limits, reviewed and inspected by the San Juan County Building Department under the interlocal agreement covering the City of Aztec, applying the 2020 New Mexico Electrical Code (2020 NEC as amended).

Verified 2026-07-18 · Source

When you need this permit

  • Electrical installation, alteration, or repair work within Aztec city limits
  • Must comply with the 2020 New Mexico Electrical Code (2020 NEC as amended) — 14.10.4 NMAC
  • Electrical Service Engineering Drawings/Calculations required for service work, per the Building Department's published Electrical Permit form list
  • New Mexico's homeowner permit exemption applies to the owner's own principal residence

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Aztec?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Under Slab

    Raceway runs prior to covering trench (for slab construction).

  2. 2

    Rough Electrical

    Electric service, feeders, and branch circuit raceway complete to termination.

  3. 3

    Electrical Final

    Panel board labeled, cover plate on, switches and outlets connected, fixtures in place.

See the full Aztec inspection guide — scheduling & re-inspection fees →

Tips

  • Do not confuse the County's Electrical PERMIT (wiring code compliance, (505) 334-4313) with the City's own 'Aztec Electrical Department' municipal electric utility ((505) 334-7667), which handles service hookups/line work, not permitting.
  • Landowners outside Aztec city limits must instead apply for electric service through the City of Farmington Electric Department, per the County's own Permit and Contact Information sheet — confirm which utility serves your property before applying.

Frequently asked questions

Aztec requires an electrical permit for: Electrical installation, alteration, or repair work within Aztec city limits; Must comply with the 2020 New Mexico Electrical Code (2020 NEC as amended) — 14.10.4 NMAC; Electrical Service Engineering Drawings/Calculations required for service work, per the Building Department's published Electrical Permit form list; New Mexico's homeowner permit exemption applies to the owner's own principal residence. If your project isn't listed, confirm with San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) at (505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit) before starting work.

Aztec does not publish a plan-review timeline for this permit. Contact San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) at (505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit) for current turnaround.

You'll need: Electrical Permit Application; Electrical Service Engineering Drawings Required / Calcs. See the required-documents checklist on this page for details on each.

Aztec requires 3 inspection(s) for an electrical permit, in order: Electrical Under Slab, Rough Electrical, Electrical Final. Schedule each through San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) ((505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit)).

Apply through San Juan County Building Department (administers building permits, plan review, and inspections for the City of Aztec under an interlocal service agreement; the City of Aztec Community Development Department separately issues its own required Land Use Permit) at 209 South Oliver Drive, Aztec, NM 87410. Phone: (505) 334-4313 (Building Division, permit/inspection scheduling); (505) 334-4550 (San Juan County Community Development main line); (505) 334-7605 (City of Aztec Community Development / Planning & Zoning, for the City's own Land Use Permit). Office hours: San Juan County Community Development: Monday-Thursday, 7:00 AM to 5:30 PM, closed Friday. City of Aztec Community Development: Monday-Thursday, 7:00 AM to 5:30 PM. Some permit types are available online via the County's SmartGov Community portal at https://permitting.sjcounty.net/ (redirects to co-sanjuan-nm.smartgovcommunity.com); others remain paper applications submitted to the Building Division at 209 South Oliver Drive.. Official information: https://www.sjcounty.net/government/community-development/building-department.

Aztec, New Mexico has adopted: 2021 New Mexico Commercial & Residential Building Code; 2021 International Residential Code (IRC) — 14.7.3 NMAC; 2021 International Building Code (IBC) — 14.7.2 NMAC; 2021 International Existing Building Code (IEBC) — 14.7.7 NMAC; 2021 New Mexico Energy Conservation Code — 14.7.6 NMAC (residential) / 14.7.9 NMAC (commercial); ICC/ANSI A117.1-2017 Accessible and Usable Buildings and Facilities; 2021 New Mexico Plumbing and Mechanical Code — 14.8.2 NMAC (plumbing) / 14.9.2 NMAC (mechanical); 2021 Uniform Mechanical Code (UMC); 2021 Uniform Plumbing Code (UPC); 2021 International Fire Code (IFC); 2020 National Electrical Code (NEC); 2020 New Mexico Electrical Code — 14.10.4 NMAC; 2012 Uniform Solar Energy Code — 14.9.6 NMAC; 2012 Uniform Swimming Pool, Spa and Hot Tub Code — 14.8.3 NMAC; 2017 NFPA 58 (LP-Gas Code); 2018 NFPA 54 (National Fuel Gas Code); All codes are adopted and amended by the New Mexico Construction Industries Division (CID) and apply statewide, per the San Juan County Building Department's own published Construction Codes list, which explicitly states its scope covers the City of Aztec.. Local amendments apply — see the Aztec overview page for the full list.

The 2020 New Mexico Electrical Code, based on the 2020 National Electrical Code (NEC), as adopted statewide by the New Mexico Construction Industries Division and enforced in Aztec by the San Juan County Building Department.

Sources & verification

Verified against official sources. Last reviewed 2026-07-18.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aztec building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.