City of Aztec Land Use Permit — Aztec, New Mexico · Requirements sheet
Verified 2026-07-18 · Source: https://www.aztecnm.gov/communitydevelopment.html
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
City of Aztec Land Use Permit in Aztec, New Mexico
A City of Aztec-issued Planning Permit required in parallel with the San Juan County-issued Building Permit for new dwellings and commercial development within city limits. It governs allowable land use, setbacks, lot coverage, and site-plan compliance under the City's own Municipal Code (Chapters 9, 18, and 26), and is administered entirely by the City's Community Development Department — genuinely distinct from the County-administered structural Building Permit.
Verified 2026-07-18 · Source
When you need this permit
- Required for construction, alteration, moving, or demolition of buildings, including expansions, garages, carports, or other add-ons, within Aztec city limits
- Not required for repairs to a building's exterior (including re-roofing) or interior remodeling that doesn't otherwise trigger a building permit, per the City's Development Handbook
- All applications require a site plan
- The Building Department requires a copy of the City's Land Use/Planning Permit to be submitted with the County building-permit application, to coordinate review order
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Aztec inspection guide — scheduling & re-inspection fees →
Tips
- Impact fees ($500 per new residential unit) are collected by the City at Land Use Permit issuance — a separate line item from both the $25/$50/$100 Land Use Permit fee itself and the County's Building Permit Fee.
- The City's Land Use Permit and the County's Building Permit are reviewed by two separate offices — the County Building Department requires a copy of the City's Land Use Permit to be submitted with the building-permit application to keep the two processes coordinated.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-18.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aztec building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Aztec
Compare city of aztec land use permit fees across New Mexico →
Look up this fee in a different city →